Plan Review Notes For Permit 06110181 |
Permit Number |
06110181 |
|
Review Stop |
B |
Sequence Number |
1 |
|
Notes |
Date |
Text |
2007-01-11 18:23:17 | DENIED BY BUILDING | | | | 1) THE ENGINEERING FOR THE METAL FENCE IS REQUIRED TO | | BE SIGNED,SEALED AND DATED BY THE ENGINEER PER FS | | 471. | | | | 2) TWO DIFFERENT ENGINEERED DRAWINGS WERE SUBMITTED. | | | | 3) THE NOC WILL NEED TO BE RE-RECORDED. FS 713.13 | | REQUIRES THE WORK TO COMMENCE WITHIN 90 DAYS AFTER THE | | RECORDING DATE. | | | | ROBERT MCDOUGAL | | BLDG. PLAN REVIEW | | (561)805-6714 | | |
|