2007-08-16 13:37:34 | FAILED FOR FOLLOWING REASONS: |
| |
| WE HAVE A NEW FOLLOWING REQUIREMENTS, PLEASE RESPOND |
| THIS TOO. |
| |
| 1. PLEASE PROVIDE A COPY OF NOTICE OF INTENT (NOI). |
| PLEASE APPLY AT FDEP, NPDES STORMWATER SECTION FOR |
| NOI. |
| YOU CAN GET NOI INFO FROM |
| WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/ |
| NOTICE OF INTENT DEP FORM 62-621.300(4)(B), |
| EFFECTIVE MAY 1, 2003 |
| THIS IS KIND OF A NEW REQUIREMENTS. YOU MAY HAVE |
| ALREADY APPLIED FOR NOI. JUST SEND US A COPY NOITHAT |
| YOU APPLY AT FDEP, NPDES STORM WATER SECTION,. |
| |
| 2. PLEASE SHOW ON DRAWINGSDUMPSTER & ITS ENCLOSURE |
| DETAILS PER CITY OF WPB, &LOCATION ON DWG, LOCATION |
| MUST BE ACCESSIBLE FOR PICKUP TRUCK. |
| 3. PLEASE SHOW ON CALCULATION HOW DID YOU DETERMINE |
| FIRST FLOOR ELEVATION, CENTER LINE OF ROAD ELEVATION , |
| SIDEWALK ELEVATION. YOU ALSOMUST MEET FLOOD ZONE OF |
| THAT AREA, FL BLDG CODE. PLEASE SHOW ON CALS WHAT |
| CRITERIA YOU USED IN DETERMINING FIRST FLOOR ELEVATION |
| LIKE 5 YEAR,10 YEAR, 25 YEAR, 100 YEAR FLOOD, PLEASE |
| SHOW ALL THESE IN CALCULATIONS,YOU NEED TO USE THE |
| WORST CASE TO GET SAFER DESIGN FOR FIRST FLOOR |
| ELEVATION. THEN SHOW THE RESULT FROM CALCULATIONS THAT |
| FIRST FLOOR ELEVATION IS HIGH ENOUGH. |
| 4. PLEASE PROVIDE A COPY OF SFWMD PERMIT, & RESUBMIT |
| GEOTECH REPORT AGAIN. |
| 5.IN YOUR STORM WATER QUALITY CALCULATIONS, YOU DID NOT |
| USE THE WORST CASE FOR SAFER DESIGN, 2.5" CRITERIA, |
| YOU SAID" PER CARLOSDEROJA ONLY 1" RUNOFF..." |
| WELL,YOU NEED TO PROVIDE A LETTER FROM CARLOS FOR |
| THAT REASONOTHERWISEYOU NEED TO USE 2.5" CRITERIA |
| FOR WATER QUALITY CALS. |
| 6.HOW DIDYOU CONNECT TO THE STORM WATER PIPES IN YOUR |
| SITE? ITS DETAILS.PLEASE SHOW ALL STORM WATER PIPES |
| AROUND YOUR SITE SO, WE CANSEE THE BEST STORM WATER |
| PIPE TO CONNECT WITH THE STORM WATERFROM ALL OTHER |
| STORM WATER PIPES. PLEASE SHOW DETAIL OF THE CONTROL |
| STRUCTURES WITH ELEVATIONS, NOTCHES, BLEEDING |
| ELEVATION, ETC DID YOU USE EXFILTRATION TRENCH ? |
| 7.POLLUTION PREVENTION: YOUR PLANS SHOW SILT FENCE |
| PARTIALLY AT SOME LOCATIONS NOTAROUND THE WHOLE SITE. |
| SILT FENCE MUST BE COMPLETELY AROUND THE SITE. |
| 8. WATER & SEWER PLANS MUST BE APPROVED FROM 45TH |
| STREET (MANNY G.), UTILITY DEPT BEFORE WE APPROVE |
| 9. ALSO PLEASE SHOW ALL CATCH BASINS NEAREST,AROUND |
| YOUR SITE FOR STORM WATER DRAIN. |
| |
| PLEASE RESPOND EACH ITEM IN DETAIL TO EXPEDITE YOUR |
| PERMITTING PROCESS. |
| |
| RASIK CHOKSHI805-6723 |