Date |
Text |
2006-11-07 16:00:24 | DENIED: |
| RESPONSE TO COMMENTS FROM PREVIOUS REVIEW THAT WERE NOT |
| ADDRESSED: |
| |
| PLEASE NOTE, RESPONSE TO COMMENTS 1, 2 & 3 STATES |
| INFORMATION WILL BE PROVIDED WITH 100% DOCUMENTATION. |
| ****************************************************** |
| * |
| COMMENT 1:REQUEST FOR ENERGY & SIZING CALCULATIONS IN |
| ACCORDANCE WITH 2004 FBC CHAPTER 13 SUB-CHAPTER 13-4. |
| |
| RESPONSE INDICATES CALCS WILL BE PROVIDED WITH 100% |
| DOCUMENTS. |
| |
| COMMENT 2:REQUEST FOR INFORMATION IN RELATION TO THE |
| FUEL TANK & DIESEL FIRE PUMPS |
| A) VENTILATION FOR THE ROOM (EXHAUST FANS WERE |
| INDICATED WITH NO VENTILATION CALCS).PLEASE REFERENCE |
| 2004 FMC 502.1.2 THROUGH 502.1.4 & NFPA 37-6.3.5.4 |
| THROUGH 6.3.5.4.3. |
| |
| B) DISTANCE TO PROPERTY LINES WITH RELATION TO THE |
| TERMINATION OF EXHAUST. |
| |
| C) CAPACITY OF THE FUEL TANKS.THE SUBMITTAL BOOK |
| INDICATES (1) 100 GAL, (1) 150 GAL, & (1) 500 GAL |
| SUB-BASE FUEL TANK.PLANS DO NOT CORRELATE WITH |
| SUBMITTAL BOOK. SUBMITTAL BOOK INDICATES 500 GAL |
| SUB-BASE FUEL TANK, PLAN SHEET P3-4.0 DETAIL 03 SHOWS |
| THE 500 GAL TANK AT THE GROUND LEVEL WITH A DAY TANK ON |
| THE ROOF.PLAN SHEET P1-6.0 INDICATES THE GENERATOR |
| AS "NATURAL GAS". PLEASE CLARIFY.PLEASE ALSO NOTE, |
| PLAN SHEET P-3.40 PROVIDES A SCHEMATIC FOR THE DIESEL |
| FUEL PIPING, SUPPLY, RETURN, & VENT PIPING SHOWN ON |
| SHEETS P1-1.0, P1-2.0, P1-3.0, P1-4.0, P1-5.0 & P1-6.0. |
| DIESEL FUEL SUPPLY AND RETURN PIPING ARE NOT DEPICTED |
| ON PLAN SHEET P1-6.0 ONLY THE VENT PIPING.PLAN SHEE |
| P1-6.0 SHOWS THE NATURAL GAS SUPPLYING FUEL TO THE |
| GENERATOR.THIS DOES NOT CORRELATE WITH THE SUBMITTAL |
| BOOK.PLEASE NOTE, PER NFPA 37-6.3.5.3 ROOMS HOUSING |
| FUEL TANKS WITH AN AGGREGATE CAPACITY LESS THAN 1320 |
| GAL, EACH TANK ROOM SHALL BE PROVIDED WITH SPILL |
| CONTAINMENT CONSISTING OF EITHER A WALL, CURB, OR DIKE |
| HAVING A CAPACITY AT LEAST EQUAL TO THAT OF THE LARGEST |
| TANK.FUEL TANKS LOCATED ON THE ROOF SHALL COMPLY |
| WITH NFPA 37-6.3.4 THROUGH 6.3.4.2. |
| |
| COMMENTS 10 & 11 NO RESPONSE WAS GIVEN. |
| |
| COMMENT 3 & 15:FIRE & FIRE/SMOKE DAMERS AT SHAFT |
| PENETRATIONS.PLEASE INDICATE DAMPERS ON THE RISERS AS |
| REQUESTED IN PREVIOUS REVIEW. |
| |
| COMMENT 9:PLAN SHEET M1-1.3 PROVIDE ELEVATION OF THE |
| MAKE -UP AIR AND EXHAUST FROM MECHANICAL ROOM B1.102 |
| THE REPONSE SENTENCE WAS NOT COMPLETE AND DID NOT |
| PROVIDE ELEVATION. |
| |
| COMMENTS 10 & 11 NO RESPONSE WAS GIVEN. |
| |
| COMMENT 12:THE EQUIPMENT SCHEDULE WAS PROVIDED BUT |
| THE CHILLER SCHEDULE ON SHEET M3-2.0 ANNOTATES ALL |
| CHILLERS AS CH-1 NOT CH-1, CH-2, CH-3 |
| |
| |
| NEW COMMENTS: |
| 13.PLEASE PROVIDE SEQUENCE OF OPERATION FOR THE SMOKE |
| CONTROL OR EVAC IN ACCORDANCE WITH 2004 FMC 513 OR |
| CHAPTER 909 OF THE FBC. |
| |
| 14.PLEASE PROVIDE VENTILATION CALCS FOR THE GARAGE |
| PER 2004 FMC 404. |
| |
| 15.PLEASE INDICATE THE VOLUME OF THE ATRIUM. |
| |
| 16.PLAN SHEET M1-1.1, FIRE DAMPERS ARE MISSING FROM |
| ELECTRICAL ROOM A1.102.PLEASE VERIFY FIRE DAMPERS, |
| FOR ALL ELECTRICAL, MECHANICAL AND STORAGE ROOMS. |
| |
| 17.PLAN SHEET M1-2.2, SUPPLY/RETURN TO AHU-2 & |
| EXHAUST DUCT (EF-4), SHAFT IS NOT LARGE ENOUGH TO |
| ENCLOSE THESE DUCTS.PLEASE NOTE, DUCTS SHALL HAVE |
| SUFFICIENT CLEARANCE FOR INSTALLATION & INSPECTION PER |
| 2004 FMC 603.1.3. |
| |
| 18.PLEASE PROVIDE ANCHORING DETAIL FOR INSTALLATION |
| OF THE COOLING TOWERS PER 2004 FBC 106.1.1.2 , 1509.4 & |
| 1509.7. |
| |
| 19.PROVIDE DETAIL FOR ANCHORING & VIBRATION ISOLATION |
| ON ALL MOUNTED EQUIPMENT. |
| |
| 20.PLAN SHEET M5-3.0 DETAIL 6 SHOWS 1" INSULATION ON |
| THE 4"CHILLED WATER PIPING.WILL THE INSULATION |
| INCREASE TO 2" ON THE LARGER PIPING? |
| |
| IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT PATTY KRAUSS |
| AT (561)805-6719 OR E-MAIL [email protected]. |
| |