Plan Review Notes For Permit 06100574
Permit Number 06100574
Review Stop M
Sequence Number 1
Notes
Date Text
2006-11-07 16:00:24DENIED:
 RESPONSE TO COMMENTS FROM PREVIOUS REVIEW THAT WERE NOT
 ADDRESSED:
  
 PLEASE NOTE, RESPONSE TO COMMENTS 1, 2 & 3 STATES
 INFORMATION WILL BE PROVIDED WITH 100% DOCUMENTATION.
 ******************************************************
 *
 COMMENT 1:REQUEST FOR ENERGY & SIZING CALCULATIONS IN
 ACCORDANCE WITH 2004 FBC CHAPTER 13 SUB-CHAPTER 13-4.
  
 RESPONSE INDICATES CALCS WILL BE PROVIDED WITH 100%
 DOCUMENTS.
  
 COMMENT 2:REQUEST FOR INFORMATION IN RELATION TO THE
 FUEL TANK & DIESEL FIRE PUMPS
 A) VENTILATION FOR THE ROOM (EXHAUST FANS WERE
 INDICATED WITH NO VENTILATION CALCS).PLEASE REFERENCE
 2004 FMC 502.1.2 THROUGH 502.1.4 & NFPA 37-6.3.5.4
 THROUGH 6.3.5.4.3.
  
 B) DISTANCE TO PROPERTY LINES WITH RELATION TO THE
 TERMINATION OF EXHAUST.
  
 C) CAPACITY OF THE FUEL TANKS.THE SUBMITTAL BOOK
 INDICATES (1) 100 GAL, (1) 150 GAL, & (1) 500 GAL
 SUB-BASE FUEL TANK.PLANS DO NOT CORRELATE WITH
 SUBMITTAL BOOK. SUBMITTAL BOOK INDICATES 500 GAL
 SUB-BASE FUEL TANK, PLAN SHEET P3-4.0 DETAIL 03 SHOWS
 THE 500 GAL TANK AT THE GROUND LEVEL WITH A DAY TANK ON
 THE ROOF.PLAN SHEET P1-6.0 INDICATES THE GENERATOR
 AS "NATURAL GAS". PLEASE CLARIFY.PLEASE ALSO NOTE,
 PLAN SHEET P-3.40 PROVIDES A SCHEMATIC FOR THE DIESEL
 FUEL PIPING, SUPPLY, RETURN, & VENT PIPING SHOWN ON
 SHEETS P1-1.0, P1-2.0, P1-3.0, P1-4.0, P1-5.0 & P1-6.0.
 DIESEL FUEL SUPPLY AND RETURN PIPING ARE NOT DEPICTED
 ON PLAN SHEET P1-6.0 ONLY THE VENT PIPING.PLAN SHEE
 P1-6.0 SHOWS THE NATURAL GAS SUPPLYING FUEL TO THE
 GENERATOR.THIS DOES NOT CORRELATE WITH THE SUBMITTAL
 BOOK.PLEASE NOTE, PER NFPA 37-6.3.5.3 ROOMS HOUSING
 FUEL TANKS WITH AN AGGREGATE CAPACITY LESS THAN 1320
 GAL, EACH TANK ROOM SHALL BE PROVIDED WITH SPILL
 CONTAINMENT CONSISTING OF EITHER A WALL, CURB, OR DIKE
 HAVING A CAPACITY AT LEAST EQUAL TO THAT OF THE LARGEST
 TANK.FUEL TANKS LOCATED ON THE ROOF SHALL COMPLY
 WITH NFPA 37-6.3.4 THROUGH 6.3.4.2.
  
 COMMENTS 10 & 11 NO RESPONSE WAS GIVEN.
  
 COMMENT 3 & 15:FIRE & FIRE/SMOKE DAMERS AT SHAFT
 PENETRATIONS.PLEASE INDICATE DAMPERS ON THE RISERS AS
 REQUESTED IN PREVIOUS REVIEW.
  
 COMMENT 9:PLAN SHEET M1-1.3 PROVIDE ELEVATION OF THE
 MAKE -UP AIR AND EXHAUST FROM MECHANICAL ROOM B1.102
 THE REPONSE SENTENCE WAS NOT COMPLETE AND DID NOT
 PROVIDE ELEVATION.
  
 COMMENTS 10 & 11 NO RESPONSE WAS GIVEN.
  
 COMMENT 12:THE EQUIPMENT SCHEDULE WAS PROVIDED BUT
 THE CHILLER SCHEDULE ON SHEET M3-2.0 ANNOTATES ALL
 CHILLERS AS CH-1 NOT CH-1, CH-2, CH-3
  
  
 NEW COMMENTS:
 13.PLEASE PROVIDE SEQUENCE OF OPERATION FOR THE SMOKE
 CONTROL OR EVAC IN ACCORDANCE WITH 2004 FMC 513 OR
 CHAPTER 909 OF THE FBC.
  
 14.PLEASE PROVIDE VENTILATION CALCS FOR THE GARAGE
 PER 2004 FMC 404.
  
 15.PLEASE INDICATE THE VOLUME OF THE ATRIUM.
  
 16.PLAN SHEET M1-1.1, FIRE DAMPERS ARE MISSING FROM
 ELECTRICAL ROOM A1.102.PLEASE VERIFY FIRE DAMPERS,
 FOR ALL ELECTRICAL, MECHANICAL AND STORAGE ROOMS.
  
 17.PLAN SHEET M1-2.2, SUPPLY/RETURN TO AHU-2 &
 EXHAUST DUCT (EF-4), SHAFT IS NOT LARGE ENOUGH TO
 ENCLOSE THESE DUCTS.PLEASE NOTE, DUCTS SHALL HAVE
 SUFFICIENT CLEARANCE FOR INSTALLATION & INSPECTION PER
 2004 FMC 603.1.3.
  
 18.PLEASE PROVIDE ANCHORING DETAIL FOR INSTALLATION
 OF THE COOLING TOWERS PER 2004 FBC 106.1.1.2 , 1509.4 &
 1509.7.
  
 19.PROVIDE DETAIL FOR ANCHORING & VIBRATION ISOLATION
 ON ALL MOUNTED EQUIPMENT.
  
 20.PLAN SHEET M5-3.0 DETAIL 6 SHOWS 1" INSULATION ON
 THE 4"CHILLED WATER PIPING.WILL THE INSULATION
 INCREASE TO 2" ON THE LARGER PIPING?
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT PATTY KRAUSS
 AT (561)805-6719 OR E-MAIL [email protected].
  