Date |
Text |
2007-07-26 11:42:13 | DENIED 4TH TIME |
| REFERENCE: |
| ** FBC-2004 PLUMBING. |
| ** FBC-2004 CHAPTER 1, THE CITY OF |
| WEST PALM BEACH AMENDMENTS. |
| ** FLORIDA ADMINISTRATIVE CODE. |
| ** FLORIDA STATUTES. |
| |
| THE FOLLOWING CORRECTIONS/INFORMATION ARE REQUIRED FOR |
| PLUMBING PLAN REVIEW TO MEET CODE COMPLIANCE WITH THE |
| ADDITION OF BATH 4 AND CABANA BATH.: |
| |
| 1. SHEET A15 THE RESUBMITTED ISOMETRIC SANITARY RISER |
| DIAGRAM DOES NOT REFLECT THE FLOOR PLAN IN THE |
| FOLLOWING AREAS. PER FBC-2004 CHAPTER 1, SECTION |
| 106.1.1 CONSTRUCTION DOCUMENTS (ISOMETRIC) SHALL BE OF |
| SUFFICIENT CLARITY TO THE LOCATION OF THE PROPOSED |
| WORK. |
| |
| A. ALL OF THE GROUND FLOOR PLUMBING (1/2 BATH, |
| KITCHEN, AND CABANA BATH). PLEASE REFERENCE THE |
| CORRECTED ISOMETRIC GROUND FLOOR PLUMBING THAT REFLECTS |
| THE FLOOR PLAN ON THIS SHEET FOR THE RESUBMITTAL. |
| |
| B. 2ND FLOOR MASTER BATH DOES NOT INDICATE THE 1/8 |
| BEND OFFSETS OR WYE FITTINGS AND THE LAV BY SHOWER |
| BEING INDICATED IN THE WRONG PLACE. THE TRAP IS BEING |
| INDICATED AS GOING OUT THE BACK WALL. PLEASE INDICATE |
| THE WASTE ARM AND CORRECT LOCATION OF TRAP. |
| |
| C. 2ND FLOOR LAUNDRY: SINK IN LAUNDRY IS MISLABELED, |
| IT SHOULD BE INDICATED AS A LAUNDRY TRAY (L.T.). THE |
| LAUNDRY TRAY WASTE ARM IS BEING INDICATED IN THE WRONG |
| PLACE. |
| |
| D. 2ND FLOOR STUDY: THE SINK IS BEING INDICATED ON THE |
| WRONG SIDE OF THE 4" HORIZONTAL SANITARY PIPE. |
| |
| E. 2ND FLOOR BATH 2: THE LAV WASTE IS BEING INDICATED |
| IN THE WRONG PLACE. |
| |
| F. 2ND FLOOR BATH 3 AND 4: FLOOR PLAN ON SHEET A6 ARE |
| INDICATING A TUBS, BUT THE SANITARY ISOMETRIC ARE |
| INDICATING SHOWERS. PLEASE CLARIFY OR CORRECT THIS ON |
| THE RESUBMITTAL. |
| |
| 2. SHEET A15 PLUMBING NOTES: PLEASE DELETE THE |
| FOLLOWING "PROVIDE MINIMUM PITCH 1/4" AT ALL HORIZONTAL |
| BRANCHES AND SEWER LINES PER 701.01. PLEASE ADD IN ITS |
| PLACE THE FOLLOWING "SLOPE OF HORIZONTAL DRAIN PIPE PER |
| TABLE 704.1" ON THE RESUBMITTAL. |
| |
| 3. SHEET A15 SANITARY ISOMETRIC RISER PLEASE INDICATE |
| THE FOLLOWING. |
| |
| A. PER FBC-2004 PLUMBING SECTION, 708.3.4: CLEANOUT AT |
| THE BASE OF THE 4" SOIL STACK TO THE 2ND FLOOR. |
| |
| B. PER FBC-2004 PLUMBING SECTION, 708.3.5: PLEASE |
| INDICATE A TWO-WAY CLEANOUT AT THE JUNCTION OF THE |
| BUILDING DRAIN AND BUILDING SEWER. |
| |
| 4.SHEET A15 2ND FLOOR PLUMBING PLAN: PLEASE CORRECT |
| THE BRANCH DRAIN TO THE LAUNDRY TO THREE INCH (3") PER |
| FBC-2004 PLUMBING SECTION 406.3. |
| |
| ********IMPORTANT INFORMATION******** |
| IN ORDER TO EXPIDITE PLAN REVIEW: WHEN RESUBMITTING, |
| PLEASE REPLACE ONLY SHEETS |
| WHICH HAVE CHANGED, PLEASE INCLUDE A |
| TRANSMITTAL LETTER INDICATING HOW EACH |
| ITEM WAS ADDRESSED AND PROVIDE ONE COPY |
| OF ALL OLD/VOIDED SHEETS FOR REFERENCE |
| ONLY. |
| NOTE: ONLY ONE CORRECTED DRAWING |
| IN RED INK FOR REFERENCE FOR |
| RESUBMITTAL. |
| |
| END OF COMMENTS: |
| |
| REVIEW BY MIKE PERSON |
| PLUMBING PLANS EXAMINER |
| (561) 805-6730 |
| FAX (561) 805-6731 |
| E-MAIL= [email protected] |
| |
| |
| |
| |
| |