Date |
Text |
2006-09-27 00:00:00 | ******DENIED****** |
| REFERENCE: FBC-2004 FUEL GAS |
| FBC-2004 CHAPTER 1 |
| |
| |
| THE FOLLOWING INFORMATION IS REQUIRED |
| FOR GAS PLAN REVIEW ON THE ISOMETRIC |
| DRAWING. |
| |
| 1. PER FBC-2004 CHAPTER 1, SECTION |
| 106.1, SUBMITTAL DOCUMENTS: CONSTRUCTION |
| DOCUMENTS SHALL BE SUBMITTED IN TWO OR |
| MORE SETS. |
| NOTE: ONLY ONE SET OF DRAWINGS AND |
| APPLIANCE SUBMITTALS WERE SUBMITTED. |
| |
| 2. SHOW TYPE OF PIPING MATERIAL BEING |
| INSTALLED, ALL PIPE SIZES, (AND THE EDH |
| NUMBER OF CORRUGATED STAINLESS STEEL |
| TUBING FOR EACH PIPE SIZE BEING USED. |
| NOTE: PLEASE CLAIFY WHAT S.S. IS. DO YOU |
| MEAN CSST? |
| |
| 3. TYPE OF GAS, (LP OR NATURAL) |
| |
| 4. SUBMIT CALCULATIONS FOR COMBUSTION |
| AIR (IF APPLICABLE) PER FBC-2004 FUEL |
| GAS CODE SECTION 304. |
| |
| 5. INDICATE THE DELIVERY PRESSURE (PSI) |
| PER FBC-2004 FUEL GAS CODE SEC. 402.2. |
| NATURAL GAS SPECIFY .5 PSI OR 2 PSI. |
| |
| 6. SUBMIT A DETAIL SHOWING THE TYPE, |
| LOCATION, SIZE AND TERMINATION OF THE |
| GAS VENTS PER FBC-2004 FUEL GAS CODE |
| SECS. 502 THRU 505. |
| |
| 7. SUBMIT MANUFACTURE SHEETS FOR ALL GAS |
| EQUIPMENT TO VERIFY COMPLIANCE WITH |
| STANDARDS NFPA 54, NFPA 58, AND THE |
| FBC-2004 FUEL GAS CODE SEC 402.2 |
| NOTE: IF GAS SYSTEM PRESSURE IS 2LB NEED |
| SHEETS ON MP REGULATORS. |
| |
| 8. FBC-2004 CHAPTER 1,SECTION |
| 106.3.4.2: THE PERSON RESPONSIBLE FOR |
| THE DESIGN OF THE DRAWING SHALL CLEARLY |
| PRINT AND SIGN NAME, AND ALSO DATE |
| DRAWING. PLEASE DO THIS PRIOR TO |
| RESUBMITTING. |
| |
| END OF COMMENTS: |
| |
| REVIEW BY MIKE PERSON |
| (561) 805-6730 |
| FAX (561) 805-6731 |
| E-MAIL [email protected] |
| UNDER SUPERVISION OF K.STEVENS |
| (561) 805-6721 |
| |
| |
| |
| |