Date |
Text |
2007-01-26 11:01:28 | PLEASE EXPLAIN IN A LETTER EACH OF THE ITEMS BELOW AND |
| IN DRAWING REVISION BLOCK,WHAT CHANGES YOU MADE AFTER |
| 11/13/06 OUR APPROVAL. |
| |
| 1. ANY CHANGES IN STANDARDS NOTES OF CITY OF WPB ON |
| DRAWINGSFOR SIDEWALK WIDTH , ITS SLOPE, DRIVEWAY, |
| PARKING, HANDICAP PARKING, PAINT ? |
| 2.ANY CHANGES IN DUMPSTER & ITS ENCLOSURE DETAILS ? |
| LOCATION ON DWG, LOCATION MUST BE ACCESSIBLE FOR PICKUP |
| TRUCK?. |
| 3. ANY CHANGES INFIRST FLOOR ELEVATION, CENTER LINE |
| OF ROAD , SIDEWALK ELEVATION?MUST MEET FL BLDG CODE, |
| PLEASE SHOW ON THE DRAWINGS. |
| 4. ANY CHANGES INSFWMD PERMIT? ANY CHANGES IN GEO |
| TECH REPORT? |
| 5. ANY CHAGES IN STORM WATER CALCULATIONS, ? ANY |
| CHANGES IN PERVIOUS AREA, LIKE GREEN, LAKES, ETC, |
| IMPERVIOUS AREA CAL.?, |
| 6.ANY CHANGES IN THE SITE AREA, YOU ARE DEVELOPING FOR |
| THIS PROJECT ? SO, WE CAN CHECK PERVIOUS, IMPERVIOUS |
| CAL. |
| 7. ANY CHAGES IN CONNECTTING THE STORM WATER PIPES IN |
| YOUR SITE? ITS DETAILS. |
| 8. ANY CHANGES IN STORM WATER PIPES AROUND YOUR SITE? |
| SO, WE CANSEE THE BEST PIPE TO CONNECT WITH THE STORM |
| WATERFROM ALL OTHER STORM WATER PIPES. PLEASE SHOW |
| DETAIL OF THE CONTROL STRUCTURES WITH ELEVATIONS, |
| NOTCHES, BLEEDING ELEVATION, ETC DID YOU CHANGE |
| EXFILTRATION TRENCH ? |
| 9.ANY CHAGES INPOLLUTION PREVENTION DETAILS,CLOTHES |
| USED FOR SILT ETC.?,PLAN MUSTPLANS SHOWSILT FENCE |
| AROUND THE SITE |
| 10.ANY CHANGES INWATER & SEWER PLANS? MUST BE |
| APPROVED FROM 45TH STREET (MANNY G.), UTILITY DEPT |
| BEFORE WE APPROVED |
| 11.ANY CHANGES IN CATCH BASINS NEAREST YOUR SITE, AND |
| AROUND YOUR SITE FOR STORM WATER DRAIN? |
| |
| RASIK CHOKSHI805-6723 |