Date |
Text |
2006-09-28 00:00:00 | ******DENIED 3RD TIME****** |
| REFERENCE: FBC-2004 FUEL GAS |
| FBC-2004 CHAPTER 1 |
| |
| THE FOLLOWING INFORMATION IS STILL |
| REQUIRED FOR GAS PLAN REVIEW FROM THE |
| PRIVIOUS COMMENTS: |
| |
| 1. (OK) |
| |
| 2. SUBMIT AN ISOMETRIC DRAWING THAT |
| CLEARLY SHOWS ALL CUT SECTIONS OF PIPE |
| AND CORRESPONDING LENGTHS PER FBC-2004 |
| FUEL GAS CODE. |
| NOTE: THE RESUBMITTED DRAWING IS STILL |
| NOT AN ISOMETRIC AND DOES NOT CLEARLY |
| SHOW ALL CUT SECTIONS OF PIPE AND |
| CORRESPONDING LENGTHS. PLEASE REFERENCE |
| THE ATTACHED ISOMETIC EXAMPLE FOR |
| RESUBMITTAL AND PLEASE INDICATE THE |
| ABOVE GROUND PIPE LENGTHS. |
| |
| 3. SHOW TYPE OF PIPING MATERIAL BEING |
| INSTALLED, ALL PIPE SIZES, (AND THE EDH |
| NUMBER OF CORRUGATED STAINLESS STEEL |
| TUBING FOR EACH PIPE SIZE BEING USED. |
| NOTE: THE RESUBMITTED DRAWING DOES NOT |
| INDICATE ALL THE PIPE MATERIALS AND |
| SIZES PLEASE INDICATE THE ABOVE GROUND |
| PIPE MATERIALS AND SIZES FOR THE |
| RESUBMITTAL. |
| |
| 4. (OK) |
| |
| 5. (OK) |
| |
| 6. (OK) |
| |
| 7. (OK) |
| |
| 8. SUBMIT MANUFACTURE SHEETS FOR ALL GAS |
| EQUIPMENT TO VERIFY COMPLIANCE WITH |
| STANDARDS NFPA 54, NFPA 58, AND THE |
| FBC-2004 FUEL GAS CODE SEC 402.2 |
| NOTE: STILL NEED MANUFAFTURER CUT SHEETS |
| OF 1ST AND 2ND STAGE REGULATORS. |
| |
| 9. FBC-2004 CHAPTER 1,SECTION 106.3.4.2: |
| THE PERSON RESPONSIBLE FOR THE DESIGN OF |
| THE DRAWING SHALL CLEARLY PRINT AND SIGN |
| NAME, AND ALSO DATE DRAWING. PLEASE DO |
| THIS PRIOR TO RESUBMITTING. |
| NOTE: DRAWINGS STILL DON'T HAVE THE |
| PRINTED AND SIGNED NAME OF THE PERSON |
| TAKING RESPONSIBILITY OF DRAWINGS AND |
| THE DATE. |
| |
| END OF COMMENTS: |
| |
| REVIEW BY MIKE PERSON |
| (561) 805-6730 |
| FAX (561) 805-6731 |
| E-MAIL [email protected] |
| UNDER SUPERVISION OF K.STEVENS |
| (561) 805-6721 |
| |
| |
| |
| |
| |
| |