2006-08-10 00:00:00 | DENIED |
| REFERNCE: FBC-2004 FUEL GAS |
| FBC-2004 CHAPTER 1 |
| |
| A. PLANS SHALL BE SEALED PER SECTION |
| 106.1. |
| |
| B. SUBMIT A SITE PLAN SHOWING ALL |
| STRUCTURES, WALLS ETC. AJOINING THE |
| GENERATOR. SECTION 106.1.2. |
| |
| C. SEPARATE GAS PERMIT REQUIRED. THE |
| FOLLOWING INFORMATION IS REQUIRED FOR |
| REVIEW FOR GAS PERMIT: |
| |
| 1. SUBMIT AN ISOMETRIC DRAWING THAT |
| CLEARLY SHOWS ALL CUT SECTIONS OF PIPE |
| AND CORRESPONDING LENGTHS PER FBC-2004 |
| FUEL GAS CODE. |
| |
| 2. SHOW TYPE OF PIPING MATERIAL BEING |
| INSTALLED, ALL PIPE SIZES, (AND THE EDH |
| NUMBER OF CORRUGATED STAINLESS STEEL |
| TUBING FOR EACH PIPE SIZE IF BEING USED. |
| |
| 3. TYPE OF GAS, (LP OR NATURAL). |
| |
| 4. BTU LOAD OF EACH APPLIANCE AND THE |
| TOTAL BTU LOAD ON THE SYSTEM. REFER TO |
| THE FBC-2004 FUEL GAS CODE SECS. 401.8 |
| THRU 402.6.1 AND TABLES 402.4(1) THRU |
| 402.4(33). |
| |
| 5. SHOW THE DISTANCE FROM THE POINT OF |
| DELIVERY, (METER), TO THE MOST REMOTE |
| OUTLET IN THE BUILDING AND/OR SYSTEM PER |
| FBC-2004 FUEL GAS CODE APPENDIX A - USE |
| OF CAPACITY TABLES A.3.1(4). |
| |
| 6. N/A |
| |
| 7. INDICATE THE DELIVERY PRESSURE (PSI) |
| PER FBC-2004 FUEL GAS CODE SEC. 402.2. |
| NATURAL GAS SPECIFY .5 PSI OR 2 PSI. |
| |
| 8.N/A |
| |
| 9. SUBMIT MANUFACTURE SHEETS FOR ALL GAS |
| EQUIPMENT TO VERIFY COMPLIANCE WITH |
| STANDARDS NFPA 54, NFPA 58, AND THE |
| FBC-2004 FUEL GAS CODE SEC 402.2. |
| INSTALLATION INSTRUCTIONS SHALL BE |
| SUBMITTED TO DETERMING THE DISTANCE FROM |
| STRUCTURES/WALLS REQUIRED. |
| |
| REVIEW BY KEN STEVENS |
| (561) 805-6721 |
| FAX (561) 805-6731 |
| E-MAIL [email protected] |