Plan Review Notes
Plan Review Notes For Permit 06050750
Permit Number 06050750
Review Stop B
Sequence Number 1
Notes
Date Text
2006-05-29 00:00:00 
 1) PROCEDURES: 1(B) A COMPLETE
 INSTALLATION SCHEDULE SUMMARIZING &
 IDENTIFYING OPENING SIZES, STORY
 HEIGHTS, UNIT MARK NUMBERS, UNIT
 SPANS/WIDTHS, UNIT STORM BAR REINFORCING
 REQUIREMENTS, WALL PRES- SURE ZONES,
 SLAT TYPES, ETC., SHALL BE SUBMITTED AT
 TIME OF PERMIT APPLICATION TO FACILITATE
 PLAN REVIEW AND PERMIT ISSUANCE.
 HI-LIGHT OR CIRCLE FROM EACH PAGE WHICH
 ITEM WILL BE USED TO INSTALL THE
 SHUTTERS FROM THE REPORTS. SEE WPB
 INSTALLATION SCHEDULE FOR THE SHUTTERS
 IN PACKAGE. ALL INFORMATION IS REQUIRED
 FOR REVIEW.
  
 2) FL S S 713.13
 NOTICE OF COMMENCEMENT, TO BE FILED
 WITH THE CLERK OF THE COURT BEFORE A
 PERMIT WILL BE ISSUED. NOTE: 713.13(2)
 IF THE WORK DESCRIBED IN THE NOTICE OF
 COMMENCEMENT IS NOT ACTUALLY COMMENCED
 WITHIN 90 DAYS AFTER THE RECORDING
 THEREOF, SUCH NOTICE IS NULL & VOID.
  
 MYRON JACOBS
 BUILDING PLAN REVIEWER
 805-6726
  
  
  