Date |
Text |
2006-06-11 00:00:00 | ********** UNSAT ************* |
| |
| ** PLEASE KNOW BESIDES THE BELOW |
| COMMENTS, PLANS ARE NOT COMPLETE AT THIS |
| TIME FOR COMPLETE REVIEW. |
| |
| |
| 1) NOTE: ATTENTION CONTRACTOR, IF PROTON |
| ELECTRICAL IS ALSO DOING THE ELECTRICAL |
| INSTALLATION FOR THE CONNECTIONS ON THE |
| GENERATOR, THEN PLEASE SIGN ON THE |
| ELECTRICAL LINE ON PERMIT APPLICATION SO |
| AN ELECTRICAL PERMIT CAN BE ESTABLISHED. |
| THIS WAS NOT |
| |
| 2) NOTE: PLEASE SUBMIT SPECS FOR FUEL |
| TANK. PLEASE SEE PLANS MUST INCLUDED |
| LOCATION, VENTILATION, FIRE RATINGS ETC |
| . |
| PLEASE SEE NOTE #5 BELOW, IF THE GEN |
| FEEDS ANY LEGALLY REQUIRED BACK UP |
| LTS/SYSTEMS, THE AMOUNT OF FUEL, AND RUN |
| TIMES SHALL BE CLEARLY INDICATED ON |
| PLANS. |
| PLEASE KNOW THERE IS NOTHING ON PLANS |
| FOR INSTALLATIONOF GEN, FUEL, LOCATION |
| ETC. |
| PLEASE SEE COMMENTS FROM OTHER TRADES |
| WHICH WILL AFFECT PLANS SUBMITTED. |
| PLEASE BE SURE ALL TANK SPECS CONTAIN |
| LISTING BY A NRTL. |
| 215.5 |
| |
| 3) NOTE: PLEASE SUBMIT A COMPLETEPLAN |
| SHOWING THE LAYOUT FOR THE GENERATOR. |
| PLEASE SEE THAT NO MEANS OF DISCOONECTS |
| ARE BEING SHOWN FOR GROUPING OF MAINS IN |
| THE BUILDING. |
| PLEASE SHOW THE LOCATION OF ALL THE |
| EXISTING GENERATORS FEEDING THIS |
| BUILDING THE MEANS OF DICONNECT LOCAITON |
| FOR ALL. |
| 230.72, 225.31-225.39, 230.2 |
| |
| 4) NOTE: PLEASE SEE THAT ALL SPECS |
| SUBMITTED FOR GEN, ATS ETC SHALL CLEARLY |
| BE HIGHLIGHTED FOR EACH UNIT EQUIPMENT |
| BEING USED ON THIS JOBSITE. |
| 215.5 |
| |
| 5) NOTE: PLEASE VERIFY IF THIS GENERATOR |
| WILL BE FEEDING ANY OF THE REQUIRED BACK |
| UP POWER FROM LIGHTING ETC. |
| PLEASE NOTE IF ALL LTS ARE BATTERY BACK |
| UP, OR ARE THEY FED FROM A LEGALLY |
| REQUIRED BACK UP SYSTEM NOW. |
| PLEASE SEE SYSTEM INSTALLATION |
| REQUIREMENTS PER 700,701, NFPA-110 ETC |
| |
| |
| 6) NOTE: PLEASE SEE PLANS INDICATE TWO |
| TRANSFORMERS BEING FED, YET PANEL SB8 |
| DOES NOT CORRELATE. |
| 215.5 |
| |
| 7) NOTE: PLEASE PLACE NOTES ON PLANS FOR |
| ALL SIGNAGE WHICH WILL BE REQUIRED. |
| 230.2E,702.8,701.9 ETC. |
| PLEASE KNOW, THE LOCATIONS OF SUCH |
| DISCONNECTS AND SYSTEMS HAVE NOT BEEN |
| APPROVED AT THIS TIME. |
| |
| 8) NOTE: PLEASE INDICATE THE OCP AT |
| GENERATOR. |
| 215.5 |
| |
| 9) NOTE: PLEASE SEE MULTIPLE PANELS ON |
| RISER WITH THE SAME IDENTIFICATION?? |
| |
| 10) NOTE: PLEASE SEE THAT ALL CONTINUOUS |
| LOADS SHALL BE SHOWN AT 125%. |
| 215.3,230.42 ETC |
| |
| 11) NOTE: PLEASE SEE MAX HEAT LOADS |
| SHALL BE FIGURED FOR THE AHU'S OR LOAD |
| SHEDDING IS PERMITTED. PLEASE PROVIDE A |
| COMPLETE DETAIL FOR LOAD SHEDDING IF |
| THIS OPTION IS TAKEN. |
| THE WIRING SCHEMATIC WILL BE REQUIRED ON |
| PLANS. |
| 702.5 ETC |
| |
| 12) NOTE: PLEASE SEE GEN ANNUNCIATOR |
| PANEL, CONTROLS,STATUS INDICATORS SHALL |
| ALSO BE LOCATED IN THE EXISTING FIRE |
| COMMAND ROOM WITH SIGNAGE AS REQUIRED. |
| NFPA-72, NFPA-101, NFPA-110 |
| |
| 13) NOTE: PLEASE KNOW, A FUEL TYPE |
| PERMIT MAY ALSO BE REQUIRED. SEE MECH |
| REVIEW. |
| |
| 14) NOTE: PLEASE SEE MISSING EQUIPMENT |
| GROUNDING CONDUCTORS. |
| 250.110,250.122,250.6,250.24. |
| PLEASE SEE NONE ARE BEING SHOWN AT THIS |
| TIME. PLEASE KNOW, IF USING ALL METAL |
| CONDUITS, THEN CONNECTORS ALL SHALL BE |
| LISTED FOR "EQUIPMENT GROUNDING". |
| STANDARD CONNECTORS ARE NO PERMITTED |
| UNLESS LISTED AS NOTED.OR |
| PLEASE INDICATE THE EQUIPMENT GROUNDING |
| CONDUCTOR SIZED PER 250.122 |
| |
| ** PLEASE SEE COMMENTS FROM OTHER TRADES |
| WHICH WILL AFFECT THE PLANS. |
| |
| PLEASE SUBMIT THE ABOVE INFORMATION FOR |
| REVIEW. IF THERE ARE ANY QUESTIONS, |
| PLEASE DO NOT HESITATE TO CALL. |
| |
| DEWEY PALMER |
| ELECTRICAL PLAN REVIEW |
| CITY OF WEST PALM BEACH |
| CONSTUCTION SERVICES DEPT. |
| 561-805-6717 |
| [email protected] |
| |
| |
| |