Date |
Text |
2007-02-06 16:19:15 | DENIED FIFTH TIME |
| REFERENCE: FBC-2004 PLUMBING |
| |
| THE FOLLOWING ITEMS ARE STILL REQUIRED TO BE CORRECTED |
| FOR PLUMBING PLAN REVIEW TO MEET CODE COMPLIANCE: |
| |
| 1. SHEET P-1 AND P-2 SANITARY ISOMETRICS AND PLUMBING |
| PLAN WASHING MACHINE BRANCH DRAINS ARE STILL SIZED |
| WRONG ON ALL UNITS ( 708 FIRST AND SECOND FLOOR, 708 |
| 1/2A AND 708 1/2B) PER FBC-2004 PLUMBING, SECTION 406.3 |
| THEY NEED TO BE THREE INCH (3") NOT TWO INCH (2"). |
| PLEASE CORRECT AND RESUBMIT. |
| |
| 2. SEE ATTACHED NOTICE FS 553.80 (2) (B) REGAURDING |
| FOUR TIMES THE FEE. |
| |
| THE FOLLWING ARE NEW ITEMS THAT NEED TO BE CORRECTED |
| FOR PLUMBING PLAN REVIEW TO MEET CODE COMPLIANCE: |
| |
| 3. SHEET P-1 GENERAL NOTES #16 DELETE "APPROVED AIR |
| CHAMBERS" AND ADD IN ITS PLACE THE FOLLOWING " WATER |
| HAMMER ARRESTORS TO BE INSTALLED PER FBC-2004 PLUMBING, |
| SECTION 604.9." |
| |
| 4. SHEET P-1 NOTE ON TUB AND SHOWER VALVES: PLEASE ADD |
| "TUB AND SHOWER VALVES TO BE INSTALLED PER FBC-2004 |
| PLUMBING, SECTION 424.3. |
| |
| 5. SHEET P-2 UNIT 708 1/2A WATER ISOMETRIC: A} PER |
| FBC-2004 PLUMBING, SECTION 606.1 (2) FULL-OPEN VALVE |
| REQUIRED ON THE WATER DISTRIBUTION SUPPLY PIPE AT THE |
| ENTRANCE INTO THE BUILDING. B} HOT AND COLD WATER ARE |
| CROSSED ON THE WASHER, KITCHEN, AND LAV, PER FBC-2004 |
| PLUMBING SECTION 607.4 FLOW OF HOT WATER TO FIXTURES |
| SHALL BE INSTALLED AND ADJUSTED SO THAT THE FLOW OF HOT |
| WATER FROM THE FITTING CORRESPONDS TO THE LEFT-SIDE OF |
| THE FIXTURE FITTING. C} WATER SERVICE NEEDS TO SUPPLY |
| THE WATER DISTRIBUTION PIPING FIRST THEN BRANCH TO THE |
| WATER HEATER AS THE CORRECTED DRAWING INDICATES, NOT |
| DIRECTLY SUPPLY THE WATER HEATER AS SHOWN. PLEASE |
| CORRECT AND RESUBMIT. D} PLEASE CLARIFY THE THIRD WATER |
| CONNECTION TO THE WASHER. IS IT NEEDED, IF NOT PLEASE |
| DELETE. |
| |
| 6. SHEET P-2 708 1/2B WATER ISOMETRIC: A} PER FBC-2004 |
| PLUMBING, SECTION 606.1 (2) FULL-OPEN VALVE REQUIRED ON |
| THE WATER DISTRIBUTION SUPPLY PIPE AT THE ENTRANCE INTO |
| THE BUILDING. B} HOT AND COLD WATER ARE CROSSED ON THE |
| LAV AND WASHER, PER FBC-2004 PLUMBING SECTION 607.4 |
| FLOW OF HOT WATER TO FIXTURES SHALL BE INSTALLED AND |
| ADJUSTED SO THAT THE FLOW OF HOT WATER FROM THE FITTING |
| CORRESPONDS TO THE LEFT-SIDE OF THE FIXTURE FITTING. C} |
| WATER SERVICE NEEDS TO SUPPLY THE WATER DISTRIBUTION |
| PIPING FIRST THEN BRANCH TO THE WATER HEATER AS THE |
| CORRECTED DRAWING INDICATES, NOT DIRECTLY SUPPLY THE |
| WATER HEATER AS SHOWN. PLEASE CORRECT AND RESUBMIT. D} |
| IS IT THE INTENT TO HAVE HOT WATER SUPPLIED TO THE HOSE |
| BIBB AS INDICATED. IF NOT PLEASE CORRECT AND RESUBMIT. |
| E} PLEASE CLARIFY THE THIRD WATER CONNECTION TO THE |
| WASHER. IS IT NEEDED, IF NOT PLEASE DELETE. |
| |
| **********IMPORTANT INFORMATION |
| IN ORDER TO EXPIDITE PLAN REVIEW: WHEN RESUBMITTING, |
| PLEASE REPLACE ONLY SHEETS |
| WHICH HAVE CHANGED AND PROVIDE ONE COPY |
| OF ALL OLD/VOIDED SHEETS FOR REFERENCE |
| ONLY. NOTE: ONLY ONE CORRECTED DRAWING |
| IN RED INK FOR REFERENCE FOR |
| RESUBMITTAL. |
| |
| END OF COMMENTS: |
| |
| REVIEW BY MIKE PERSON |
| (561) 805-6730 |
| FAX (561) 805-6731 |
| E-MAIL [email protected] |
| UNDER SUPERVISION OF K.STEVENS |
| (561) 805-6721 |
| |