2006-02-17 00:00:00 | DENIED: |
| 1.PLAN SHEET M.01 MECHANICAL NOTE #1, |
| REFERENCE STANDARDS ARE NOT THE CURRENT |
| STANDARDS AS ADOPTED WITH THE 2004 FBC. |
| (EXAMPLE - ASHRAE 62-01, 15-01, 34-01, |
| NFPA 90A-02, 90B-02, ETC).PLEASE |
| VERIFY ALL REFERENCED STANDARDS. |
| |
| 2.PLAN SHEET M0.2 O.A. CALCS & EXHAUST |
| CALCS. REFERENCE THE WRONG ASHRAE |
| STANDARD. |
| |
| 3.PLAN SHEET M2.1.1, PLEASE INDICATE |
| RETURN AIR.PLEASE NOTE, NO |
| COMBUSTIBLES ALLOWED IN THE PLENUM PER |
| 2004 FMC 602.2.1 |
| |
| 4.PLAN SHEET M2.1.1, NOTES REFERENCE |
| PLAN SHEET M7.3 FOR DETAIL OF THE |
| UNDERFLOOR AIR HIGHWAY LOOP & THE FUTURE |
| "YORK FLEXSYS VAV MIT TERMINAL |
| DIFFUSER".DETAILS ON PLAN SHEET M7.3 |
| DO NOT SHOW THIS APPLICATION.ALL |
| DETAILS INDICATE DUCT SYSTEM IN THE |
| CEILING.PLEASE INDICATE HOW THE DUCT |
| WILL BE SUPPORTED UNDER THE FLOOR. |
| |
| 5.PLAN SHEET M2.1.1, 2.1.2, & 2.2.2 |
| MECHANICAL ROOMS ARE OPEN RETURN WITH |
| FLOOR DRAINS INDICATED IN THE MECHANICAL |
| ROOM.PLANS DO NOT PROVIDE A LAYOUT OF |
| THE CONDENSATE FROM THE AHU.IS THE |
| INTENT TO TERMINATE INTO THE FLOOR |
| DRAIN? WHAT WILL BE THE PRESSURE |
| DIFFERENTAL IN THE RETURN AIR PLENUM. |
| PLEASE REFERENCE 2004 FPC SECTION 901.2. |
| |
| 6.PLEASE INDICATE PIPING MATERIAL FOR |
| THE CONDENSER WATER.2004 FMC CHAPTER |
| 12. |
| |
| IF YOU HAVE ANY QUESTIONS, PLEASE |
| CONTACT PATTY KRAUSS AT (561)805-6719. |
| |
| |
| |
| |
| |