2006-02-10 00:00:00*** PLEASE SEE NOTES UNDER MAIN BLDG
 ALSO FOR ADDRESS.
  
 PLEASE KNOW, THE LEGAL PROPERTY MAY NOT
 CHANGE AS THE ELECTRICAL SERVICEAND
 GENERATORS COME FROM GARAGE BLDG TO MAIN
 BLDG.
 PLEASE SEE ANY LEGAL PROPPERTY PCN
 CHNAGE ETC WILL REQUIRE LEGAL EASEMENTS
 ETC.
2006-02-01 00:00:00********** UNSAT **********
  
 ** PLEASE KNOW, PLANS AND SUBMITTIALS
 ARE NOT COMPLETE AT THIS TIME.
  
  
 1)NOTE: PLEASE SEE ALL CURRENT CODES
 SHALL BE REFERENCED TO THE CURRENT CODES
 IN EFFECT. PLEASE SEE PLANS CALL FOR
 2001 FLORIDA BUILDING CODE. PLEASE KNOW,
 AS OF OCT 1ST, 2005 THE NEW FBC IS THE
 2004 EDITION. PLEASE SEE THE FOLLOWING
 SHALL BE REFERENCED. 2003 NFPA-101, 2002
 NFPA-70, AND 2002 NFPA-72
  
 2)NOTE: PLANS WILL REQUIRED BATTERY BACK
 UP LT FIXTURES IN MAIN ELECTRICAL RM,
 ELEVATOR RMS.
 PLEASE ALSO KNOW BATTERY BACK UP
 FIXTURES WILL BE REQUIRED IN STAIRWAY
 AND EGRESS PATHS TO PROVIDE A MIN OF 1FT
 CANDLE OF LIGHT BY SOME SORT OF BATTEY
 BACK UP FIXTURE. PLEASE SEE NFPA-101
 7.9.2.2, TRIPPING OR SHUTTING OFF ANY
 SINGLE DEVICE OR MEANS OF OVERCURRENT
 PROTECTION SHALL NOT LEAVE ANY ONE
 EGRESS PATH IN TOTAL DARKNESS.
 PLEASE PROVIDE PHOTOMETRICS FOR
 STAIRWAYS, AS THE 2003 LS 101 7.8.1.3
 REQUIRES A MIN OF 10FY CANDLES(108LUX)
 IN STAIRWAYS UNDER NORMAL LIGHTING
 CONDITIONS AND 7.9.2.2 PERMITS THE
 DERATING TO A MIN OF 1FT CANDLE UNDER
 EMERGENCY CONDITIONS.
 700.16.,700.12E ETC
  
 3)NOTE: PLEASE SEE POSSIBLE BLDG
 COMMENTS AS STAIRWAY DOORS SEEM TO SWING
 IN, INSTEAD OF THE DIRECTION OF EGRESS.
 PLEASE SEE ANY POSSIBLE COMMENTS WITH
 RESPECT TO THE "FUTURE" TENANT SPACE.
 (GYM).
  
 4)NOTE: PLEASE SUBMIT ALL MANUFACTURES
 SPECS/CUT SHEETS FOR GENERATOR, ATS,
 ETC. PLEASE PROVIDE SPECS FOR ANY TANKS
 FOR THE PRIME-MOVER OF GEN.
 PLEASE BE SURE ALL SPECS ETC INDICATE
 LISTINGS FROM A NRTL.
 NO REVIEW CAN BE DONE AT THIS TIME.
  
 5)NOTE: PLEASE SEE NO MAIN IS SHOWN ON
 THE LINE-SIDE OF ATS SHOWN. PLEASE SEE
 THE FOLLOWING COMMENT WITH RESPECT TO
 GFP FOR SYSTEMS 277/480V 1000A'[S OR
 MORE.
 230.70,ETC.
  
 6)NOTE: PLEASE SEE ATS MANUFACTUREA S
 GFP IS REQUIED BY THE NEC FOR SERVICE
 AND MAY REQUIRE A 4-POLE ATS FOR GFP TO
 WORK CORRECTLY.
 PLEASE PROVIDE INFORMATION; PLEASE SEE
 GENERATOR IS ALREADY SHOWN AS A
 SEPARATELY DERIVED SYSTEM AS REQUIRED,
 HOWEVER NOT ENOUGH ATS INFORMATION IS
 SUBMITTED FOR CORRELATION OF REVIEW FOR
 CODE COMPLIANCE.
 EXAMPLE, PLEASE SEE TEXT TAKEN FROM
 ASCO:
 "WHERE GROUND FAULTPROTECTION IS
 TRIGGERED BY THE CODE AND AN ALTERNATE
 POWER SUPPLY IS INCLUDED,SWITCHING OF
 THE NEUTRAL BECOMES NECESSARY. THE
 CIRCUIT SHOWN ABOVE ILLUSTRATESSUCH A
 CIRCUMSTANCE. THE SERVICE IS LARGER THAN
 1,000 AMPS. CONSEQUENTLY, GROUNDFAULT
 PROTECTION IS REQUIRED AT THE MAIN
 SERVICE DISCONNECT AT A MINIMUM. IF IT
 IS INSTALLED THERE AND THE GENERATOR
 NEUTRAL GROUNDING WAS THROUGH A SOLID
 CONNECTION TO THE MAIN SERVICE NEUTRAL,
 A GROUND FAULT WHEN THE GENERATOR IS
 FEEDING THE LOAD WILL CAUSE THE MAIN
 SERVICE DISCONNECT TO OPEN. THIS WILL
 NOTDISCONNECT THE ARCING FAULT FROM
 THE GENERATOR. COORDINATION IS THUS
 LOST."
  
 7)NOTE: PLEASE SEE SERVICE MAINS AS
 REQUIRED DO NOT INDICATE ANY GFP PER
 230.95,240.13 ETC.
  
 8)NOTE: PLEASE LABEL ALL MAINS, 1, 2, 3
 ETC, 1OF? 2 OF ? ETC.
  
 9)NOTE: PLEASE PROVIDE ONE LINE
 GROUNDING ELECTRODE DIAGRAM FOR BLDG, TO
 INCLUDE GROUNDING ELECTRODE RISER FOR
 ANY TRANSFORMERS. 250.30,250.58
  
 10)NOTE: PLEASE SEE PANELS , (MDP WHICH
 ARE NOT COMPLETE AT THIS TIME. PLEASE
 SEE SOME AREA OF PANELS WHERE XXX'S ARE
 SHOWN FOR REQUIRED INFORMATION.
 PLEASE SEE "GGP" WHERE BRANCH CIRCUIT
 INFORMATION APPEARS IN THE TITLE BLOCK
 OF SAID PANEL.
 PLEASE SEE OTHER PANELS WHERE ALL
 INFORMATION INDICATED IS SHOWN AS
 "SPARE"? PLEASE SPECIFY "FUTURE" USE AND
 FOR WHAT LOADS THESE WILL FEED.
  
 11)NOTE: PLEASE CORRELATE RISER DIAGRAM
 AND PANELS.
 PLEASE SEE "GLH", "GMDP", GLH", ETC,
 THESE ARE SHOWN BEING FED FROM OTHER
 EQUIPMENT ON RISER THAN LISTED ON PANEL
 SCHEDULES.
 PLEASE ALSO SEE "GDP", "GGP", AND "GLP",
 PLEASE SEE RISER, PLEASE SEE "T1B" AS
 THIS IS FED FROM TWO SEPARATE PANELS,
 AND CORRELATE WIRTH RISER.
 215.5
  
 12)NOTE: PLEASE SEE NOTES FOR
 DISTRIBUTION SYSTEM MENTIONS TO EXTEND
 TO MAIN BLDG, PLEASE SEE NOTES FROM MAIN
 BLDG REVIEW WHEN COMPLETED AS THIS MAY
 AFFECT ELECTRICAL SERVICE OR DESIGN AS
 SHOWN.
  
 13)NOTE: PLEASE COMPLETE ALL SERVICE
 ENTRANCE CONDUCTORS ON RISER ALONG WITH
 ALL FEEDERS.
 PLEASE SEE MISSING SEC'S TO EM SYSTEM,
 ATS OR NEW MAIN DISCONNECT, PLEASE SEE
 MISSING FEEDERS FROPM GEN, PLEASE SEE
 MISSING SEC'S TO GMDP, ATS TO GDP ETC .
 PLEASE COMPLETE RISER.
  
 14)NOTE: PLEASE SEE MISSING OVERCURRENT
 PROTECTION AT GENERATOR. PLEASE ALSO SEE
 MISSING LOAD CALCUALTIONS FOR INTENDED
 LOAD FOR GENERATOR.
 PLEASE ALSO SEE FOLLOWING COMMENT.
  
 15)NOTE: PLEASE COMPLETE AND SUBMIT MIN
 LOAD CALCUALTIONS AS REQUIRED PER
 NEC.220
 PLEASE SEE ALL MAIN DISTRIBUTIION
 SYSTEMS ARE SHOWING "BLANKS" FOR LOADS??
 PLEASE BE SURE TO INDICATE ALL LOADS. NO
 REVIEW OF THESE CAN BE DOINE AT THIS
 TIME.
 215.5
  
 16)NOTE: PLEASE SEE NOTES FOR GENERATORS
 AS INDICATED ON ELECTRICAL PLANS WHICH
 NOTES ALL GENERATOR CONDUITS PROCEEDING
 TO THE MAIN OFFICE BLDG??
 PLEASE INDICATE WHERE GENFOR GARAGE IS
 LOCATED?
 PLEASE ALSO SEE COMMENTS FOR MAIN BLDG
 AS THESE NOTES INDICATE ALL THESE
 FEEDERS SHALL PROCEED TO THE FIRST FLR
 MAIN ELECTRICAL ROOM, HOWEVER THIS DOES
 NOT SEEM TO CORRELATE WITH WHAT IS SHOWN
 ON MAIN BLDG PLANS.
 215.5
  
 17)NOTE: PLEASE SEE FBC 2004 CHAPTER 13,
 13-413.1ABC.1.1, .2 FOR VOLTAGE DROP
 INFORMATION NEEDED.
  
 18)NOTE: PELASE SEE LIGHTING
 REQUIREMENTS UNDER 13-415 FOR AREAS OF
 CONTROL AND TANDEM WIRING.
 PLEASE SPECIFY THIS INFORMATION ON
 PLANS.
  
 19)NOTE: PLEASE SEE LANDSCAPE PLANS
 MENTIONS AND NOTES LIGHTING AND TO SEE
 ELECTRICAL PLANS FOR THESE, HOWEVER
 THESE ITEMS COULD NOT BE LOCATED ON
 ELECTRICAL PLANS.
 PLEASE SUBMIT WIND LOAD CALCUALTIONS FOR
 ALL SITE LIGHTING POLES TO MEET FBC 140
 MPH.
  
 20)NOTE: PLEASE SEE LANDSCAPE PLANS ARE
 SEALED "PHOTO-COPIES" OF ARCHITECT'S
 SIGNATURE. PLEASE SEE FS 481.221 WHICH
 REQUIRES THE SIGNATURE TO BE AN ORIGINAL
 SIGNATURE.
  
 ** PLEASE KNOW, REVIEW FOR MAIN BLDG HAS
 NOT COMMENCED AT THIS TIME.
  
 ** PLEASE SEE ANY POSSIBLE COMMENTS FROM
 OTHER REVIEWER(S) WHICH MAY AFFECT
 ELECTRICAL PLANS.
  
 ** PLEASE REMOVE ALL OLD/VOIDED SHEETS
 AND ON.Y INSERT NEW REVISED SHEETS INTO
 COMPLETED SETS FOR REVIEW AND STAMPING.
 ONLY SUBMIT ONE COPY OF OLD/VOIDED
 SHEETS FOR REFERENCE.
  
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE DO NOT HESITATE IN CONTACTING
 THIS OFFICE.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 561-805-6717
 DPALMER2WPB.ORG
  
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved