2009-04-12 12:54:22** NOTES**
  
 1) NOTE: SITE LIGHTING WORK WAS COMPLETED WITHOUT
 PERMITS OR PLANS FOR THE SCOPE OF WORK WHICH IS ONLY
 NOW REVISED AND PART OF THE BASE BUILDING.
 THE SITE LIGHTING ORIGINALLY APPLIED FOR IN 2006 WAS
 EXPIRED FOR BOTH THE MAIN SITE LIGHTING PERMIT AS WELL
 AS THE ELECTRICAL SUB PERMIT BEFORE ACTUAL WORK WAS
 EVER COMMENCED. NO INSPECTIONS WERE EVER SCHEDULED
 UNDER 0611.0393 AND 06110241.
 VALUE INCREASED ON BASE BUILDING PERMIT TO INCLUDE
 VALUE WHICH WAS APPLIED FOR UNDER 09020126. GC IS
 RESPONSIBLE TO SUBMIT LETTER TO CLOSE OUT 09020126 AS
 WORK WAS TRANSFERRED TO BASE BUILDING INCLUDING FEES.
 THE REVISED ENERGY CALCULATIONS WERE REVIEWED FOR
 ELECTRICAL LIGHTING COMPLIANCE ONLY. ALL OTHER TRADES
 PASSED PREVIOUS CALCULATIONS. THERE ARE NO GROSS ERRORS
 ON LIGHTING AS STATED IN FBC CHAPTER 13.
 **
 ALL SITE LIGHT POLES, STRUCTURAL AND ELECTRICAL
 INSPECTIONS SHALL BE COMPLETED AND WORKED OUT WITH THE
 BUILDING AND ELECTRICAL INSPECTORS.
  
  
 IF THERE ARE ANY QUESTIONS; OR IF COMMENTS ARE NOT
 TYPED IN A CLEAR MANNER PLEASE DO NOT HESITATE TO
 CONTACT THIS REVIEWER.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW II
 CONSTRUCTION SERVICES DEPARTMENT
 CITY OF WEST PALM BEACH
 561-805-6717
 [email protected]
  