Plan Review Notes
Plan Review Notes For Permit 05091425
Permit Number 05091425
Review Stop P
Sequence Number 3
Notes
Date Text
2006-08-26 00:00:00 
  
  
  
 PASSED/PROVISO
  
 SHTS P-1 & P-22 FLOOR DRAINS ARE NOT
 APPROVED IN THE STAIRWELLS. POSITIVE
 PRESSURES CAUSED BY THE STAIRWELL
 PRESSURIZATION MAY CONFLICT WITH SECTION
 901.2. ALSO PENETRATIONS IN AN EXIT
 ENCLOSUER ASSEMBLY OTHER THAN THOSE
 LIMITED TO NFPA 101 SECTION 7.1.3.2.1(5)
 ARE NOT ALLOWED. - REVISIONS REQUIRED
 FOR THESE SHEETS
  
  
  
  
 GAS APPLIANCE VENTING SHALL BE FIELD
 INSPECTED AND APPROVED.
 MANUF. SPECIFICATION SHEETS SHALL BE
 SUBMITTED AT THE TIME OF GAS PERMIT
 APPLICATION. MANUF. SPECIFICATIONS
 SHEETS REQUIRED FOR THE GAS REGULATORS.
 VENTS FOR REGULATORS SHALL BE MADE OF
 NON COMBUSTABLE MATERIAL. GAS RISER - A
 SHUT OFF VALVE SHALL BE INSTALLED PRIOR
 TO THE REGULATORS WITH A UNION BETWEEN
 OR AFTER REGULATOR. (SHT P-6). SECTION
 410.2(5). REVISIONS REQUIRED FOR THESE
 SHEETS.
  
  
  
  
 SHTS P-4 & P-21A COOLING TOWER WATER
 RISER DIAGRAM. THE CHECK VALVES TO THE
 FOUNTAINS AND THE TRASH CHUTES ARE NOT
 APPROVED. INSTALL N-36 VACUUM BREAKERS
 FOR THIS APPLICATION. - THE IRRIGATION
 SYSTEM REQUIRES A PRESSURE VACUUM
 BREAKER TO THAT LINE SEPARATE FROM THE
 REST OF THE SYSTEM. - CLARIFY WATER
 PIPING TO POOL HEATERS AS THERE IS MAKE
 UP WATER TO THE COLLECTING TANKS. -
 REVISION REQUIRED FOR THESE SHEETS.
  
  
  
  
 SEE PROVISO REQUIREMENTS FOR SHEETS P-1,
 P-4, P-6, P-21A, & P-22.
  
  