Date |
Text |
2005-12-17 00:00:00 | DENIED |
| REFERENCE: FBC-2001 PLUMBING |
| FBC-2001 FUEL GAS |
| FBC-2001 BUILDING |
| FBC-2001 CHAPTER 1 |
| FBC-2001 CHAPTER 11 |
| FHA-98 DESIGN MANUAL |
| FLORIDA ADMINISTRATIVE CODE |
| FLORIDA STATUTES |
| WPB CITY CODE |
| |
| 1. PLANS APPEAR TO BE INCOMPLETE AS |
| SUBMITTED. MORE COMMENTS MAY BE |
| FORTHCOMING NEXT REVIEW. |
| 2. SHT L-6 MISSING. (SEE INDEX ON SHT |
| L-1). SECTION 104.2.1. |
| 3. SHT A-0.1 INDEX INDICATES THAT SHTS |
| A-5.1 THRU A-5.6 HAVE KITCHEN AND |
| BATHROOM ELEVATIONS, NOTES & DETAILS. |
| THESE SHEETS WERE NOT SUBMITTED. SECTION |
| 104.2.1. |
| 4. SHTS A-1.7, A-1.8, A-2.6.1 THRU |
| A-2.6.6, SUBMIT CALCULATIONS FOR PRIMARY |
| AND SECONDARY ROOF DRAINS FOR ALL ROOFS. |
| SHOW THE LOCATION OF ALL SECONDARY ROOF |
| DRAINS FOR ALL ROOFS/DECKS. |
| 5. ALL UNIT TYPES SHALL COMPLY WITH |
| FHA-98 DESIGN MANUAL REQUIREMENTS ONE |
| THRU SEVEN. SUBMIT DETAILS. |
| 6. NOT USED |
| 7. ALL ARCHITECT SHEETS. SEAL OF THE |
| ARCHITECT SHALL IMPART INFORMATION |
| REQUIRED BY FAC/FS. LITTLE OR NO |
| INFORMATION CAN BE GLEANED FROM THE SEAL |
| ON SOME SHEETS. PLEASE BE SURE EACH |
| SHEET IS SEALED CORRECTLY & INFORMATION |
| REQUIRED IS IMPARTED ON EACH SHEET. FAC |
| 61G1-16.004 & FS 481.2055. |
| 8. SHT A-2.7.5 SHOW THE LOCATION OF ALL |
| SECONDARY DRAINS REQUIRED BY SECTION |
| 1107. |
| 9. SHTS A-2.7.5 & A-10.1 MORE |
| INFORMATION IS REQUIRED FOR THE |
| FOUNTAINS. PLEASE INDICATE IF THERE WILL |
| BE WATER SUPPLY LINES AND OR DRAINAGE |
| LINES FOR FOUNTAINS. IF WATER SUPPLY |
| LINES ARE INSTALLED, BACKFLOW PREVENTION |
| IS REQUIRED. IF DRAINS ARE INSTALLED, |
| THEY SHALL CONNECT TO THE SANT. SYSTEM |
| AND THE OVERFLOW SHALL DRAIN TO STORM. |
| PLEASE CLARIFY. SECTIONS 104.2.1 & 608. |
| 10. SHT A-2.7.5 SEPARATE PERMITS |
| REQUIRED FOR THE POOL & SPA POOL. |
| (INFORMATIONAL). |
| 11. SHT P-1 NO PIPING SHOWN TO FLOOR |
| DRAINS IN THE TRASH ROOM AND IN THE PUMP |
| ROOMS. SECTION 104.2.1. |
| 12. SHT P-1 NO PIPING SHOWN TO RISERS |
| 29, 30, & 44 THRU 51. SECTION 104.2.1. |
| 13. SHT P-1 RISERS 10 & 26 NOT SHOWN ON |
| FLOOR PLAN. SECTION 104.2.1. |
| 14. SHT P-2 NO FLOOR PLANS FOUND FOR THE |
| FLOOR PLAN A-1.2. PLEASE CLARIFY. |
| SECTION 104.2.1. |
| 15. SHT P-2 4"-180FU DOWNSTREAM OF RISER |
| S/51A IS NOT CORRECT. PLEASE CHECK |
| FIGURES. SECTION 104.2.1. |
| 16. SHT P-2 RECALCULATE FU'S DOWNSTREAM |
| OF RISERS 64 & 65. SECTION 104.2.1. |
| 17. SHT P-2 INDICATE FU VALUE FOR RISERS |
| 75 & 82. SECTION 104.2.1. |
| 18. SHT P-4 SUBMIT CALCULATIONS FOR |
| PRIMARY AND SECONDARY ROOF DRAINS. SHOW |
| SF OF EACH DRAINED AREA PLUS 1/2 AREA OF |
| ALL VERTICAL WALLS INCLUDING PARAPETS, |
| PLUS THE AREA OF ROOFS THAT DRAIN ONTO |
| THE ROOF/DECK AREA FROM ABOVE. |
| 19. SHT P-4 NUMEROUS RWL'S & DECK DRAINS |
| ARE SHOWN FOR DD & PLANTER DRAINS ON THE |
| 9TH FLOOR, BUT NO PIPING IS SHOWN |
| INDICATING WHERE THE DRAINS ARE DRAINING |
| TO. PLEASE CLARIFY. SHOW PIPING ON RWL |
| RISER DIAGRAMS. ALSO NO RWL'S FOR THESE |
| DRAINS ARE SHOWN ON SUBSEQUENT SHEETS. |
| SECTION 104.2.1. |
| 20. SHT P-5 SHOW THE LOCATION OF ALL |
| SECONDARY DRAINS REQUIRED IN SECTION |
| 1107. |
| 21. SHT P-5 RWL 3200SF NOT SHOWN ON THE |
| FLOOR PLAN. (NEAR RISER 79) 104.2.1. |
| 22. SHT P-7 SUBMIT CALCULATION FOR |
| PRIMARY AND SECONDARY ROOF DRAINS. (SEE |
| COMMENT #18). SECTIONS 1106 & 1107. |
| 23. SHT P-7 SUBMIT A DETAIL FOR THE |
| BOILER ROOM. SHOW THE PIPING LAYOUT |
| INCLUDING ALL PIPE SIZES, VALVES, VACUUM |
| RELIEF VALVES, CIRCULATION PUMPS, P&T |
| VALVES, PAN DRAINS, THERMAL EXPANSION |
| CONTROL ECT. INDICATE ALL PIPE |
| MATERIALS. SECTION 104.2.1. |
| 24. SHTS P-8 THRU P-12 ALL UNITS WATER |
| RISER DIAGRAMS. WATER HAMMER ARRESTOR |
| REQUIRED AT THE REFRIGERATOR ICE MAKER |
| IN AN "EFFECTIVE RANGE". PDI-WH 201 AND |
| MANUF. INSTALLATION REQUIREMENTS. |
| 25. SHT P-13 FLUSH RING RISER FOR THE |
| TRASH CHUTE REQUIRES BACKFLOW |
| PROTECTION. PLEASE INDICATE THE METHOD |
| OF PROTECTION. SECTION 608. |
| 26. SHT P-13 WATER RISER 13 INDICATES 1" |
| COLD WATER SUPPLY TO WATER HEATERS, BUT |
| HOT WATER RISERS SHOW 2". PLEASE |
| CLARIFY. SECTION 104.2.1. |
| 27. SHT P-14 PLEASE INDICATE MATERIAL |
| USED AND TYPE OF SYSTEM. SECTION |
| 104.2.1. |
| 28. P-16 SANT. RISERS 44A 7 51A. PER |
| SECTION 914.1 A RELIEF VENT IS REQUIRED |
| AT EACH 10TH INTERVAL BEGINING WITH THE |
| TOP FLOOR. |
| 29. SUBMIT A SANITARY HORIZONTAL RISER |
| DIAGRAM IN ISOMETRIC FORM FOR THE |
| BUILDING DRAIN. INDICATE ALL PIPE SIZES |
| AND SHOW THE LOCATION OF ALL RISERS. |
| SHOW DRAINAGE FIXTURE UNITS AS IT |
| ACCUMULATES IN THE SYSTEM. SECTION |
| 104.3.1.1. |
| 30. SUBMIT A STORM ISOMETRIC RISER |
| DIAGRAM FOR THE HORIZONTAL PIPING OF THE |
| BUILDING STORM DRAIN. SHOW ALL PIPE |
| SIZES, RISER LOCATIONS, AND THE SQUARE |
| FOOTAGE AS IT ACCUMULATES IN THE SYSTEM. |
| SECTION 104.3.1.1. |
| 31. SUBMIT STORM RWL RISER DIAGRAMS. |
| SHOW ALL PIPE SIZES, OFFSETS & SQUARE |
| FEET. |
| 32. SHT P-15 RISER 7 FIRST FLOOR TUB |
| MISLABLED AS A SHOWER. SECTION 104.2.1. |
| 33. SHT P-18 RISERS 86, 87, 81, 80 LOWER |
| OFFSET VENTS REQUIRED. (SHOW AT LOWEST |
| OFFSET) SECTION 915.3 |
| 34. SHT P-19 RISER 41 RELIEF VENT |
| REQUIRED. SECTION 914. |
| 35. P-20 SPRINKLER DRAIN DETAIL, DRAIN |
| TO CONNECT TO THE SANITARY SYSTEM, NOT |
| THE STORM AS SHOWN. CITY CODE 90-203. |
| 36. THE FOLLOWING INFORMATION IS |
| REQUIRED FOR GAS PERMIT APPLICATION: |
| A. SUBMIT AN ISOMETRIC DRAWING THAT |
| CLEARLY SHOWS ALL CUT SECTIONS OF PIPE |
| AND CORRESPONDING LENGTHS PER FBC-2001 |
| FUEL GAS CODE. |
| B. SHOW TYPE OF PIPING MATERIAL BEING |
| INSTALLED, ALL PIPE SIZES, (AND THE EDH |
| NUMBER OF CORRUGATED STAINLESS STEEL |
| TUBING FOR EACH PIPE SIZE IF BEING USED. |
| C. TYPE OF GAS, (LP OR NATURAL) |
| D. BTU LOAD OF EACH APPLIANCE AND THE |
| TOTAL BTU LOAD ON THE SYSTEM. REFER TO |
| THE FBC-2001 FUEL GAS CODE SECS. 401.8 |
| THRU 402.5.2 AND TABLES 402(1) THRU |
| 402(34). |
| E. SHOW THE DISTANCE FROM THE POINT OF |
| DELIVERY, (METER), TO THE MOST REMOTE |
| OUTLET IN THE BUILDING AND/OR SYSTEM PER |
| FBC-2001 FUEL GAS CODE APPENDIX A - USE |
| OF CAPACITY TABLES (A)(3). |
| F. SUBMIT CALCULATIONS FOR COMBUSTION |
| AIR (IF APPLICABLE) PER FBC-2001 FUEL |
| GAS CODE SECTION 304. |
| G. INDICATE THE DELIVERY PRESSURE (PSI) |
| PER FBC-2001 FUEL GAS CODE SEC. 402.2. |
| NATURAL GAS SPECIFY .5 PSI OR 2 PSI. |
| H. SUBMIT A DETAIL SHOWING THE TYPE, |
| LOCATION, SIZE AND TERMINATION OF THE |
| GAS VENTS PER FBC-2001 FUEL GAS CODE |
| SECS. 502 THRU 506. |
| I. SUBMIT MANUFACTURE SHEETS FOR ALL GAS |
| EQUIPMENT TO VERIFY COMPLIANCE WITH |
| STANDARDS NFPA 54, NFPA 58, AND THE |
| FBC-2001 FUEL GAS CODE SEC 402.2 |
| J. CLEARLY SHOW THE LOCATION AND CAP- |
| ACITY OF LP TANK(S), TYPE OF TANK (DOT |
| OR ASME), THE DISTANCE OF THE TANK FROM |
| THE BUILDING AND ADJACENT PROPERTY LINES |
| THE DISTANCE OF THE TANK FROM ALL SOUR- |
| CES OF IGNITION, OTHER CONTAINERS, BUILD |
| INGS, AND THE LOCATION OF ANY BUILDING |
| OPENINGS BELOW THE RELIEF VALVE OF THE |
| TANK PER NFPA 58, TABLE 3-2.2.2. |
| K. CLEARLY INDICATE ON THE PLAN IF THE |
| LP TANK IS ABOVE OR BELOW GROUND, AND |
| SHOW REQUIRED PROTECTION OF THE TANK AND |
| APPURTENANCES PER NFPA 58. IF THE TANK |
| IS BELOW GROUND THE CONTAINER SHALL BE |
| SECURILY ANCHORED PER NFPA 58 SECTION |
| 3-2.2.7(H). |
| 37. ALL PLUMBING SHEETS. ENGINEERS SEAL |
| SHALL SHOW ALL INFORMATION REQUIRED BY |
| FAC 61G15-23.001 & FS 481.025 |
| |
| WHEN RESUBMITTING PLANS PLEASE INDICATE |
| THE REVISION & REMOVE & REPLACE ANY |
| PAGES AS NECESSARY. A TRANSMITTAL LETTER |
| LISTING THE ORIGINAL REVIEW COMMENT NUM- |
| BER, WITH A DESCRIPTION OF THE REVISION |
| MADE, IDENTIFYING THE SHEET OR SPECIFICA |
| TION PAGE WHERE THE CHANGES CAN BE FOUND |
| WILL HELP TO EXPEDITE YOUR PERMIT. THANK |
| YOU FOR YOUR ANTICIPATED COOPERATION. |
| |
| REVIEW BY KEN STEVENS |
| (561) 805-6721 |
| FAX (561) 805-6731 |
| E-MAIL [email protected] |