Plan Review Notes
Plan Review Notes For Permit 05091425
Permit Number 05091425
Review Stop P
Sequence Number 1
Notes
Date Text
2005-12-17 00:00:00DENIED
 REFERENCE: FBC-2001 PLUMBING
 FBC-2001 FUEL GAS
 FBC-2001 BUILDING
 FBC-2001 CHAPTER 1
 FBC-2001 CHAPTER 11
 FHA-98 DESIGN MANUAL
 FLORIDA ADMINISTRATIVE CODE
 FLORIDA STATUTES
 WPB CITY CODE
  
 1. PLANS APPEAR TO BE INCOMPLETE AS
 SUBMITTED. MORE COMMENTS MAY BE
 FORTHCOMING NEXT REVIEW.
 2. SHT L-6 MISSING. (SEE INDEX ON SHT
 L-1). SECTION 104.2.1.
 3. SHT A-0.1 INDEX INDICATES THAT SHTS
 A-5.1 THRU A-5.6 HAVE KITCHEN AND
 BATHROOM ELEVATIONS, NOTES & DETAILS.
 THESE SHEETS WERE NOT SUBMITTED. SECTION
 104.2.1.
 4. SHTS A-1.7, A-1.8, A-2.6.1 THRU
 A-2.6.6, SUBMIT CALCULATIONS FOR PRIMARY
 AND SECONDARY ROOF DRAINS FOR ALL ROOFS.
 SHOW THE LOCATION OF ALL SECONDARY ROOF
 DRAINS FOR ALL ROOFS/DECKS.
 5. ALL UNIT TYPES SHALL COMPLY WITH
 FHA-98 DESIGN MANUAL REQUIREMENTS ONE
 THRU SEVEN. SUBMIT DETAILS.
 6. NOT USED
 7. ALL ARCHITECT SHEETS. SEAL OF THE
 ARCHITECT SHALL IMPART INFORMATION
 REQUIRED BY FAC/FS. LITTLE OR NO
 INFORMATION CAN BE GLEANED FROM THE SEAL
 ON SOME SHEETS. PLEASE BE SURE EACH
 SHEET IS SEALED CORRECTLY & INFORMATION
 REQUIRED IS IMPARTED ON EACH SHEET. FAC
 61G1-16.004 & FS 481.2055.
 8. SHT A-2.7.5 SHOW THE LOCATION OF ALL
 SECONDARY DRAINS REQUIRED BY SECTION
 1107.
 9. SHTS A-2.7.5 & A-10.1 MORE
 INFORMATION IS REQUIRED FOR THE
 FOUNTAINS. PLEASE INDICATE IF THERE WILL
 BE WATER SUPPLY LINES AND OR DRAINAGE
 LINES FOR FOUNTAINS. IF WATER SUPPLY
 LINES ARE INSTALLED, BACKFLOW PREVENTION
 IS REQUIRED. IF DRAINS ARE INSTALLED,
 THEY SHALL CONNECT TO THE SANT. SYSTEM
 AND THE OVERFLOW SHALL DRAIN TO STORM.
 PLEASE CLARIFY. SECTIONS 104.2.1 & 608.
 10. SHT A-2.7.5 SEPARATE PERMITS
 REQUIRED FOR THE POOL & SPA POOL.
 (INFORMATIONAL).
 11. SHT P-1 NO PIPING SHOWN TO FLOOR
 DRAINS IN THE TRASH ROOM AND IN THE PUMP
 ROOMS. SECTION 104.2.1.
 12. SHT P-1 NO PIPING SHOWN TO RISERS
 29, 30, & 44 THRU 51. SECTION 104.2.1.
 13. SHT P-1 RISERS 10 & 26 NOT SHOWN ON
 FLOOR PLAN. SECTION 104.2.1.
 14. SHT P-2 NO FLOOR PLANS FOUND FOR THE
 FLOOR PLAN A-1.2. PLEASE CLARIFY.
 SECTION 104.2.1.
 15. SHT P-2 4"-180FU DOWNSTREAM OF RISER
 S/51A IS NOT CORRECT. PLEASE CHECK
 FIGURES. SECTION 104.2.1.
 16. SHT P-2 RECALCULATE FU'S DOWNSTREAM
 OF RISERS 64 & 65. SECTION 104.2.1.
 17. SHT P-2 INDICATE FU VALUE FOR RISERS
 75 & 82. SECTION 104.2.1.
 18. SHT P-4 SUBMIT CALCULATIONS FOR
 PRIMARY AND SECONDARY ROOF DRAINS. SHOW
 SF OF EACH DRAINED AREA PLUS 1/2 AREA OF
 ALL VERTICAL WALLS INCLUDING PARAPETS,
 PLUS THE AREA OF ROOFS THAT DRAIN ONTO
 THE ROOF/DECK AREA FROM ABOVE.
 19. SHT P-4 NUMEROUS RWL'S & DECK DRAINS
 ARE SHOWN FOR DD & PLANTER DRAINS ON THE
 9TH FLOOR, BUT NO PIPING IS SHOWN
 INDICATING WHERE THE DRAINS ARE DRAINING
 TO. PLEASE CLARIFY. SHOW PIPING ON RWL
 RISER DIAGRAMS. ALSO NO RWL'S FOR THESE
 DRAINS ARE SHOWN ON SUBSEQUENT SHEETS.
 SECTION 104.2.1.
 20. SHT P-5 SHOW THE LOCATION OF ALL
 SECONDARY DRAINS REQUIRED IN SECTION
 1107.
 21. SHT P-5 RWL 3200SF NOT SHOWN ON THE
 FLOOR PLAN. (NEAR RISER 79) 104.2.1.
 22. SHT P-7 SUBMIT CALCULATION FOR
 PRIMARY AND SECONDARY ROOF DRAINS. (SEE
 COMMENT #18). SECTIONS 1106 & 1107.
 23. SHT P-7 SUBMIT A DETAIL FOR THE
 BOILER ROOM. SHOW THE PIPING LAYOUT
 INCLUDING ALL PIPE SIZES, VALVES, VACUUM
 RELIEF VALVES, CIRCULATION PUMPS, P&T
 VALVES, PAN DRAINS, THERMAL EXPANSION
 CONTROL ECT. INDICATE ALL PIPE
 MATERIALS. SECTION 104.2.1.
 24. SHTS P-8 THRU P-12 ALL UNITS WATER
 RISER DIAGRAMS. WATER HAMMER ARRESTOR
 REQUIRED AT THE REFRIGERATOR ICE MAKER
 IN AN "EFFECTIVE RANGE". PDI-WH 201 AND
 MANUF. INSTALLATION REQUIREMENTS.
 25. SHT P-13 FLUSH RING RISER FOR THE
 TRASH CHUTE REQUIRES BACKFLOW
 PROTECTION. PLEASE INDICATE THE METHOD
 OF PROTECTION. SECTION 608.
 26. SHT P-13 WATER RISER 13 INDICATES 1"
 COLD WATER SUPPLY TO WATER HEATERS, BUT
 HOT WATER RISERS SHOW 2". PLEASE
 CLARIFY. SECTION 104.2.1.
 27. SHT P-14 PLEASE INDICATE MATERIAL
 USED AND TYPE OF SYSTEM. SECTION
 104.2.1.
 28. P-16 SANT. RISERS 44A 7 51A. PER
 SECTION 914.1 A RELIEF VENT IS REQUIRED
 AT EACH 10TH INTERVAL BEGINING WITH THE
 TOP FLOOR.
 29. SUBMIT A SANITARY HORIZONTAL RISER
 DIAGRAM IN ISOMETRIC FORM FOR THE
 BUILDING DRAIN. INDICATE ALL PIPE SIZES
 AND SHOW THE LOCATION OF ALL RISERS.
 SHOW DRAINAGE FIXTURE UNITS AS IT
 ACCUMULATES IN THE SYSTEM. SECTION
 104.3.1.1.
 30. SUBMIT A STORM ISOMETRIC RISER
 DIAGRAM FOR THE HORIZONTAL PIPING OF THE
 BUILDING STORM DRAIN. SHOW ALL PIPE
 SIZES, RISER LOCATIONS, AND THE SQUARE
 FOOTAGE AS IT ACCUMULATES IN THE SYSTEM.
 SECTION 104.3.1.1.
 31. SUBMIT STORM RWL RISER DIAGRAMS.
 SHOW ALL PIPE SIZES, OFFSETS & SQUARE
 FEET.
 32. SHT P-15 RISER 7 FIRST FLOOR TUB
 MISLABLED AS A SHOWER. SECTION 104.2.1.
 33. SHT P-18 RISERS 86, 87, 81, 80 LOWER
 OFFSET VENTS REQUIRED. (SHOW AT LOWEST
 OFFSET) SECTION 915.3
 34. SHT P-19 RISER 41 RELIEF VENT
 REQUIRED. SECTION 914.
 35. P-20 SPRINKLER DRAIN DETAIL, DRAIN
 TO CONNECT TO THE SANITARY SYSTEM, NOT
 THE STORM AS SHOWN. CITY CODE 90-203.
 36. THE FOLLOWING INFORMATION IS
 REQUIRED FOR GAS PERMIT APPLICATION:
 A. SUBMIT AN ISOMETRIC DRAWING THAT
 CLEARLY SHOWS ALL CUT SECTIONS OF PIPE
 AND CORRESPONDING LENGTHS PER FBC-2001
 FUEL GAS CODE.
 B. SHOW TYPE OF PIPING MATERIAL BEING
 INSTALLED, ALL PIPE SIZES, (AND THE EDH
 NUMBER OF CORRUGATED STAINLESS STEEL
 TUBING FOR EACH PIPE SIZE IF BEING USED.
 C. TYPE OF GAS, (LP OR NATURAL)
 D. BTU LOAD OF EACH APPLIANCE AND THE
 TOTAL BTU LOAD ON THE SYSTEM. REFER TO
 THE FBC-2001 FUEL GAS CODE SECS. 401.8
 THRU 402.5.2 AND TABLES 402(1) THRU
 402(34).
 E. SHOW THE DISTANCE FROM THE POINT OF
 DELIVERY, (METER), TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND/OR SYSTEM PER
 FBC-2001 FUEL GAS CODE APPENDIX A - USE
 OF CAPACITY TABLES (A)(3).
 F. SUBMIT CALCULATIONS FOR COMBUSTION
 AIR (IF APPLICABLE) PER FBC-2001 FUEL
 GAS CODE SECTION 304.
 G. INDICATE THE DELIVERY PRESSURE (PSI)
 PER FBC-2001 FUEL GAS CODE SEC. 402.2.
 NATURAL GAS SPECIFY .5 PSI OR 2 PSI.
 H. SUBMIT A DETAIL SHOWING THE TYPE,
 LOCATION, SIZE AND TERMINATION OF THE
 GAS VENTS PER FBC-2001 FUEL GAS CODE
 SECS. 502 THRU 506.
 I. SUBMIT MANUFACTURE SHEETS FOR ALL GAS
 EQUIPMENT TO VERIFY COMPLIANCE WITH
 STANDARDS NFPA 54, NFPA 58, AND THE
 FBC-2001 FUEL GAS CODE SEC 402.2
 J. CLEARLY SHOW THE LOCATION AND CAP-
 ACITY OF LP TANK(S), TYPE OF TANK (DOT
 OR ASME), THE DISTANCE OF THE TANK FROM
 THE BUILDING AND ADJACENT PROPERTY LINES
 THE DISTANCE OF THE TANK FROM ALL SOUR-
 CES OF IGNITION, OTHER CONTAINERS, BUILD
 INGS, AND THE LOCATION OF ANY BUILDING
 OPENINGS BELOW THE RELIEF VALVE OF THE
 TANK PER NFPA 58, TABLE 3-2.2.2.
 K. CLEARLY INDICATE ON THE PLAN IF THE
 LP TANK IS ABOVE OR BELOW GROUND, AND
 SHOW REQUIRED PROTECTION OF THE TANK AND
 APPURTENANCES PER NFPA 58. IF THE TANK
 IS BELOW GROUND THE CONTAINER SHALL BE
 SECURILY ANCHORED PER NFPA 58 SECTION
 3-2.2.7(H).
 37. ALL PLUMBING SHEETS. ENGINEERS SEAL
 SHALL SHOW ALL INFORMATION REQUIRED BY
 FAC 61G15-23.001 & FS 481.025
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE
 THE REVISION & REMOVE & REPLACE ANY
 PAGES AS NECESSARY. A TRANSMITTAL LETTER
 LISTING THE ORIGINAL REVIEW COMMENT NUM-
 BER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICA
 TION PAGE WHERE THE CHANGES CAN BE FOUND
 WILL HELP TO EXPEDITE YOUR PERMIT. THANK
 YOU FOR YOUR ANTICIPATED COOPERATION.
  
 REVIEW BY KEN STEVENS
 (561) 805-6721
 FAX (561) 805-6731
 E-MAIL [email protected]