Plan Review Notes
Plan Review Notes For Permit 05081909
Permit Number 05081909
Review Stop P
Sequence Number 1
Notes
Date Text
2005-09-08 00:00:00DENIED;
 1. FBC-2001 SEC 424.2.6.1 ENGINEERING
 DESIGN, CONSTRUCTION AND WORKMANSHIP.
 ANSI/NSPI-5. (ADD TO NOTES)
 2. FBC-2001424.2.6.6.2 SHOW COMPLIANCE
 WITH ANSI/ASME A112.19.8M. PROVIDE MODEL
 NUMBER AND MANUF INFO FOR VAC LOCK.
 (GIVE DETAIL, SUBMITTAL OR ADD TO NOTES)
 3.) FBC-2001424.2.6.6.5 WHERE
 PROVIDED, THE VACUUM OR PRESSURE CLEANER
 FITTING SHALL BE LOCATED AT LEAST 6" AND
 NOT GREATER THAN 12" BELOW THE MINIMUM
 OPER- ATING WATER LEVEL OR AS AN
 ATTACHMENT TO THE SKIMMER.
 4. FBC-2001 424.2.8.1 VALVES SHALL BE
 MADE OF MATERIALS THAT ARE APPROVED IN
 THE FLA BLDG CODE, PLUMBING.THEY WILL
 BE READILY ACCESSIBLE FOR MAINT. AND
 REMOVAL.SEC 424.2.8.2 FULL WAY VALVES
 SHALL BE INSTALLED TO INSURE PROPER
 FUNCTION OF THE FILTRATION AND PIPING
 SYSTEMS.SEC 424.2.8.3 WHERE CHECK
 VALVES ARE INSTALLED THEY SHALL BE OF
 THE SWING OR VERTICAL CHECK PATTERNS.
 SEC 424.2.8.4 COMBINATION VALVES SHALL
 REQUIRE APPROVAL OF THE ADMINISTRATIVE
 AUTHORITY PRIOR TO THEIR INSTALLATION.
 5. FBC-2001 424.2.12.1 PRESSURE TESTS.
 PER MANUFACTURE RECOMMENDATIONS, NO AIR
 TEST SHALL BE APPROVED FOR PVC PIPE AND
 FITTINGS. (ADD TO NOTES)
 6)424.2.9 WATER SUPPLY, LOCAL ORD
 #2853-95, BACKFLOW REQUIRED ON WATER
 SERVICE. (ADD TO NOTES)
 7)424.2.13.2 JOINTS AND CONNECTIONS, FBC
 PLUMBING SEC 605.21, PERPLE PRIMER
 REQUIRED ON PVC PIPING. (ADD TO NOTES)
 8)424.2.14.2 WATER RETENTION, PROVIDE A
 POSITIVE MEANS OF RETAINING WATER IN
 HEATER WHEN PUMP IS SHUT OFF. ( ADD TO
 NOTES)
 PLUMBING PLAN REVEW BY;
 JOHN LEECH
 805-6695