Date |
Text |
2006-09-23 00:00:00 | PLAN DENIED |
| 1) PLEASE REFER TO SECTION 104.2.1.3 |
| CHAPTER ONE AMENDMENTS 2001 QUALITY OF |
| PLANS PAGES AC-1 - AC-9. |
| 2) GARAGE VENTLATION MUST BE TIED IN TO |
| EMERGENCY POWER,SO FANS CAN RUN WHEN |
| POWER FAILS. |
| 3) PAGE AC-12 NEED RETURN AIR FOR |
| ELEVATOR LOBBY TOWER # 7. |
| 4) PAGE AC-12 ALL TRASH ROOM A/C MARKED |
| # 10,0N HEAT PUMP SCHEDULE A/C ARE |
| MARKED 33 - 40 PAGE AC-36. |
| 5) PAGE AC-01 PLEASE REMOVE EF-38 FRON |
| PLANS IF NOT BEING USED. |
| 6) PAGE AC-12 PLEASE PROVIDE DUCT SIZE |
| FOR A/C # 9 BEFOR 6X6 DUCT. |
| 7) PAGE AC-10 CAN NOT FIND DUCT |
| CONTINUATION ON PAGE AC-01. |
| 8) PAGE AC-2 PLANS AND DRAWING NOTES DO |
| NOT MATCH. |
| 9) PAGE AC-13 AND A LOT OF THE PLANS |
| HAVE PRINT ON TOP OF PRINT CAN NOT READ |
| PLANS. |
| 10) PAGE AC-13 SMOKE EVAC.? |
| 11) PAGE AC-13 PLEASE REFER TO DASHED |
| LINES FOR RETURN AIR PLENUM. |
| 12) PAGE AC-14 PLEASE INDECATE SIZE OF |
| RETURN AIR DUCT FOR A/C # 15 |
| 13) PAGE AC-14 PLEASE INDECATE DUCT SIZE |
| OF FLEX OFF SUPLY PLENUM ON A/C # 15. |
| CAN WE PLEASE SET UP A MEETING AFTER |
| OCTOBER 2 TO GO OVER THE PLANS. |
| PLAN REVIEW BY HAROLD MOSER 561-805-6732 |