2007-06-27 12:02:16 | -----------------DENIED-------------------- |
| |
| FBC 2001 CODE FAMILY |
| |
| 1. PG M3: AHU 15 & 16, RECIRCULATION OF AIR FROM LOCKER |
| ROOMS AND TOILET ROOMS IS PROHIBITED PER FBC,M TABLE |
| 403.3(B). NOTE #13 CALLS FOR LOUVERED DOORS IN LOCKER |
| ROOMS FOR RETURN. THERE ARE TWO OPTIONS FOR CODE |
| COMPLIANCE: |
| A) REPLACE LOUVER DOOR WITH A SOLID DOOR, PROVIDING |
| DOOR GASKET AND SEALED THRESHOLD TO ISOLATE RETURN FROM |
| BATHROOM/LOCKER ROOM AREA. |
| B) PROVIDE A DUCTED RETURN TO RUN CONTINUOUS FROM |
| RETURN GRILL IN WALL TO THE RETURN INLET ON AHU'S. |
| |
| 2. AHU 16 RETURN IS LOCATED IN A STORAGE ROOM WHERE IT |
| WILL BE ISOLATED FROM RETURNING ANY OF THE 1085 CFM |
| SUPPLIED TO THE STAGE AREA.. BALANCED RETURN IS |
| REQUIRED PER FBC,M 601.4. |
| |
| 3. AHU'S 15 AND 16 SHOW 1380 CFM OF SUPPLY, BUT ARE |
| RATED FOR 5 TONS OF COOLING. ADDISON UNITS SHOW 900 OR |
| 1100 CFM SUPPLY BUT ARE RATED FOR 5 OR 6 TONS OF |
| COOLING. PLEASE PROVIDE COOLING LOAD CALCULATIONS, |
| REVISED ENERGY CALCULATIONS AND MANUFACTURER'S DATA |
| SHOWING THE EQUIPMENT WILL FUNCTION AS INTENDED WITHIN |
| THESE DESIGN PARAMATERS. |
| |
| 4. PLEASE PROVIDE ARCHITECTURAL PLANS SHOWING THE |
| LOCATION OF ALL RATED WALLS TO VERIFY THE LOATION OF |
| ALL FIRE DAMPERS RELATED TO THESE WALLS PER FBC,M |
| 607.1.2. |
| |
| NOTE: THE RETURN OPENINGS IN THE BLOCK WALLS IN THE |
| GYMNASIUM, HAVE PROVISIONS BEEN MADE TO PROVIDE |
| ADDITIONAL SUPPORT AT THESE OPENINGS, SUCH AS LENTILS? |
| |
| IF YOU HAVE ANY QUESTIONS PLEASE CONTACT: |
| |
| RONALD J REGUEIRO |
| 561.805.6719 |
| [email protected] |