2007-06-09 18:50:31 | ** UNSAT ** |
| SHEETS E 2.02, 2.02C, 4.10 AND 5.01 HAVE COMMENTS. ALL |
| OTHER SHEETS STAMPED AS REVIEWED. |
| |
| 1) NOTE: PLEASE SEE PHOTO-METRICS ON WEST SIDE OF |
| BUILDING DOES NOT INDICATE THE ENTIRE EGRESS PATH ON |
| STAIRS FOR POINTS CALCULATED. THE AREA BY THE HAND |
| RAILS IS ONLY PART OF THE STAIRS. |
| PLEASE SEE LS 101 7.8.1.3, 7.9.2. |
| PLEASE SEE THE CIRCUITING ON PLANS INDICATES EM-1, YET |
| EM-1 ON PANEL SCHEDULE DOES NOT COORDINATE WITH THIS. |
| ALL THREE STAIRS ARE NOTED WITH THE SAME EM-1. |
| PLEASE REVISE E2.02, 2.02C. |
| |
| 2) NOTE: PLEASE SEE RISER WHICH INDICATES MDH AS |
| 900AMPS WHICH THE CONDUCTORS AS SHOWN ON SCHEDULE WOULD |
| NOT MEET 240.4C |
| PLEASE SEE SHEET 5.01 AS THIS SHOWS AN 800AMP BUS AND A |
| 700AMP MAIN? |
| PLEASE BE SURE TO COORDINATE THIS MAIN AND ANY OTHERS |
| BEFORE SUBMITTING REVISIONS. |
| |
| 3) NOTE: AS NOTED, PLEASE SEE THE GROUNDING DETAIL ON |
| 5.10 WHICH INDICATES *FENCE STEEL AS PART OF THE |
| GROUNDING ELECTRODE SYSTEM AT CHILLER PLANT. THIS SEEMS |
| TO BE A MISPRINT. THIS WAS CONFIRMED WITH GC |
| SUPERINTENDENT THAT THIS IS THE FOOTER STEEL. THIS WAS |
| REDLINED ON THIS SHEET AND STAMPED. |
| |
| |
| **OTHER PLAN SHEETS SUBMITTED STAMPED. |
| |
| ** IF THERE ARE ANY QUESTIONS, PLEASE CALL. |
| |
| DEWEY PALMER |
| ELECTRICAL PLAN REVIEW II |
| CONSTRUCTION SERVICES DEPARTMENT |
| CITY OF WEST PALM BEACH. |
| 561-805-6717 |