Date |
Text |
2007-06-18 09:47:17 | FBC 2001 |
| |
| SUBMITTAL #05100.02. ONLY SOME OF THE INFORMATION |
| SUBMITTED WILL BE APPROVED. THOSE ITEMS WHICH ARE |
| APPROVED WILL BE STAMPED. THE OTHER ITEMS WILL BE |
| RETUNED. THE SUBMITTALS BY KENNETH J. PAGANO, PE #58131 |
| ARE OK.THE INFORMATION BY SCOTT L. SCHURWAN PE |
| #31867, IS MISSING THE PRINTED NAME AND NUMBER/THE DATE |
| AND THE SIGNATURE ON SOME OF THE SUBMITTALS WERE |
| STAMPED WHICH IS NOT ACCEPTABLE. SEE F.A.C. |
| 61G15-23.002(1)A PROFESSIONAL ENGINEER SHALL SIGN HIS |
| NAME AND AFFIX HIS SEAL TO ALL PLANS, SPECIFICATIONS, |
| REPORTS, FINAL BID DOCUMENTS BEING FILED FOR PUBLIC |
| RECORD. THE DATE THAT THE SIGNATURE AND SEAL IS AFFIXED |
| AS PROVIDED HEREIN SHALL BE ENTERED ON SAID PLANS, |
| SPECIFICATIONS, REPORTS, OR OTHER DOCUMENTS IMMEDIATELY |
| UNDER THE SIGNATURE OF THE PROFESSIONAL ENGINEER. |
| |
| (2) A COVER OR INDEX SHEET FOR ENGINEERING |
| SPECIFICATIONS MAY BE USED AND THAT SHEET MUST BE |
| SIGNED, SEALED AND DATED BY THOSE PROFESSIONAL |
| ENGINEERS IN RESPONSIBLE CHARGE OF THE PRODUCTION AND |
| PREPARATION OF EACH SECTION OF THE ENGINEERING |
| SPECIFICATION WITH SUFFICIENT INFORMATION ON THE COVER |
| SHEET OR INDEX SO THAT THE USER WILL BE AWARE OF EACH |
| PORTION OF THE SPECIFICATION FOR WHICH EACH |
| PROFESSIONAL ENGINEER IS RESPONSIBLE. SEE F.A.C. |
| 61G15-23.002 |
| |
| MYRON JACOBS |
| BUILDING PLAN REVIEWER |
| 805-6726 |
| |