2005-03-02 00:00:00***** UNSAT *****
  
 1)NOTE: PLEASE SEE BLDG/FIRE AND
 MECHANICAL REVIEW NOTES FOR "ATRIUM".
 IT IS MY UNDER STANDING A VARIANCE IS TO
 BE APPLIED FOR WHICH MAY OR MAY NOT
 AFFECT ELECTRICAL PLANS.
  
 2)NOTE: PLEASE SEE A DETAILED LETTER(?)
 WILL BE REQUIRED FOR PHASE II AND SHUT
 DOWN OF ELECTRICALEQUIPMENT BEFORE
 PULLING IN CONDUCTORS ETC.
  
 3)NOTE: PLEASE SEE RESPONSE LTR
 MENTIONS; "THE LIGHTNING PROTECTION
 SYSTEM UNDER THE ELECTRICAL CONTRACTOR'S
 PERMIT (OR) A SEPARATE SUBCONTRACTOR
 PERMIT". PLEASE SEE SINCE LIGHTNING
 PROTECTION SYSTEM HAS BEEN REMOVED FROM
 PLANS. THIS WILL BE REQUIRED TO BE UNDER
 SEPARATE PERMIT AND MAY NOT BE UNDER
 ELECTRICAL CONTRACTORS BASEBUILDING
 ELECTRICAL PERMIT.
  
 4)NOTE: PLEASE SEE RESPONSE LTR TO NOTE
 #4 FROM PREVIOUS REVIEW WHICH MENTIONS;
 A)L2B3: "THIS PANEL IS A SPARE PANEL FOR
 FUTURE LOADS".
 PLEASE CLARIFY, PANEL SCHEDULE FOR L2B3
 CONTAINS NUMEROUS CIRCUITS AND LOADS??
  
 5)NOTE: PLEASE SEE NOTE #4 FROM PREVIOUS
  
 REVIEW; RESPONSE LTR PART;
 H) L1A2: RISER TO BE CHANGED TO 125A,
 FEEDER SIZE WILL BE CHANGED
 ACCORDINGLY".
 PLEASE SEE PANEL ON RISER NOW MENTIONS
 150A MLO, AND PANEL INDICATES 150A MCB.
 PLEASE SEE INCREASE FROM LTR NOTING 125A
 WHICH IS FINE, HOWEVER RISER INDICATES
 MLO, WHEN MCB IS REQUIRED FOR SECONDARY
 SIDE OF TRANSFORMER.
 THIS SEEMS TO BE A MISPRINT?
  
 6)NOTE: PLEASE SEE EH2 IS A 200MCB FED
 FROM MSB WITH A 200A BRKR. THIS IS OK,
 HOWEVER FEED FROM GENERATOR INDICATES A
 400A BRKR FEEDING 400A ATS AND THEN TO
 200A RATED PANEL/BRKR.
 PLEASE VERIFY THIS.
 PLEASE ALSO VERIFY CONDUCTORS/CONDUITS
 FROM GENERATOR TO NEW DISC'S, DISC'S
 BACK TO ATS AND ATS TO PANELS EH2.
 PLEASE VERIFY IF A TAP RULE IS OF SOME
 SORT IS BEING APPLIED.
 PLEASE ALSO SEE POSSIBLE VOLTAGE DROP.
  
 7)NOTE: PLEASE SEE MANUFACTURE CUT/SPECS
 SHEETS STILL REQUIRED FOR FIRE PUMP/
 FIRE PUMP CONTROLLER, ATS, GNERATOR AND
 SUB BASE FUEL FOR LIQUID TYPE FUELS.
 SPECS BOOKS DO NOT SEEM TO SPECIFICALLY
 DESIGNATE EQUIPMENT, SIZES ETC.
  
  
 8)NOTE: PLEASE SEE SPEC BOOK PAGE
 16075-8, MENTIONS BROWN, ORANGE, YELLOW
 FOR 277/480V SYSTEMS.
 PLEASE SEE "B" IS NOT A HIGH-LEG FOR
 277/480V. PLEASE SEE LOCAL AMENDMENTS
 FOR BR/ PURPLE/ YELLOW.215
  
 9)NOTE: PLEASE SEE ONLY SET OF SPECS
 BOOKS WERE SUBMITTED, PLEASE SUBMIT TWO
 MORE SETS FOR REVIEW.
  
 PLEASE SEE DUE TO HAND WRITTEN NOTES
 ADDED FOR LOCKED ROTOR FOR FIRE PUMP ETC
 ANDCOMMENTS FOR CONDUCTORS/ CONDUITS
 AND PANEL L1A2, PLEASE REVISE AND
 REPRINT NEW RISER DIAGRAM SHEET.
  
 PLEASE SEE ANY POSSIBLE COMMENTS FROM
 OTHER REVIEWER(S) WHICH MAY AFFECT
 ELECTRICAL PLANS.
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE DO NOT HESITATE TO CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 CITY OF WEST PALM BEACH
 CONSTUCTION SERVICES DEPT.
 561-805-6717
 [email protected]
  
  
  