2005-02-04 00:00:00 | ****CORRECTIONS**** |
| |
| SAMANTHA HILL, BUILDING PLANS EXAMINER |
| [email protected] |
| |
| 1.)THE PLANS FOR THE STRUCTURE APPEAR |
| TO CONFLICT WITH THE EXISTING BUILDING. |
| TYPE VI IS DECLARED (DWG |
| #XP-N-00-02-FL).THE ADDITION IS TO BE |
| OF THE SAME BUILDING TYPE AS THE |
| EXISTING. |
| |
| 2.)IS THIS BUILDING SPRINKLED?NOTE |
| ON THE PLAN.SPRINKLERS REQUIRED AT |
| NEW |
| AREAS FOR ADDITIONS TO SPRINKLED |
| BUILDINGS.PLEASE NOTE EXISTING |
| BUILDING CONDITION ON THE PLAN. |
| |
| 5.)THE PLAN FOR THE ROOFTOP STRUCTURE |
| ALSO DECLARE A BUSINESS OCCUPANCY, THEN |
| STATES THAT IT "SHALL NOT BE LOCATED |
| WHERE ACCESSIBILITY IS REQUIRED". |
| BUSINESS OCCUPANCY REQUIRES |
| ACCESSIBILITY.THE PLAN PREPARED BY |
| MORRISON HERSCHFIELD INDICATE THAT THIS |
| IS UNINHABITABLE.IF THIS STRUCTURE |
| HAS |
| A BUSINESS OCCUPANCY AS DECLARED, SHOW |
| COMPLIANCE WITH FBC CHAPTER 11. |
| |
| 6.)SHOW OCCUPANCY SEPARATION |
| COMPLIANCE (BETWEEN THE EXISTING |
| STRUCTURE AND NEW), FBC CHAPTER 7. |
| |
| 6.)THE PLAN FOR THE ROOFTOP STRUCTURE |
| DECLARES HVHZ; CITY OF WEST PALM BEACH |
| IS NOT IN THE HVHZ. |
| |
| 7.)A TITLE BLOCK IS REQUIRED FOR THE |
| ENGINEER (PLANS FOR ROOFTOP STRUCTURE). |
| IF PRECISION QUINCY CORP IS THE TITLE |
| BLOCK FOR THE ENGINEER, A CERTIFICATE |
| OF AUTHORIZATION NUMBER IS TO BE ON THE |
| PLAN.THE PRINTED NAME AND LICENSE |
| NUMBER OF THE PERSON SEALING THE |
| DOCUMENT IS TO BE ON THE PLAN. |
| FAC61G15-23.002. |
| |
| 8.)THE TWO SETS OF PLANS PREPARED BY |
| MORRISON HERSCHFIELD ARE NOT THE SAME. |
| ONE IS DATED 8/27, REVISION 2.THE |
| OTHER HAS AN UNDATED SEAL, REVISION 4. |
| PLEASE DATE FAC61G1-15, AND SUBMIT TWO |
| IDENTICAL SETS. |
| |
| 9.)A-S3, PROVIDE THE PRESCRIPTIVE |
| STRENGTH FOR THE GUARDRAIL COMPLIANT |
| WITH FBC1608.2.2(1) THROUGH (4). |
| |
| 10.) I AM STILL UNABLE TO FIND THE ROOF |
| DESIGN PRESSURE ON THE PLAN.SEE THE |
| PREVIOUS LISTS, SPECIFICALLY ITEM #2 ON |
| PREVIOUS LIST.DPS CANNOT BE SPECIFIED |
| BY THE ROOFER. |
| |
| 11.)SEE THE PREVIOUS LIST, ITEM #7. |
| PROVIDE CALCULATIONS FOR THE EXISTING |
| ROOF STRUCTURE AND ITS ABILITY TO |
| ACCOMODATE THE NEW EQUIPMENT.THE |
| CALCULATIONS REFER TO COLUMN CHECK, |
| SHEAR WALL CHECK, FOUNDATION CHECK. |
| WHAT ABOUT THE ROOF DECK? |
| |
| 12.)PROVIDE A DATE FOR THE SEAL FOR |
| THE CALCS AND THE CERTIFICATE OF |
| AUTHORIZATION NUMBER ON THE CALCS. |
| SECOND TIME FOR THIS COMMENT; PLEASE |
| COMPLY.THIS IS A REQUIREMENT FOR ALL |
| DOCUMENTS. |
| |
| 13.)FS553.80(2)(B), 4X FEE WILL BE |
| CHARGED, SEE ATTACHED. |