Date |
Text |
2004-05-07 00:00:00 | 1) WET FIRE HYDRANTS ARE REQUIRED |
| PRIOR TO, DURING AND AFTER CONSTRUCTION. |
| |
| 2) ELECTRONIC SWITCHES, CHAIN AND LOCK |
| REQUIRED ON FIRE LINE BACKFLOW DEVICE. |
| |
| 3) SUITABLE ROADS ARE REQUIRED FOR |
| FIRE AND PARAMEDICAL EQUIPMENT DURING |
| CONSTRUCTION. |
| |
| 4) ALL EXTERIOR STAIRS SHALL BE PROVIDED |
| WITH HANDRAILS ON BOTH SIDES. |
| |
| 5) PLEASE PROVIDE PRESCRIPTIVE STRENGTH |
| REQUIREMENTS FOR ALL HANDRAILS. |
| |
| 6) A KNOX-BOX WILL BE REQUIRED FOR |
| THE BUILDING. |
| |
| 7) KNOX-BOX LOCKING CAPS WILL BE |
| REQUIRED FOR THE FIRE DEPARTMENT |
| CONNECTION. |
| |
| 8) THE DUMPSTER ENCLOSURE SHALL |
| NOT INTERFERE WITH ACCESS TO THE |
| PROPOSED FIRE HYDRANT. |
| |
| 9) IT APPEARS THAT THE FIRE MAINS ARE |
| DEAD-ENDED IN ALL LOCATIONS. FIRE |
| MAINS SHALL BE LOOPED WHENEVER POSSIBLE. |
| |
| 10) PLEASE EXPLAIN VEHICLE TURN-AROUND. |
| ALL DEAD-ENDS OVER 150 FEET SHALL BE |
| PROVIDED WITH APPROVED TURN-AROUNDS |
| FOR EMERGENCY EQUIPMENT. THE ONE |
| DEPICTED ON THE PLANS DOES NOT MEET |
| EITHER OF THE THREE SHOWN IN NFPA 1, |
| CHAPTER 3. |
| |
| 11) SEPARATE PLANS AND PERMITS |
| REQUIRED FOR FIRE ALARM SYSTEM. THE |
| FIRE ALARM SYSTEM SHALL BE UL LISTED |
| FOR CENTRAL STATION SERVICE. |
| |
| 12) FIRE SPRINKLER NOTES INDICATE A |
| LIGHT HAZARD DESIGN. WHAT TYPE OF |
| OCCUPANCIES ARE PLANNED FOR THE |
| BUILDING. WHAT TYPES OF MATERIAL WILL |
| BE STORED IN THE BUILDING. IS STORAGE |
| PLANNED AT HEIGHTS OF 8 OR GREATER THAN |
| 12 FEET. ALSO WILL ANY HAZARDOUS OR |
| FLAMMABLE MATERIALS BE STORED IN THE |
| BUILDING. |
| |
| 13) PLEASE DISPLAY RISE, RUN AND TREAD |
| DEPTH FOR ANY STAIRS THAT ARE PLANNED. |
| |
| MIKE CARSILLO, ASSISTANT FIRE MARSHAL |
| 835-2910 |