Date |
Text |
2004-05-03 00:00:00 | PLUMBING PLAN REVIEW, DENIED FBC 2001 |
| (1)SEC 104.6.5 BUILDING PERMIT VALUATION |
| VALUATION BASED ON TOTAL REPLACEMENT VAL |
| UE TO INCLUDE STRUCTAL, ELECTRIC,PLUMBIN |
| G, MECHANICAL, INTERIOR FINISH, NORMAL |
| SITE WORK, ARCHITECTURAL AND DESIGN FEES |
| EXCLUDING ONLY LAND VALUE. |
| (2) ADD THE FOLLOWING TO PLUMBING NOTES. |
| SEC 424.2.6.6.5 WHERE PROVIDED, THE |
| VACUM OR PRESSURE CLEANER FITTING SHALL |
| BE LOCATED AT LEAST 6" AND NOT GREATER |
| THAN 12" BELOW THE MINIMUM OPERATING |
| WATER LEVEL, |
| SEC 424.2.9 WATER SUPPLY, LOCAL ORDANCE |
| #2853-95 BACK FLOW PREVENTER REQUIRED |
| ON WATER SERVICE, PRIOR TO COMMENCING |
| WORK. |
| SEC 424.2.12.1 PRESSURE TEST. NO AIR |
| TEST WILL BE APPROVED FOR PVC PIPE. |
| SEC 424.2.13.2 JOINTS AND CONNECTIONS |
| PURPLE PRIMER, REQUIRED ON PVC PIPING. |
| SEC 424.2.14.2 WATER RETENTION, PROVIDE |
| A POSITIVE MEANS OF RETAINING WATER IN |
| THE HEATER WHEN THE PUMP IS SHUT OFF. |
| SEC 424.2.14.4 CONNECTIONS, ALL WATER |
| HEATING HEATING EQUIPMENT SHALL BE INSTA |
| LLED WITH FLANGES OR UNION CONNECTIONS |
| ADJACENT TO THE WATER HEATER. |
| SEC 424.2.15 GAS PIPING, SEPERATE PLANS |
| AND PERMIT REQUIRED. |
| END OF COMMENTS QUESTIONS 561-805-6692 |