2003-08-09 00:00:00DENIED
 REFERENCE: FBC-2001 424.2 SWIMMING POOLS
  
 A) PLEASE ADJUST YOUR NOTES, DETAILS, OR
 SUBMITTALS TO REFLECT THE FOLLOWING IN-
 FORMATION REQUIRED FOR PLAN REVIEW
 1) COMPLY WITH FBC-2001 SEC 424.2
 PRIVATE SWIMMING POOLS.
 2) FBC-2001 SEC 424.2.6.1 ENGINEERING
 DESIGN, CONSTRUCTION AND WORKMANSHIP.
 ANSI/NSPI-5. (ADD TO NOTES)
 3) FBC-2001 SEC 424.2.6.6 ENTRAPMENT
 PROTECTION FOR SUCTION INLETS. (DETAIL)
 4) FBC-2001424.2.6.6.2 SHOW COMPLIANCE
 WITH ANSI/ASME A112.19.8M. PROVIDE MODEL
 NUMBER AND MANUF INFO FOR VAC LOCK.
 (GIVE DETAIL OR ADD NOTE)(SUBMITTAL)
 5) FBC-2001424.2.6.6.3 (1,2,3) ENTRAP-
 MENT AVOIDANCE. (DETAIL)
 6) FBC-2001424.2.6.6.5 WHERE PROVIDED,
 THE VACUUM OR PRESSURE CLEANER FITTING
 SHALL BE LOCATED AT LEAST 6" AND NOT
 GREATER THAN 12" BELOW THE MINIMUM OPER-
 ATING WATER LEVEL OR AS AN ATTACHMENT TO
 THE SKIMMER. (DETAIL)
 7) FBC-2001424.2.7.1 POOL CIRCULATING
 PUMPS SHALL BE EQUIPPED ON THE INLET
 SIDE WITH AN APPROVED TYPE HAIR AND LINT
 STRAINER WHEN USED WITH A PRESSURE FIL-
 TER. (DETAIL) (NOTES)
 8) FBC-2001 424.2.7.2 PUMPS AND EQUIP-
 MENT SHALL BE MOUNTED ON A SUBSTANTIAL
 BASE IN A MANNER THAT WILL ELIMINATE
 STRAIN ON PIPING. SLAB SHALL BE A NOMIN-
 AL 4" THICK. (DETAIL)
 9) FBC-2001 424.2.9 WATER SUPPLY, LOCAL
 ORD. #2853-95, BACKFLOW REQUIRED ON
 WATER SERVICE. (ADD TO NOTES)
 10) FBC-2001 424.2.12.1 PRESSURE TESTS.
 PER MANUFACTURE RECOMMENDATIONS, NO AIR
 TEST SHALL BE APPROVED FOR PVC PIPE AND
 FITTINGS. (ADD TO NOTES)
 11) FBC-2001 424.2.13.2JOINTS AND CON-
 NECTIONS, FBC PLMG SEC 605.21, PURPLE
 PRIMER REQUIRED ON PVC PIPING. (ADD TO
 NOTES)
 12) FBC-2001 424.2.14.1 SWIMMING POOL
 WATER HEATERS SHALL BEAR THE LABEL OF A
 RECOGNIZED TESTING AGENCY. MANUFACTURE
 SHEETS REQUIRED. (SUBMITTAL)
 13) FBC-2001 424.2.14.2 WATER RETENTION,
 PROVIDE A POSITIVE MEANS OF RETAINING
 WATER IN THE HEATER WHEN PUMP IS SHUT
 OFF. (MANUFACTURE CUT SHEETS SUBMITTAL)
 14) FBC-2001 424.2.14.4 CONNECTIONS, ALL
 WATER HEATING EQUIPMENT SHALL BE INSTAL-
 LED WITH FLANGES OR UNION CONNECTIONS
 ADJACENT TO THE HEATER. (ADD TO NOTES)
 15) FBC02001 424.2.15 GAS PIPING SHALL
 COMPLY WITH FBC FUEL GAS. SEPARATE PLANS
 AND PERMIT REQUIRED. (NOTES)
 16) SUBMIT A PIPING SCHEMATIC SHOWING
 ALL PIPE SIZES, VALVES, PUMP, FILTER,
 HEATER, BYPASS, VACUUM, SKIMMER, MAIN
 DRAINS FOR POOL & SPA, RETURN LINES ECT.
 17) TIME CLOCK SHALL BE INSTALLED PER
 SECTION 13-612.1.ABC.2.3.3 ENERGY CODE.
  
 REVIEW BY KEN STEVENS
 (561) 805-6721
 FAX (561) 653-2692
 E-MAIL [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved