Date |
Text |
2003-09-30 00:00:00 | SHEET A1.0 NOW DECLARES UL DESIGN U 906 |
| FOR THE FIRE RATED STAIRS.U 906 |
| INVOKES 6" PROPRIETARY BLOCK FOR THE |
| DESIGN. |
| THE PLANS INDICATE 8" BLOCK FOR THE |
| STRUCTURAL.PLEASE REVISE AS NECESSARY. |
| |
| SHEET A1.0 CALLS FOR HANDRAILS TO BE |
| DESIGNED FOR 50 PLF IN ANY DIRECTION. |
| THIS DOES NOT COMPLY WITH FBC 1608.2.1. |
| |
| THE 90# LIVE LOAD SHOWN FOR THE STORAGE |
| AREA ON SHEET A2.0 IS LESS THAN THE |
| MINIMUM 125# LIVE LOAD FOR LIGHT |
| STORAGE IN FBC TABLE 1604.1. |
| PLEASE REVISE AS NECESSARY. |
| |
| SHEET A1.1 MAKES NOTE OF FIRE |
| SPRINKLERSIF THE BUILDING IS TO HAVE |
| FIRE |
| SPRINKLERS, THE DESIGN IS REQUIRED TO |
| BE ON THE PERMIT PLANS.SEE FBC |
| 104.3.1.1 #4. |
| |
| AS PREVIOUSLY NOTED, SEE FBC 104.2.1.1 |
| FOR THE ROOF COVERING DESIGN |
| INFORMATION NECESSARY ON THE PLANS. |
| |
| THE PREVIOUS CHECK LIST REQUESTED THE |
| DESIGN INFORMATION FOR THE PRE-CAST |
| CONCRETE FLOOR SYSTEM.SEE CHAPTER |
| 61G15-30 RESPONSIBILITY RULES COMMON TO |
| ALL ENGINEERS, OF THE FL ADMINISTRATIVE |
| CODE AS PERTAINS TO DELEGATING |
| ENGINEERING REQUIREMENTS. |
| |
| HOW WILL THE #4@12" OC TERMINATE IN |
| THE B1 BEAM FOR THE BALCONY SHOWN ON |
| SHEET S1.1? |
| |
| THE BALUSTRADE CONNECTION DETAIL ON |
| SHEET A1.1 IS SOMEWHAT VAGUE WITH ITS |
| >>1/2" DOWEL TOP AND BOTTOM <<.WHAT |
| ISTHE EMBEDMENT DEPTH OF THE DOWEL(S)? |
| WILL THEY BE CAST IN PLACE?SEE FBC |
| 1608.2.2 FOR MINIMUM DESIGN LOADING AND |
| PROVIDE SUPPORTING CALCULATIONS TO |
| DEMONSTRATE COMPLIANCE WITH SAME. |
| SEE ALSO, FBC 1015 FOR MINIMUM GUARD |
| RAIL DIMENSIONS AND NOTE SAME IN THE |
| DESIGN CRITERIA. |