2003-05-05 00:00:00 | BUILDING DENIED |
| |
| 1) A RECORDED COPY OF THE NOTICE OF |
| COMMENCEMENT MUST BE SUBMITTED BEFORE A |
| PERMIT CAN BE ISSUED. |
| |
| 2) PROVIDE A SOIL BORING TEST REPORT AS |
| REQUIRED BY THE CITY AMENDMENTS TO THE |
| FBC 1804.2.2. |
| |
| 3) THE COVERED PATIO SHOWN ON THE |
| SURVEY DOES NOT MATCH THE PLANS. |
| |
| 4) SPECIFY THE LENGTH/EMBEDMENT DEPTH OF |
| THE 1/2" DIAMETER EXPANSION ANCHORS USED |
| AT THE WOOD FRAME TO CONCRETE WALL |
| CONNECTION ON SHEET A6. |
| |
| 5) THE COLUMN SCHEDULE ON S1 SPECIFIES |
| TWO 2X4S FOR POST C2 AND THE NOTE ON THE |
| FOUNDATION PLAN AT C2 SPECIFIES THREE |
| 2X4S FOR THE POST. PLEASE CLARIFY. |
| |
| 6) STRESS INCREASES FOR THE SHORT TERM |
| LAOD OF STEEL ARE NO LONGER ALLOWED TO |
| BE TAKEN BY FBC 1609.4.3. SEE THE 2003 |
| USP CATALOG FOR LOAD VALUES THAT DO NOT |
| INCLUDE A STRESS INCREASE ON THE STEEL |
| CALCULATIONS. PLEASE REVISE THE |
| CONNECTOR UPLIFT VALUES ACCORDINGLY. |
| |
| 7) PLEASE REVISE NOTE #7 UNDER EXTERIOR |
| SOFFIT SPECS. ON A5 TO INDICATE THAT |
| 3/8" HIGH RIB METAL LATH IS REQUIRED TO |
| BE FASTENED AT EVERY RIB (4"O.C.) PER |
| ASTM C 1063. PLEASE CORRECT. |
| NOTES 4 AND 5 ARE THE SAME. |
| |
| 8) PROVIDE A PRODUCT APPROVAL FOR THE |
| OUTSWING GLAZED DOOR AT THE CABANA BATH. |
| |
| ROBERT MCDOUGAL |
| BLDG. PLAN REVIEW |
| (561)659-8096 EXT.8202 |