Plan Review Notes
Plan Review Notes For Permit 03020961
Permit Number 03020961
Review Stop E
Sequence Number 2
Notes
Date Text
2003-05-01 00:00:00********* UNSAT **********
  
 1)NOTE: PLEASE SEE E-1, THERE ARE FEEDER
 /CONDUIT NOTES FOR MAINS 1 ETC. NOTES
 MENTION SEE "NOTE 7&9?ON WHICH PAGE
 WOULD THIS BE?
  
 2)NOTE: PLEASE SEE RISER DIAGRAM AND
 E-1. E-1 SEEMS TO SHOW MAIN #2 AS BUS
 STAB AND RISER SHOWS CONDUIT/FEEDERS?
 PLEASE CORRELAT/CLARIFY.
  
 3)NOTE: PLEASE SEE E-1, SHOWS MULTIPLE
 LINES COMING FROM HDP, RISER ONLY SHOWS
 2LINES COMING OUT AND GOING UP TO ROOF.?
 CONDUITS THAT APPEAR TO COME FROM XDP
 ON RISER DIAGRAM SEEM TO BE SHOWN COMING
 FROM HDP ON E-1? PLEASE CORRELATE. PANEL
 HB? ETC
 4)NOTE: PLEASE SEE E-13, IT APPEARS TO
 SHOW FEEDERS FOR MAIN 3 COMING OVERHEAD.
 PLEASE NOTE, AS PER LOCAL AMENDMENTS,
 NO MORE THAN 8' OF UNPROTECTED CONDUCTOR
 -S ARE PERMITTED INTO BLDG. PLEASE SHOW
 AS EITHER UNDERGROUND OR COMPLETE CONCR-
 -ETE ENCASEMENT. 230-70 LOCAL AMEND.
  
 5)NOTE: PLEASE CLARIFY FIXTURE TYPE FOR
 ELEVATOR EQUIPMENT ROOM AND OTHER ROOMS
 THAT REQUIRE EMERGENCY LIGHTING REQ`D TO
 MEET 700-16? SOME OTHER LOCATIONS SHOW
 ROOMS AND TYPE OF FIXTURES REFERENCE
 BACK TO FIXTURE SCHEDULE.FIX SCH, DETAIL
 -S DUAL BALLAST/BULBS.
  
 6)NOTE: PLEASE SEE E-8, SHOWS RECEPT
 ADDED TO SERVE KITCHEN COUNTER PENINSUL-
 -AR. HOWEVER SHOWN ON LIVING ROOM CIR-
 -CUIT? PLEASE SEE 210-11,210-52 220-16
 ETC. MUST BE ON W/SMALL APPLAIANCE."A-3"
 PLEASE ALSO CLARIFY HOW THE CIRCUIT #`S
 ARE SHOWN AS THE SAME W/ AN A&B?
  
 7)NOTE: PLEASE NOTE, OCP FOR FIRE PUMP
 TO BE PER 695-4B-1 ALSO SEE NOTE 12
  
 8)NOTE: PLEASE CLARIFY SIZE OF MAIN 4OF4
 FEEDS 1000A PANEL AC ON ROOF.
  
 9)NOTE: PLEASE CORRELATE FEEDERS NOTED
 ON BOTTOM OF LOAD CALCS FOR UNITS ON
 E-8,9,10 WITH RISER DIAGRAM. RISER SHOWS
 3-#1'S ETC AND FEEDERS NOTED AT #2'S?
  
 10)NOTE: PLEASE CLARIFY HOW POWER IS
 TRANSFERED OVER FROM FPL TO GENERATOR
 FOR FIRE PUMP? PLEASE ALSO SEE RISER
 DIAGRAM, SHOWS POWER FROM FPL TO EM MAIN
 AND THEN TO X-FER SWITCH, WHICH IS FINE,
 HOWEVER, SHOWS POWER COMING FROM
 GENERATOR TO EM MAIN? PLEASE CLARIFY HOW
 THE POWER WOULD BE TRANSFERED AT THIS
 LOCATION. HOW WOULD THIS KEEP POWER
 BEING ON EQUIPMENT AT THE SAME TIME
 FROM TWO DIFFERENT SOURCES W/OUT GOING
 THROUGH TRANSFER SWITCH?
  
 11)NOTE: PLEASE SEE NOTE/WIRE/CONDUIT
 ON RISER DIAGRAM FOR FROM 1000A BRKR
 ON GENERATOR.
  
 12)NOTE: PLEASE SHOW/CLARIFY MEANS OF
 DISC REQ`D FOR FIRE PUMP. PLEASE NOTE,
 SHOW A MANUAL MEANS REQ`D, 225-31
 230-76, 230-79, FOR DISC MEANS.
 PLEASE CLARIFY IF THERE WILL BE A MANUAL
 MEANS OF DISC AND/OR TRANSFER SWITCH
 LOCATED WITH/ON SERVICE ENTRANCE RATED
 EQUIPMENT/CONTROLLER FOR FIRE PUMP.
  
 13)NOTE: PLEASE SEE GENERATOR NOTES,
 NOTES MENTION A 600A AND 400A BRKR ON
 GENERATOR AND ELECTRICAL RISER DIAGRAM
 EQUIPMENT NOTES, MENTION 500A AND 1000A
 OCP.? PLEASE CORRELATE.
  
  
 PLEASE NOTE, A RESPONSE LETTER FROM
 ELECTRICAL ENGINEER WILL HELP WITH
 CLARIFICATIONS OF SOME COMMENTS ETC.
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS,
 PLEASE CALL. IF A MEETING ON PHONE OR
 IN PERSON IS NEEDED, PLEASE CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 561-805-6717
 [email protected]