Plan Review Notes
Plan Review Notes For Permit 03020961
Permit Number 03020961
Review Stop P
Sequence Number 1
Notes
Date Text
2003-03-15 00:00:00DENIED
 REFERENCE: FBC-2001 PLUMBING
 FBC-2001 FUEL GAS
 FBC-2001 CHAPTER 11
 FHA-AMEND 98 DESIGN MANUAL
  
 1) SHT A5.1.05 DETAIL #1 EMPLOYEE REST-
 ROOM, DOOR CAN NOT OPEN INTO THE CLEAR
 FLOOR SPACE OF ANY FIXTURE OR THE 5'
 TURNING CIRCLE. 11-4.22.2. TURNING RADI-
 US SHALL BE UNOBSTURCTED.
 2) SHT A5.1.08 UNIT BATHROOM INTERIOR
 ELEVATIONS, INDICATE OPENINGS FOR W/C'S
 AND LAV HEIGHTS PER FHA DESIGN MANUAL.
 3) SHT A-7.1.0.6 ROOF DRAINS FOR CANOPY,
 PLEASE PROVIDE DRAIN DETAIL, PIPING
 DIAGRAM AND SHOW WHERE THE PIPING TERM-
 INATES.
 4) SHT A-7.1.1.6 DETAIL #1 BREAKROOM
 ELEVATION, PER SECTION 11-4.24.2, MAX.
 HEIGHT FOR SINK SHALL BE 2'10". 2'11"
 SHOWN.
 5) SHTS P-2 AND P-16, VENTS REQUIRED FOR
 FLOOR DRAINS IN PUMP ROOMS.
 6) SHT P-2 MORE INFORMATION REQUIRED FOR
 DEEP STORAGE TANK IN TRANSFORMER VAULT.
 IS THERE ANY PIPING FOR THIS TANK? WHAT
 WILL BE STORED?
 7) SHT P-2 NUMBER 4 IN BOX INDICATES A
 3" SPRINKLER DRAIN, BUT WAS UNABLE TO
 LOCATE. THIS SHALL DRAIN TO SANITARY.
 PLEASE INDICATE WHERE THIS DRAIN IS.
 8) SHT P-5 POOL EQUIPMENT ROOM SHOWS A
 6" HUB DRAIN, BUT IS NOT SHOWN ON ANY
 RISER. PLEASE INDICATE WHAT THE DRAIN IS
 FOR AND WHERE IT PIPES TO. IF IT IS AN
 INDIRECT WASTE IT WILL REQUIRE A FLOOR
 SINK AND SHALL PIPE TO SANITARY.
 9) SHT P-3 3" WATER FOR COOLING TOWER &
 5" DOMESTIC WATER CHANGES ON SHT P-4, &
 CHANGES BACK ON SHT P-5. PLEASE CLAIRFY.
 10) SHT P-6 SANITARY DRAIN LINES DO NOT
 REFLECT FIXTURE LAYOUT FOR PUBLIC BATH-
 ROOM DETAIL.
 11) SHT P-8 WATER SUPPLY LINES FOR COOL-
 ING TOWER SHOWS 3" SUPPLY FROM PUMP, AND
 ANOTHER 3" LINE (#7) TYING INTO THE SYS-
 TEM. WHERE IS THIS LINE COMMING FROM. IS
 THIS A CROSS CONNECTION FROM THE DOMES-
 TIC WATER? PLEASE CLAIRFY.
 12) SHTS P-9 UNIT A-1, & P-10 UNITS B-2A
 B-3, & B-2B, SECTION 909.1 WET VENT.
 ONLY THE FIXTURES WITHIN THE BATHROOM
 GROUP SHALL CONNEDT TO THE WET-VENTED
 HORIZONTAL BRANCH DRAIN. THE WASHMACHINE
 ON THESE STACKS SHALL DRAIN DOWNSTREAM
 OF THE BATHROOM GROUPS. ALSO MAKE CHANG-
 ES TO RISER DIAGRAM SHT P-13.
 13) SHT P-12 WATER RISER DIAGRAMS (ALL).
 AIR CHAMBERS ARE NOT APPROVED. PLEASE
 DELETE THESE FROM THE RISER DIAGRAMS.
 14) WATER RISER FOR PUBLIC BATHROOMS DO
 NOT REFLECT THE FIXTURE LAYOUT. NO WATER
 TO THE SHOWERS, DRINKING FOUNTAINS NOT
 SHOWN ON MENS, 4 LAVS IN WOMENS ROOM.
 PLEASE CLAIRFY.
 15) SHT P-16 SANT. RISER TO PUBLIC BATHS
 DO NOT REFLECT THE FLOOR PLAN.
 16) SHT P-16 PLEASE INDICATE PITCH FOR
 ALL SANITARY PIPE. ALL PIPE WILL BE RUN
 AT A UNIFORM PITCH. SIZING INDICATES
 1/2" PER FOOT REQUIRED FOR SIZE OF PIPE
 AND NUMBER OF FIXTURES UNITS.
 17) SHTS P-2 & P-16 CLEAN OUTS REQUIRED
 PER SECTION 708.3.1 IN THE BLDG DRAIN,
 MAX. 100', PER SECTION 708.3.4 AT CHANGE
 OF DIRECTION OVER 45 DEGREES, AND AT THE
 BASE OF EACH STACK PER 708.3.4. PLEASE
 SHOW C/O'S WHERE REQUIRED.
 18) SHT P-13 SOIL AND WASTE STACKS IN
 BLDGS. HAVING MORE THAN 10 BRANCH INTER-
 VALS SHALL BE PROVIDED WITH A RELIEF
 VENT AT EACH 10TH INTERVAL INSTALLED BE-
 GINNING WITH THE TOP FLOOR. SEC 914.1
 19) PLEASE PROVIDE A HORIZONTAL CONDEN-
 SATE BLDG DRAIN LINE. SHOW ALL PIPE
 SIZES, POINT OF TERMINATION, AND SUPPLY
 CALCULATIONS FOR GALLONS PER MINUTE OF
 DISCHARGE FOR SYSTEM. SYSTEM SHALL RUN
 SEPARATELY OUT OF BLDG WITH A RELIEF
 VENT AS IS EXITS BLDG.
 20) PLEASE PROVIDE A HORIZONTAL BLDG
 STORM DRAIN. SHOW ALL PIPE SIZES, PITCH,
 ACCUMULATED SQUARE FOOTAGE, AND TERMIN-
 ATION POING.
 21) PLEASE PROVIDE A STORM RISER DIAGRAM
 SHOW ALL ROOF DRAIN SIZES, SQ FT DRAINED
 PIPE SIZE, PITCH, AREA DRAINS, AND
 PLANTER DRAINS WITH ACCUMULATED SQ FT.
 22) HEALTH DEPT REVIEW REQUIRED FOR
 FACILITIES FOR POOLS.
 23) SEPARATE PERMIT REQUIRED FOR POOLS.
 24) A GREASE TRAP WILL PROBABLY BE REQ-
 UIRED IF ANY OF THE USES FOR THE RETAIL
 SPACE MENTIONED ON SHT G-4 THAT PREPARE
 OR SERVE FOOD ARE USED. IN THAT EVENT,
 PER UTILITY ORD #2938-96 RODNEY COMPO,
 ENVIRONMENTAL COMPLIANCE WILL BE CONTAC-
 TED FOR GREASE TRAP SIZE. (561) 837-4074
 25) SHT P-8 COOLING TOWER DRAIN TO SAN-
 ITARY AND OVER FLOW TO STORM.
 26) SHT P-8 SHOWS 3" GAS LINE AT WATER
 HEATERS, BUT P-2 SHOWS ONLY 2" GAS AT
 METER. PLEASE CLAIRFY.
 27) SEPARATE GAS PERMIT REQUIRED. THE
 FOLLOWING IS REQUIREMENTS FOR APPLYING.
 1. SUBMIT AN ISOMETRIC DRAWING THAT
 CLEARLY SHOWS ALL CUT SECTIONS OF PIPE
 AND CORRESPONDING LENGTHS PER FBC-2001
 FUEL GAS CODE.
 2. SHOW TYPE OF PIPING MATERIAL BEING
 INSTALLED, ALL PIPE SIZES, (AND THE EDH
 NUMBER OF CORRUGATED STAINLESS STEEL
 TUBING FOR EACH PIPE SIZE BEING USED.
 3. TYPE OF GAS, (LP OR NATURAL)
 4. BTU LOAD OF EACH APPLIANCE AND THE
 TOTAL BTU LOAD ON THE SYSTEM. REFER TO
 THE FBC-2001 FUEL GAS CODE SECS. 401.8
 THRU 402.5.2 AND TABLES 402(1) THRU
 402(34).
 5. SHOW THE DISTANCE FROM THE POINT OF
 DELIVERY, (METER), TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND/OR SYSTEM PER
 FBC-2001 FUEL GAS CODE APPENDIX A - USE
 OF CAPACITY TABLES (A)(3).
 6. SUBMIT CALCULATIONS FOR COMBUSTION
 AIR (IF APPLICABLE) PER FBC-2001 FUEL
 GAS CODE SECTION 304.
 7. INDICATE THE DELIVERY PRESSURE (PSI)
 PER FBC-2001 FUEL GAS CODE SEC. 402.2.
 NATURAL GAS SPECIFY .5 PSI OR 2 PSI.
 8. SUBMIT A DETAIL SHOWING THE TYPE,
 LOCATION, SIZE AND TERMINATION OF THE
 GAS VENTS PER FBC-2001 FUEL GAS CODE
 SECS. 502 THRU 506.
 9. SUBMIT MANUFACTURE SHEETS FOR ALL GAS
 EQUIPMENT TO VERIFY COMPLIANCE WITH
 STANDARDS NFPA 54, NFPA 58, AND THE
 FBC-2001 FUEL GAS CODE SEC 402.2
 10. CLEARLY SHOW THE LOCATION AND CAP-
 ACITY OF LP TANK(S), TYPE OF TANK (DOT
 OR ASME), THE DISTANCE OF THE TANK FROM
 THE BUILDING AND ADJACENT PROPERTY LINES
 THE DISTANCE OF THE TANK FROM ALL SOUR-
 CES OF IGNITION, OTHER CONTAINERS, BUILD
 INGS, AND THE LOCATION OF ANY BUILDING
 OPENINGS BELOW THE RELIEF VALVE OF THE
 TANK PER NFPA 58, TABLE 3-2.2.2.
 11. CLEARLY INDICATE ON THE PLAN IF THE
 LP TANK IS ABOVE OR BELOW GROUND, AND
 SHOW REQUIRED PROTECTION OF THE TANK AND
 APPURTENANCES PER NFPA 58. IF THE TANK
 IS BELOW GROUND THE CONTAINER SHALL BE
 SECURILY ANCHORED PER NFPA 58 SECTION
 3-2.2.7(H).
 28) SEPARATE PERMIT REQUIRED FOR GREASE
 TRAP.
 29) SEPARATE PERMIT REQUIRED FOR IRRIGA-
 TION.
 30) SHT P-2 PENETRATIONS INTO AND OPEN-
 INGS THROUGH A STAIRWAY ENCLOSURE ASSEM-
 BLY ARE PROHIBITED EXCEPT FOR REQUIRED
 EXIT DOORS, DUCTWORK AND EQUIPMENT NEC-
 ESSARY FOR INDEPENDENT STAIR PRESSUREIZ-
 ATION, SPRINKLER PIPING, STANDPIPES AND
 ELECTRICAL CONDUIT SERVING THE STAIRWAY
 AND TERMINATING ATY A STEEL BOX. - THE
 GAS LINE RUNNING THROUGH THE STAINWAY IS
 NOT ALLOWED.SECTION 1006.1.3.1
 30)...........
 LOOK FOR COMMENTS BY THE OTHER PLAN
 REVIEW DISCIPLINES THAT MAY BE WRITTEN
 ON THE APPLICATION, PLANS, OR ATTACHED
 SEPARATELY. WHEN RESUBMITTING PLANS
 PLEASE CLEARLY INDICATE THE REVISION AND
 REMOVE AND REPLACE ANY PAGES AS NECESS-
 ARY. SUBMIT (1) SET OF OLD DRAWINGS WITH
 THE PLANS WHEN RESUBMITTING PLANS. A
 TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW NUMBER, WITH A DESCRIPTION OF THE
 REVISION MADE, IDENTIFYING THE SHEET OR
 SPECIFICATION PAGE WHERE THE CHANGES CAN
 BE FOUND, WILL HELP TO EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 REVIEW BY KEN STEVENS
 (561) 659-8096 EXT 8377