2003-01-17 00:00:00 | PASSED/PROVISO | | | | VALVES REQUIRED PRIOR TO REGULATORS. | | DRYER IN CONFINED - SECTION 304.3 TWO | | OPENINGS REQUIRED. | | MANUFACTURE INSTALLATION INSTRUCTIONS | | REQUIRED AT FINAL FOR GENERATOR. | | | | REVIEW BY KEN STEVENS | | (561) 659-8096 EXT 8377 | | PASSED/PROVISO | | | | - VALVES ARE REQUIRED PRIOR TO REGULATOR | | - DRYER IN CONFINED SPACE, TWO OPENINGS | | ARE REQUIRED PER SECTION 304.3.1 | | - MANUFACTURE INSTALLATION SHEETS ARE | | REQUIRED AT FINAL FOR GENERATOR. | | | | | | PER N. MELICK MANUFACTURE INFO | | NOT REQUIRED FOR 1 & 2 FAMILY HOMES. | | JULY 17, 2002 OFFICAL INTERPRETATION. | | THE FIELD INSPECTOR SHALL VERIFY THE | | INSTALLED EQUIPMENT INPUT DOES NOT EX- | | CEED THE PIPE SIZING. |
|