Plan Review Notes For Permit 02101405 |
Permit Number |
02101405 |
|
Review Stop |
R |
Sequence Number |
1 |
|
Notes |
Date |
Text |
2002-11-27 00:00:00 | BUILDING PROVISO | | | | 1) A RECORDED COPY OF THE NOTICE OF | | COMMENCEMENT MUST BE SUBMITTED BEFORE A | | PERMIT CAN BE ISSUED. | | | | 2) SUBMIT A SOIL TEST REPORT FROM A | | SOILS ENGINEER INDICATING THE SAFE | | BEARING CAPACITY OF THE SOIL PRIOR TO | | POURING THE FOUNDATION AS REQUIRED BY | | CITY AMENDMENTS SECTION 1804.2.2. A | | SOIL DENSITY TEST IS ALSO REQUIRED. | | | | 3) SUBMIT A SIGNED AND SEALED DETAIL, | | INDICATING THE CONNECTION OF THE SECOND | | FLOOR WOOD FRAME EXTERIOR BEARING WALL | | TO THE WOOD FLOOR TRUSSES. | | | | 4) SUBMIT SIGNED & SEALED DRAWINGS OF | | THE BUCKET CONNECTOR SHOWN IN DETAIL D | | ON S2. | | | | 5) SUBMIT SIGNED AND SEALED DETAIL WHICH | | INDICATES THE DIMENSIONS AND REINFORCING | | FOR THE F4 FOOTINGS INDICATED ON S1. | | | | 6)PROVIDE (2) CURRENT AND COMPLETE | | COPIES OF SBCCI OR METRO-DADE PRODUCT | | APPROVALS FOR THE FIXED GLASS WINDOWS | | PRIOR TO INSTALLATION. |
|