2002-08-22 00:00:00 | BUILDING PLAN REVIEW |
| *******DENIED******* |
| |
| 1) INDICATE THE APPROPRIATE INTERNAL |
| PRESSURE COEFFICIENT ON THE PLANS AS |
| REQUIRED BY 2001 FBC 1606.1.7. (FOR AN |
| ENCLOSED STRUCTURE IT IS + OR - .18, SEE |
| ASCE 7-98) |
| |
| 2) PROVIDE UL LISTING AND MANUFACTURER'S |
| SPECIFICATIONS FOR A ONE HOUR FIRE RATED |
| GLASS BLOCK ASSEMBLY. |
| |
| 3) REVISE BUCK DETAIL FOR EXTERIOR DOOR |
| ON A-3 TO CORRESPOND WITH DOOR PRODUCT |
| APPROVAL. THE PRODUCT APPROVAL SUBMITTED |
| REQUIRES 2X BUCKS FOR THE FULL WIDTH OF |
| THE JAMB. NOTE: THE PRODUCT APPROVAL |
| SUBMITTED IS NOT FOR A SINGLE DOOR WITH |
| A SIDELITE AS INDICATED ON THE PLANS. |
| |
| 4) PROVIDE DETAILS/SPECS FOR CEILING |
| INSTALLATIONS AT ENTRY AND REAR PORCH. |
| SPECIFY THE CEILING MATERIAL THAT WILL |
| BE USED. SEE ASTM C 1063 FOR REQUIRED |
| FASTENERS AND METAL LATH, FOR STUCCO |
| APPLICATION. |
| |
| 5) PROVIDE DETAIL OF ASSEMBLY OF BUILT- |
| UP POST,(3) 2X4, USED TO CARRY TRUSS |
| GIRDER. INDICATE FASTENERS AND SPACING |
| USED TO JOIN 2X4S. INDICATE CONNECTIONS |
| AT TOP AND BOTTOM OF 2X COLUMN TO |
| ACHIEVE CONTINOUS LOAD PATH. |
| |
| 6) ITEM #14 UNDER 'SECTION & DETAILS KEY |
| NOTES' ON A-3 INDICATES THAT VENTS ARE |
| ONLY REQUIRED FOR ATTIC SPACE ABOVE |
| LIVING AREA. ALL ATTIC SPACE IS REQUIRED |
| TO BE VENTED PER 2001 FBC 1203.1.3 AND |
| 2309.6. PLEASE REVISE. |
| |
| 7) THE REQUIRED FASTNER SPACING FOR THE |
| ROOF SHEATHING IS INCORRECT ON SHEETS |
| GN-1 AND S-2 OF THE PLANS. THE CORRECT |
| SPACING IS 6"O.C.EDGES AND 6"O.C. |
| INTERMEDIATE IN ZONES 1 & 2 AND 4"O.C. |
| EDGES AND 6"O.C. INTERMEDIATE IN ZONE 3. |
| SEE NOTES ON PLAN AND ATTACHED COPY OF |
| REVISED TABLE 2306.1 FROM CITY OF WPB |
| AMENDMENTS TO THE 2001 FBC. PLEASE |
| CORRECT. |
| |
| 8) SECTION 1 ON S-2 INDICATES A 2X6 WOOD |
| FRAME WALL AT THE FRONT ENTRY AND |
| SECTION A-A ON A-3 SHOWS MASONRY |
| CONSTRUCTION. PLEASE CLARIFY AND PROVIDE |
| A DETAIL INDCATING THE CONTINOUS LOAD |
| PATH. |
| |
| 9) THE ROOF UPLIFT PRESSURES DIAGRAM ON |
| S-2 SHOWS A GABLE ROOF AT THE ENTRY AND |
| A HIP ROOF AT BEDROOM #2 AND THE FRONT |
| ELEVATION ON A-2A SHOWS A HIP AT THE |
| ENTRY AND GABLE AT BEDROOM #2. THE ROOF |
| FRAMING PLAN ON S-2 HAS A GABLE AT THE |
| ENTRY AND A GABLE AT BED ROOM #2. PLEASE |
| REVISE SO THAT ALL DRAWINGS ARE |
| CONSISTENT. |
| |
| 10) SHEET S-2 INDICATES THE WOOD FRAME |
| BEARING WALLS AT THE GALLERY TO BE 10'HT |
| AND S-1 & A-1 SHOW IT TO BE 12' A.F.F. |
| |
| 11) PROVIDE (2) CURRENT AND COMPLETE |
| COPIES OF SBCCI OR METRO-DADE PRODUCT |
| APPROVALS FOR: |
| - ENTRY DOOR WITH ONE SIDELITE AS SHOWN |
| ON PLANS (THE ONE SUBMITTED IS FOR DOORS |
| WITHOUT SIDELITES) |
| - STRUCTURAL MULLIONS THAT CAN BE |
| INSTALLED HORIZONTALLY (ONE SUBMITTED IS |
| LIMITED TO VERTICAL INSTALLATION) |
| - ARCHED TOP FIXED GLASS WINDOWS (NOT |
| COVERED BY THE APPROVAL SUBMITTED FOR |
| THE RECTANGULAR FIXED GLASS WINDOWS) |
| - SLIDING GLASS DOOR AND TRANSOM |
| ASSEMBLY (MULLION USED TO CONNECT DOOR |
| WITH TRANSOM MUST BE TESTED AND APPROVED |
| FOR USE WITH SLIDING GLASS DOOR) |
| |
| 12)PROVIDE (2) PRODUCT APPROVALS, KEY |
| PLANS AND INSTALLATION SCHEDULES |
| INDICATING THE SPECIFIC TYPES OF ANCHORS |
| TO BE USED FOR STORM PANELS. |
| |
| 13) PROVIDE ADDITIONAL COPIES OF SOIL |
| REPORT AND ENERGY CALCULATIONS. TWO SETS |
| OF DOCUMENTS ARE REQUIRED. |
| |
| ROBERT MCDOUGAL |
| BLDG. PLAN REVIEW |
| (561)659-8096 EXT.8202 |