Date |
Text |
2002-04-05 00:00:00 | **************DENIED******************** |
| |
| 1. AHU # 7 HAS NO OUTSIDE AIR VALUE ON |
| SCHEDULE. |
| 2. THE LOCATION AND INSTALLATION DETAILS |
| OF ALL FIRE DAMPERS SHALL BE LOCATED ON |
| THE PLANS BY THE DESIGNER PER |
| 2001FBC(M). PLEASE INDICATE ALL FIRE |
| DAMPERS IN DUCTS PENETRATING RATED |
| WALLS. |
| 3. M 203 VCV 2 PLAN CFM = 2275. SCHEDULE |
| ONLY CALLS FOR 1875 CFM. |
| 4. M 205 VAV 9 PLAN CFM = 1350. SCHEDULE |
| ONLY CALLS FOR 1275 CFM. |
| 5. M 206 VAV 5 DISTRUIBUTION EXCEEDS |
| SCHEDULE |
| 6. M 206 VAV 15 2 MARKED ON PLAN, NO 14 |
| INDICATED. |
| 7. M206 VAV 15 PLAN CFM= 2000. SCHEDULE |
| CALLS FOR 1200 CFM. |
| 8. M 206 (2) VAV 26 SHOWN W/ DIFFERENT |
| TOTAL CFM ON PLAN |
| 9. VAV IN CONFERENCE RM 3-X04 NOT |
| MARKED. |
| 10. DEFINE FUNCTION OF FCU 8 BOTH DROPS |
| SHOW SUPPLY AIR, NO PIPING TO UNIT, NO |
| CFM. |
| 11. INDICATE EQUIPMENT ENERGY RATING ON |
| SCHEDULE. |
| 12. BALANCED AIR RETURN PER FBC(M) |
| 406.1REQUIRED FOR ALL SPACES. |
| 13. PROVIDE MECHANICAL ROOM DRAWING FOR |
| AHU INSTALATION DETAILS AND CLARITY TO |
| SHOW SERVICE ACCESS REQUIREMENTS |
| INCLUDING COIL PULL AND OTHER REQUIRED |
| FLOOR AREA TO BE LEFT OPEN FOR SERVICE. |
| 14. M 301. PROVIDE INFORMATION ON RELIEF |
| PIPING TERMINATION FOR CHILLER |
| EQUIPMENT. |
| 15. PROVIDE REFRIGERANT INFORMATION |
| INCLUDING QUANTITIES AND VENTILATION |
| CALCULATIONS FOR COMPLIANCE WITH FBC(M) |
| CH 11. |