2001-11-19 00:00:00 | *************BUILDING UNSAT************* |
| |
| 1)A RECORDED COPY OF THE NOTICE OF |
| COMMENCEMENT MUST BE SUBMITTED BEFORE A |
| PERMIT CAN BE ISSUED. |
| |
| 2) THE IMPORTANCE FACTOR ON SHEET C-1 IS |
| INCORRECTLY GIVEN AS 1.05, IT SHOULD BE |
| 1.0. |
| |
| 3) THE ATTIC ACCESS SIZE LISTED IN NOTE7 |
| ON SHEET A-2 IS INCORRECT THE MINIMUM |
| SIZE IS 22X36 INCHES. 97 SBC 2309.6 |
| |
| 4) THE PLANS INDICATE R-30 CEILING |
| INSULATION ON A-5 AND THE ENERGY CALS. |
| LIST CEILING INSULATION AS R-19. PLEASE |
| CLARIFY. |
| |
| 5) SECTIONS A AND B ON A-5 SHOW AN 18" |
| DEEP FOOTING (6" ABOVE GRADE AND 12" TO |
| BOTTOM OF FOOTING) AND THE FOOTING |
| SCHEDULE ON SHEET S-1 GIVES FOOTING |
| DEPTH OF 16". PLEASE CLARIFY. |
| |
| 6) THE MEAN ROOF HEIGHT IS SHOWN AS |
| + 17'-8" ON A-3 AND IS LISTED AS 15'-0" |
| ON S-2. PLEASE CORRECT. |
| |
| 7) FOUNDATION NOTES ON C-1 STATES FOOT- |
| ING DESIGN BASED ON SOIL BEARING |
| CAPACITY OF 2500 PSF AND SOIL STATEMENT |
| ON S-1 STATES FOUNDATION DESIGNED FOR AN |
| ALLOWABLE SOIL BEARING PRESSURE OF |
| 2000 PSF. PLEASE CLARIFY. |
| |
| 8) CITY OF WPB AMENDMENTS TO 97 SBC |
| REQUIRE SPECIAL NAILING ZONES FOR ROOF |
| SHEATHING AND DESIGNATE THEM BY ZONES 1, |
| 2 AND 3 AS INDICATED ON A DIAGRAM. ON |
| S-2 THE ZONES GIVEN (RI AND SI) ON THE |
| ROOF SHEATHING ARE NOT CORRECT. |
| |
| 9) NO CONNECTOR IS INDICATED FOR ONE END |
| OF THE GIRDER TRUSS AT THE GARAGE ON |
| S-2. |
| |
| 10) HUGHES AND SEMCO HAVE BEEN PURCHASED |
| BY USP. THE UPLIFT AND LOAD VALUES OF |
| SOME OF THE CONNECTORS HAVE CHANGED AND |
| OTHERS WILL NO LONGER BE AVAILABLE. |
| PLEASE REVISE THE ANCHOR SCHEDULE TO |
| REFLECT THESE CHANGES. |
| USC3F= 6170#, TAPR 216= 1290# (FOR |
| INSTALLATIONS CLOSER THAN 8" ON CENTER |
| CONSULT USP TECHNICAL ASSISTANCE FOR |
| REDUCED LOAD VALUES), RTP18818 IS NO |
| LONGER AVAILABLE UNDER THIS PRODUCT CODE |
| |
| 11) THE BEAM SCHEDULE ON S-2 INDICATES |
| NO #3 TIES ARE REQUIRED FOR L-3 AND |
| SECTION 12 ON S-3 CALLS FOR #3 TIES AT |
| 16". PLEASE CLARIFY. |
| |
| 12) THERE ARE NO POSITIVE AND PRESSURES |
| INDICATED FOR THE FRONT DOORS ON A-3. |
| |
| 13) IF THE DOUBLE FRONT DOORS ARE GLAZED |
| AS INDICATED BY THE PRODUCT APPROVALS, |
| STORM PANELS OR IMPACT GLASS WILL BE |
| REQUIRED. |
| |
| 14) PROVIDE PRODUCT APPROVALS FOR |
| STRUCTURAL MULLIONS TO CONNECT THE |
| SLIDING GLASS DOORS WITH FIXED GLASS |
| WINDOWS ABOVE AND FRENCH DOOR WITH F.G. |
| WINDOW ABOVE. |
| |
| 15) PROVIDE PRODUCT APPROVAL FOR FRENCH |
| DOOR. |
| |
| 16) PROVIDE KEY PLAN, INSTALLATION |
| SCHEDULE, INDICATE ANCHOR TYPE AND |
| INSTALLATION METHOD THAT WILL BE USED. |
| |
| ROBERT MCDOUGAL |
| BLDG. PLAN REVIEW |
| (561)659-8096 EXT.8202 |