2001-03-13 00:00:00PROVISO: 3/13/01 AS OF A MEETING TODAY
 WITH NANCY DENMARK, MIKE CARLSELO, JIM
 WITMER THE CONTRACTOR MARK BUTTERS AND
 FRANK BUTTERS WE ARE IN AGGREEMENT TO
 ISSUE THTE BUILDING PERMIT WITH A PRO-
 VISO AND ADDITIONAL INFORMATION TO BE
 SUBMITTED THROUGH SUBPERMITS. AREAS NOT
 TO BE COVERED UNDER THIS PERMIT WILL BE
 THE OUTFITTING OF ROOMS103,103A,107,&
 107A. THE CONTRACTOR MAY FORM AND POUR
 THE WALLS & CEILING OF THESE ROOMS.
 THE SECOND AREA NOT INCLUDED UNDER THIS
 PERMIT WILL BE THE 550 SQ. FT DECK ON
 THE EXTERIOR OF THE BUILDING AS WELL AS
 THE SLAB ENCLOSURE AND 500 GAL. NITROGEN
 TANK TO BE LOCATED ON THE SOUTH SIDE OF
 THE BUILDING.
  
 PROVISO:
 1)- THE CONTTRACTOR WILL SUPPLY ALL THE
 EQUIRED INFORMATION REQUIRED TO MEET
 THE REQUIREMENTS OF SBC 407.2 1-10.
  
 2)- THE ARCHITECT WILL REVISE THE WALLS
 FOR THE CLOSET THAT WILL HOUSE THE
 HYDROGEN AS PERNFPA 50A .4.3.1 OPENINGS
 TO OTHER PARTS OF THE BUILDING SHALL NOT
 BE PERMITTED.
  
 3)- NFPA 50A WILL BE FOLLOWED FOR THE
 USE OF HYDROGEN IN SPECIAL ROOMS.
  
 4)-NFPA 55 WILL BE FOLLOWED FOR THE
 USE OF LIQUID GASES IN PORTABLE CYLINDER
  
 5)- THE ARCHETECT WILL CORRECT THE FLOOR
 DRAIN SHOWN IN THE ISOMETRIC FOR THE
 CONTANMENT ROOM.
  