2001-01-08 00:00:00 | SECOND CHECKLIST: |
| 1-IMPACT FEES WERE NOT PAID. |
| 2-PROVIDE CURRENT PRODUCT APPROVAL FOR |
| SLIDING GLASS DOORS. OR PROVIDE A |
| COMPLETE SITE SPECIFIC ENGINEERING |
| ANALYSIS WITH ALL CALCULATIONS, COPIES |
| OF STRUCTURAL TESTS PERFORMED AS PER |
| ASTM E-330, COMPLETE INSTALLATION |
| DETAILS INCLUDING FASTENING TO THE |
| STRUCTURE. AND INCLUDE SITE SPECIFIC |
| FORM (ATTACHED) SIGNED, SEALED AND |
| DATED BY THE MANUFACTURER ENGINEER AND |
| THE ARCHITECT OF RECORD. |
| 3-PRODUCT APPROVAL FOR SKYLIGHT IS |
| INCOMPLETE. MISSING COPIES OF THE |
| APPROVED DRAWINGS. |
| 4-TWO HOUR CONCRETE BLOCK: PROVIDE |
| CERTIFICATION FROM MANUFACTURER |
| ENGINEER STATING THAT CONCRETE BLOCK |
| EQUIVALENT THICKNESS COMPLIES WITH |
| ASTM C140 FOR FIRE RESISTANCE. |
| SECTION 709.3 SBC 1997. |
| 5-PROVIDE PRODUCT APPROVAL FOR WINDOW |
| MULLIONS. |
| 6-COMPLETELY SPECIFY CEILING CONSTRUCT'N |
| AT ENTRY AND REAR PORCHES. INCLUDE ALL |
| FASTENERS TYPES AND SPACING. SECTION |
| 2504 SBC 1997. |
| 7-REVISE ROOF TRUSS ANCHOR SCHEDULE AS |
| REQUIRED. NEED TO SPECIFY WOOD TO WOOD |
| CONNECTORS AT PORCHES' ROOF TRUSSES |
| ANCHORED TO WOOD BEAMS. |
| 8-OWNER/AGENT TO SIGN AND DATE THE |
| ENERGY CALCULATIONS. |
| 9-PROVIDE A CURRENT PRODUCT APPROVAL |
| FOR STORM PANELS. |