Plan Review Details - Permit 99090252
Plan Review Stops For Permit 99090252
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2000-09-22 Cont ID  
Sent By drunnels Date 2000-09-22 Time 07:27 Rev Time 1.00
Received By drunnels Date 2000-09-22 Time 07:26 Sent To  
Notes
2001-01-08 00:00:00SHOP DRAWINGS FOR DOME AT MACY'S
 1. SUBMIT CODE USED FOR DESIGN ON SIGNED
 AND SEALED DRAWINGS

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2000-09-21 Cont ID  
Sent By drunnels Date 2000-09-21 Time 08:51 Rev Time 2.00
Received By drunnels Date 2000-09-21 Time 08:51 Sent To  
Notes
2001-01-08 00:00:00REVIEW OF A REVISION

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 1999-10-06 Cont ID  
Sent By bstaples Date 1999-10-06 Time 11:19 Rev Time 5.00
Received By bstaples Date   Time   Sent To  
Notes
2001-01-08 00:00:001 REVIEW SEE NOTES ATTACHED TO PLANS
 1/11/2000
 2. SHEET A.1.2 FIRE WALL TO D-BLOCK IF
 WALL IS TO BE USED BY BOTH BUILDINGS
 SUPPLY ENGINEERING MEETING REQUIREMENTS
 OF 1997 STANDARD BUILDING CODE (SBC)
 PAGE 16 DEINITIONS.
 3. ROOF SYSTEM SEE 1997 SBC SECTIONS
 1503.1.2.3, SLOPE 1/4" PER FT.
 T-600 1 HOUR FIRE RATING
 1503.3 PRODUCT APPROVAL FOR 110 MPH
 SYSTEM, COSTAL EXPOSURE.
 4. PRODUCT APPROVAL ON:
 WINDOWS, DOORS AND SKYLIGHTS FOR 110 MPH
 5. SHEET A.3.0 AND SITE PLAN VIOLATION
 CHAPTER 32, 1997 SBC SECTION 3204.
 PROVIDE PRODUCT INFORMATION INDICATING
 COMPLIANCE WITH CHAPTER 24, 1997 SBC.
 6. SOIL TEST REPORT.
 7. GLAZING PROVIDE PRODUCT APPROVAL
 INFORMATION FOR IMPACT PROTECTION OF ALL
 GLAZED OPEANINGS.DOORS,WINDOWS,SKYLIGHTS
 8. EXTERIOR TRIM, PROVIDE CODE
 COMPLIANCE INFORMATION FOR TRIM MEETING
 THE REQUIREMENTS OF CHAPTER 26, 1997 SBC
 PROVIDE PRODUCT APPROVAL FOR EFIS SYSTEM
 MEET CHAPTER 26 AND TABLE 600, 1997 SBC

Review Stop E ELECTRICAL
Rev No 3 Status F Date 2000-09-19 Cont ID  
Sent By dpalmer Date 2000-09-19 Time 17:26 Rev Time 0.00
Received By dpalmer Date 2000-09-19 Time 17:26 Sent To  
Notes
2001-01-08 00:00:00**************** UNSAT *****************
  
 1)NOTE: PLEASE SHOW ALL AIC RATINGS FOR
 ALL EQUIPMENT BEING SHOWN. ALL MAINS/
 PANELS/BREAKERS MUST BE RATED FOR
 AVAILABLE FAULT CURRENT. PER 110-9
 PLEASE SUBMIT ALL THE ABOVE PER 215-5
  
 2)NOTE: PLEASE NOTE THAT NOT ALL PANEL
 SCHEDULES WERE SHOWN?? PLEASE DO SO.
  
  
 PLEASE SUBMIT THE ABOVE INFORMATION FOR
 REVIEW. IF THERE ARE ANY QUESTIONS
 PLEASE CALL.
  
 DEWEY PALMER
 ELECTRICAL PLAN REVIEW
 CITY OF WEST PALM BEACH
 561-659-8096 EXT 8372

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2000-09-13 Cont ID  
Sent By jleahy Date 2000-09-13 Time 15:13 Rev Time 1.00
Received By jleahy Date 2000-09-13 Time 15:13 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 1999-09-30 Cont ID  
Sent By jleahy Date 1999-09-30 Time 09:58 Rev Time 2.00
Received By jleahy Date 1999-09-30 Time 09:40 Sent To  
Notes
2001-01-08 00:00:00THIS PERMIT IS FOR THE SHELL ONLY NO
 INTERIOR WORK UNTIL A COMPLETE SET OF
 DRAWINGS IS SUBMITTED AND REVIEWED!!!
  
 THIS PLAN IS FOR THE SLAB WORK ONLY NO
 WORK ABOVE THE SLAB WILL NOT BE ALLOWED
 UNTIL PLANS FOR THE INTERIOR WORK ARE
 SUBMITTED!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 1999-10-01 Cont ID  
Sent By bstaples Date 1999-10-01 Time 09:35 Rev Time 8.00
Received By bstaples Date   Time   Sent To  
Notes
2001-01-08 00:00:00SEE CHECK LIST ATTACHED TO PLANS.

Review Stop M MECHANICAL (A/C)
Rev No 5 Status P Date 2000-09-09 Cont ID  
Sent By ndenmark Date 2000-09-09 Time 08:03 Rev Time 0.33
Received By ndenmark Date 2000-09-09 Time 08:03 Sent To  
Notes
2001-01-08 00:00:00AS BUILTS DRAWINGS AC1 AND AC2

Review Stop M MECHANICAL (A/C)
Rev No 4 Status P Date 2000-01-27 Cont ID  
Sent By ndenmark Date 2000-01-27 Time 15:36 Rev Time 0.50
Received By ndenmark Date 2000-01-27 Time 15:36 Sent To  
Notes
2001-01-08 00:00:00SEE ATTACHED LETTER OF EXPLANATION FROM
 THERMALTECH ENGINERING

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2000-01-27 Cont ID  
Sent By ndenmark Date 2000-01-27 Time 15:34 Rev Time 0.50
Received By ndenmark Date 2000-01-27 Time 15:34 Sent To  
Notes
2001-01-08 00:00:00ADDENDUM NO. 8 REVISIONS OKAY

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2000-01-27 Cont ID  
Sent By ndenmark Date 2000-01-27 Time 15:31 Rev Time 1.00
Received By ndenmark Date 2000-01-27 Time 15:30 Sent To  
Notes
2001-01-08 00:00:00********CORRECTED BY LETTER ATTACHED****
 EXHAUST FANS ARE NOT ALL INDICATED ON
 ROOF PROVIDE LOCATION FOR EACH FAN.
 PROVIDE AIR BALANCE SCHEDULE PER 1997
 SMC 501.2
 PROVIDE OUTSIDE AIT CALCULATIONS PER
 ASHRAE 62-89
 EXHAUST AIR TOTALS IN BUILDING DOES NOT
 MATCH FAN CAPACITY ON SCHEDULE

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 1999-10-05 Cont ID  
Sent By ndenmark Date 1999-10-05 Time 14:45 Rev Time 0.00
Received By ndenmark Date 2000-01-11 Time 17:13 Sent To  
Notes
2001-01-08 00:00:00PROVISO:
 1) PROTECT OPEN ENDS OF DUCTS THAT ARE
 INSTALLED AT THIS PHASE
 2)OUTSIDE AIR OPENINGS ARE NOT TO BE
 LOCATED WITHIN 10 FT OF EXHAUST AIR OUT-
 LETS OR PLUMBING VENT STACKS
 3) APPLIANCES ON ROOF SHALL BE MIN 18"
 ABOVE ROOF SURFACE. THIS DISTANCE IS
 MEASURED TO THE BOTTOM OF THE SUPPORT
 STRUCTURE OF THE STAND, NOT TO THE TOP
 4) NO OUTSIDE AIR INFORMATION IS PROVIDE
 WITH THIS PLAN. PROVIDE OUTSIDE AIR
 CALCULATIONS PER ASHRAE 62-89 AND AIR
 BALANCE SCHEDULE WITH PLANS FOR INTERIOR
 BUILD-OUT
 THIS INFORMATION BELONGS TO PERMIT
 99100790 SHELL PERMIT

Review Stop P PLUMBING
Rev No 10 Status P Date 2000-10-03 Cont ID  
Sent By tlarge Date 2000-10-03 Time 12:32 Rev Time 0.50
Received By tlarge Date 2000-10-03 Time 12:32 Sent To  
Notes
2001-01-08 00:00:00AS-BUILTS

Review Stop P PLUMBING
Rev No 9 Status F Date 2000-09-26 Cont ID  
Sent By tlarge Date 2000-09-26 Time 06:50 Rev Time 2.75
Received By tlarge Date 2000-09-23 Time 05:38 Sent To  
Notes
2001-01-08 00:00:001)SUBMIT DETAILED FLOOR PLAN OF TOILET
 ROOM ON FIRST FLOOR.TOILET ROOM SHALL
 COMPLY W/FACBC FOR ALL HANDICAP REQS.
 SHOW LOCATION OF REQD.DRINKING FOUNTAIN.
 FOUNTAIN SHALL COMPLY W/FACBC SEC.
 4.1.3(10)(A).PROVISIONS SHALL BE MADE
 FOR PEOPLE WHO HAVE TROUBLE BENDING AND
 STOOPING.
  
 2)SHT.P202-CLARIFY "HWC"IN TOILET ROOM.
  
 3)SHT.P206-A DRAIN IS REQD.ON THE WATER
 HEATER PAN.TERMINATION OF DRAIN SHALL
 COMPLY W/SPC SEC.507.8.3.DRAIN SHALL BE
 A MIN.OF 1".
  
 4)SHT.P207-RISER #3-SHOW SQ.FT.AREA
 DRAINED BY EACH CANOPY DRAIN.COMPLY W/
 SPC SEC.1108.1 AND TABLE 1108.1.
  
 CALL 561-659-8096,EXT.8377 IF YOU HAVE
 QUESTIONS.
  
 TIMOTHY LARGE
 PLUMBING PLANS EXAMINER.

Review Stop P PLUMBING
Rev No 8 Status F Date 2000-09-15 Cont ID  
Sent By tlarge Date 2000-09-15 Time 17:21 Rev Time 2.65
Received By tlarge Date 2000-09-15 Time 16:55 Sent To  
Notes
2001-01-08 00:00:001)SUBMIT DETAILED FLOOR PLAN OF TOILET
 ROOM ON 1ST.LEVEL AND LOCATION OF DRINK-
 ING FOUNTAIN.TOILET ROOM SHALL COMPLY W/
 FACBC FOR ALL HANDICAP REQS.DRINKING
 FOUNTAIN SHALL COMPLY W/FACBC SEC.
 4.1.3.(10) (A).(PROVISIONS SHALL BE MADE
 FOR PEOPLE WHO HAVE TROUBLE BENDING OR
 STOOPING.)
  
 2)SHT.P206-HEATER PAN DRAIN CANNOT BE
 INSTALLED AS DRAWN.COMPLY W/COUNTYWIDE
 AMENDMENTS TO SPC SEC.507.8.4.ALSO,SEE
 NOTE ON SHT.P201.
  
 3)SHT.P208-IF CONDENSATE MATERIAL ON
 ROOF IS PVC IT SHALL BE PAINTED W/A
 WATER BASED PAINT PER MANUF.RECOMMEND-
 ATIONS AND SUPPORTED AT MAX.4' INTERVALS
 NOT 6' AS NOTED.SPC SEC.310.3.6.
  
 CALL IF YOU HAVE ANY QUESTIONS
 TIMOTHY LARGE
 PLUMBING PLANS EXAMINER.

Review Stop P PLUMBING
Rev No 7 Status F Date 2000-09-10 Cont ID  
Sent By tlarge Date 2000-09-10 Time 07:57 Rev Time 1.00
Received By tlarge Date 2000-09-10 Time 07:19 Sent To  
Notes
2001-01-08 00:00:001)SUBMIT PLANS THAT CLEARLY SHOW ALL THE
 REVISIONS.CROSSED OUT AND SCRATCHED OUT
 LINES DO NOT REFLECT THE CHANGES.CLOUD
 ALL AREAS AFFECTED.COUNTYWIDE AMENDMENTS
 TO SPC SEC.104.2.1.
  
 CALL 561-659-8096,EXT.8377 IF YOU HAVE
 ANY QUESTIONS.
 TIMOTHY LARGE
 PLUMBING PLANS EXAMINER.

Review Stop P PLUMBING
Rev No 6 Status P Date 2000-03-14 Cont ID  
Sent By tlarge Date 2000-03-14 Time 17:57 Rev Time 0.75
Received By tlarge Date 2000-03-14 Time 17:57 Sent To  
Notes
2001-01-08 00:00:00***************PROVISO******************
 SUBMIT REVISED STORM DRAINAGE RISER FOR
 ADDED ROOF DRAINS.(SEE SHT.A1.3.)SHOW
 SQ.FOOTAGE DRAINED BY EACH DRAIN AND
 CONNECTION TO EXISTING SYSTEM.SIZING
 SHALL COMPLY W/SPC SEC.1108.1,1108.2.

Review Stop P PLUMBING
Rev No 5 Status P Date 2000-02-24 Cont ID  
Sent By tlarge Date 2000-02-24 Time 08:59 Rev Time 1.25
Received By tlarge Date 2000-02-24 Time 08:59 Sent To  
Notes
2001-01-08 00:00:00STORM AND PLBG.FIXTURE REQS.REVISIONS.

Review Stop P PLUMBING
Rev No 4 Status P Date 2000-02-04 Cont ID  
Sent By tlarge Date 2000-02-04 Time 11:43 Rev Time 2.00
Received By tlarge Date 2000-02-04 Time 11:45 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 3 Status N Date 2000-02-09 Cont ID  
Sent By tlarge Date 2000-01-25 Time 09:21 Rev Time 4.50
Received By tlarge Date 2000-01-25 Time 09:21 Sent To  
Notes
2001-01-08 00:00:00REFER TO ALL PREVIOUS PLUMBING COMMENTS.
 ALL CORRECTIONS SHALL BE MADE TO THE
 PLANS PRIOR TO RESUBMITTAL TO THIS DEPT.
  
 *****NOTE:THESE PLANS HAVE BEEN REVIEWED
 THREE TIMES TO DATE AND THERE ARE STILL
 NUMEROUS ITEMS WHICH HAVE NOT BEEN
 PROPERLY ADDRESSED, OR HAVE NOT BEEN
 ADDRESSED AT ALL.I'VE DISCUSSED THESE
 ISSUES W/THE DESIGN PROFESSIONALS FOR
 THIS PROJECT W/LIMITED OR NO SUCCESS AND
 CANNOT WASTE ANY MORE VALUABLE TIME ON
 THIS PROJECT UNTIL ALL ITEMS HAVE BEEN
 CORRECTED.I CAN BE REACHED AT:
 (561)659-8096,EXT.8377.
  
 TIMOTHY K. LARGE
 PLUMBING PLAN REVIEW.

Review Stop P PLUMBING
Rev No 2 Status N Date 2000-02-09 Cont ID  
Sent By tlarge Date 2000-01-06 Time 18:29 Rev Time 5.75
Received By tlarge Date 2000-01-06 Time 18:29 Sent To  
Notes
2001-01-08 00:00:00SUBMIT TOTAL OCCUPANT LOAD OF STRUCTURE
 PER SPC SEC.407.1.3.
  
 CONFIGURATION OF WOMEN'S RESTROOM ON SHT
 A1.5.DOESN'T CORRELATE W/SHTS.A1.2 OR
 A6.2.CLARIFY.
  
 CLEARLY SHOW LENGTH AND WIDTH DIMENSIONS
 OF HANDICAP STALLS AND TOILET ROOMS.
 COMPLY W/FACBC SEC.4.17.3 EXCEPTION:NEW
 CONSTRUCTION AND FIGURES 28 AND 30.
  
 GRAB BARS BEHIND WATER CLOSETS SHALL
 COMPLY W/FACBC SEC.4.16.4 & 4.17.6.
  
 CLEAR FLOOR SPACE UNDER HANDICAP LAVS.
 SHALL COMPLY W/FACBC SEC.4.19.2.
  
 SHOW MOUNTING HEIGHTS/DIMENSIONS OF ALL
 HANDICAP FIXTURES AND APPURTENANCES.
 COMPLY W/ALL APPLICABLE SECTIONS OF
 FACBC.
  
 DRINKING FOUNTAIN BY SECURITY OFFICE
 SHALL COMPLY W/FACBC SEC.4.1.3(10)(A)
  
 SUBMIT ISOMETRIC DRAWING FOR COMPLETE
 UNDERGROUND STORM DRAINAGE PIPING FOR
 THE BUILDING STORM DRAINAGE SYSTEM PER
 COUNTYWIDE AMENDMENTS TO SPC SEC.104.2.1
 SIZING OF SYSTEM SHALL COMPLY W/SPC SEC.
 1108.2.1.SYSTEM DOESN'T COMPLY.
  
 SUBMIT CALCULATIONS/DETAILS FOR
 PROVISIONS FOR SECONDARY DRAINAGE FOR
 ROOF STRUCTURE PER SPC SEC.1109.SUBMIT
 DETAILS OF SCUPPERS W/ALL DIMENSIONS.
  
 CLEARLY SHOW TERMINATION POINT OF STORM
 DRAINAGE SYSTEM.(SEE 8"RISERS AND CANOPY
 AT ROTUNDA ON A200.)
  
 SHT.P200-RISER #4 -4"ROOF DRAIN NOT
 SHOWN ON SHT.P206.
  
 SHT.P201-RISER FOR MSB ON 2ND FLR.DOES
 NOT CORRELATE W/ISOMETRIC ON P206.(SEE
 AREA AT COLS.9-10 BETWEEN E-F.)
  
 FLOOR DRAINS IN RESTROOMS AND FAMILY
 TOILET ROOM ARE S-TRAPPED.COMPLY W/SPC
 SEC.901.2.
  
 SHOW SIZE OF CONDENSATE DRAINS ON PLANS.
 COMPLY W/SMC SEC.304.8.4.
  
 SHT.P206.-2ND.FLR.MEN'S AND WOMEN'S R.R.
 SIZING OF DRAINAGE SYSTEM SHALL COMPLY
 W/SPC TABLE 714.2.(REFER TO 1 1/2"& 2"
 DRAINS).
  
 BRANCH VENT SIZING FOR WATER CLOSETS
 SHALL COMPLY W/SPC TABLE 902.2.
  
 SHT.P206-JANITOR SINK NOT SHOWN ON WATER
 AND SANITARY RISERS.
  
 SHT.P201 REFERS TO SHT.P700 FOR CONTIN-
 UATION OF SANITARY.NO SUCH SHEET IS IN
 PLANS.
  
 A HEATER PAN AND PAN DRAIN ARE REQUIRED
 FOR THE EWH.COMPLY W/COUNTYWIDE AMEND-
 MENTS TO SPC SEC.507.8.1.
  
 MAX.TEMPERATURE OF WATER TO PUBLIC REST-
 ROOMS SHALL BE 110 DEGREES PER FEC SEC.
 412.1.ABCD.2.3.2.
  
 HOSE BIBBS SHALL BE VALVED PER SPC SEC.
 610.4.1.
  
 SHT.P206-WATER SUPPLY CONTROL SHALL
 COMPLY W/SPC SEC.610.4.1 & 610.4.2.
  
 VENTS THRU ROOF SHALL NOT BE INCREASED
 IN SIZE (ONLY WHERE FROST CLOSURE IS A
 PROBLEM.)SPC SEC.905.2,918,920.2.-SEE
 FUTURE RESTROOM AREA,& F.D.AT PUMP ROOM.
  
 THE FOLLOWING JOB SPECS.DO NOT COMPLY
 W/SPC.THEY SHALL BE CHANGED TO COMPLY
 W/THE FOLLOWING CODE SECS.:
 PAGE 15410-15-(H)(I)-VERT.AND HORIZONTAL
 SUPPORTS SHALL COMPLY W/SPC SEC.310.2-
 310.3.6.
 PAGE 15430-6-(3.3)-CLEANOUTS SHALL
 COMPLY W/SPC 710.2.4.
 PAGE 15497(1-3)SECS.3.2-3.5-SYSTEM TESTS
 SHALL COMPLY W/SPC SECS.311.2-311.7.5.

Review Stop P PLUMBING
Rev No 1 Status N Date 2000-02-09 Cont ID  
Sent By tlarge Date 1999-09-21 Time 16:56 Rev Time 6.25
Received By tlarge Date 1999-09-18 Time 12:00 Sent To  
Notes
2001-01-08 00:00:00SUBMIT OCCUPANT LOAD PER SPC SEC.407.1.3
  
 NUMBER OF DRINKING FOUNTAINS FOR
 OCCUPANT LOAD SHALL COMPLY W/TABLE 407
 OF SPC.
  
 SUBMIT STORM DRAINAGE ISOMETRIC FOR
 REVIEW.COMPLY W/SPC SECS.1108.
  
 SUBMIT CALCULATIONS/DETAILS FOR
 PROVISIONS FOR SECONDARY DRAINAGE FOR
 ROOF STRUCTURE PER SPC SEC.1109.
  
 CONFIGURATION OF WOMEN'S RESTROOM ON
 A1.2 DOESN'T CORRELATE W/SHT.A1.5 OR
 A6.2.(AMOUNT OF PLBG.FIXTURES DOESN'T
 MATCH.)
  
 CLEARLY SHOW LENGTH AND WIDTH DIMENSIONS
 OF HANDICAP STALLS AND TOILET ROOM.
 COMPLY W/FACBC SEC.4.17.3 EXCEPTION:NEW
 CONSTRUCTION AND FIGURES 28 & 30.
  
 SHT.A6.2-GRAB BARS BEHIND WATER CLOSETS
 SHALL COMPLY W/FACBC SEC.4.16.4 & 4.17.6
  
 CLEAR FLOOR SPACE UNDER HANDICAP LAV.
 SHALL COMPLY W/FACBC SEC.4.19.2.
  
 SHOW MOUNTING HEIGHTS/DIMENSIONS OF ALL
 HANDICAP FIXTURES AND APPURTENANCES.
 COMPLY W/FACBC.
  
 DISTANCE OF FLOOR DRAINS FROM VENT SHALL
 COMPLY W/TABLE 908.1 OF COUNTYWIDE
 AMENDMENTS TO STD.PLBG.CODE.
  
 SHT.P200-CLEARLY SHOW CONTINUATION POINT
 OF 8" STORM DRAIN AND SANITARY LINE.SEE
 COLS.#B-D & "10".
  
 SUBMIT A STORM DRAINAGE ISOMETRIC FOR
 REVIEW.NOTE SQUARE FOOTAGE DRAINED BY
 EACH ROOF DRAIN.COMPLY W/SPC SEC.1108.1,
 1108.2.
  
 SHT.P201-RISER FOR MSB ON 2ND FLR.
 DOESN'T CORRELATE W/ISOMETRIC ON P206.
 SPC 104.2.1.
  
 FLOOR DRAINS ARE NOT PROPERLY VENTED PER
 SPC SEC.901.2
  
 FLOOR DRAIN IS REQD.IN THE FAMILY TOILET
 ROOM PER SPC SEC.409.4.1.1.
  
 SHT.P206-CLEARLY SHOW ORIGINATION POINT
 OF DOMESTIC WATER LINE.SPC 104.2.1.
 A BACKFLOW DEVICE IS REQD.ON THE WATER
 SERVICE TO THE BLDG.PER SPC SEC.606.
  
 JOB SPECS.-PG.15410-15.-(H)(I)-VERTICAL
 AND HORIZ.SUPPORTS SHALL COMPLY W/SPC
 SEC.310.2-310.3.6.
  
 JOB SPECS.-PG.15430-6.-(3.3)-CLEANOUTS
 SHALL COMPLY W/SPC 710.2.4.
  
 JOB SPECS.-PG.15497-SECS.3.2-3.5.SYSTEM
 TESTS SHALL COMPLY W/SPC SECS.311.2 -
 311.7.5.
  
 *************SHELL ONLY*****************
  
 SUBMIT ISOMETRIC DRAWINGS FOR ALL WATER,
 SANITARY,STORM AND CONDENSATE SYSTEMS TO
 BE INSTALLED IN THE SHELL STRUCTURE. .
 SPC 104.2.1.
  
 ROOF SYSTEM SHALL BE SUPPLIED W/
 PROVISIONS FOR SECONDARY DRAINAGE PER
 SPC SEC.1109.
  
 CLEARLY SHOW ORIGINATION /TERMINATION
 POINTS OF THE SANITARY,STORM,CONDENSATE,
 AND WATER SYSTEMS ON THE PLANS.SPC 104.2
  
 A BACKFLOW PREVENTION DEVICE IS REQD.ON
 THE DOMESTIC WATER SYSTEM PER SPC SEC.
 606.
  
 NOTE:PLUMBING PROVISO:
 THE ABOVE INFORMATION FOR THE SHELL BLDG
 SHALL BE SUBMITTED FOR REVIEW WITHIN
 30 DAYS OF ISSUANCE OF SHELL PERMIT.
 10/4/99.T.LARGE.

Review Stop Z ZONING
Rev No 1 Status P Date 1999-09-10 Cont ID  
Sent By gjoyce Date 1999-09-09 Time 14:45 Rev Time 0.75
Received By gjoyce Date   Time   Sent To  
Notes
2001-01-08 00:00:00NEEDS SITE PLAN, PASSED TO BUILDING
 CALLED JIM 9-9-99