Plan Review Stops For Permit 22090680 |
Review Stop |
AD |
ADDRESSING |
Rev No |
2 |
Status |
P |
Date |
2022-10-26 |
|
|
Cont ID |
|
Sent By |
cpuell |
Date |
2022-10-26 |
Time |
11:05 |
Rev Time |
0.00 |
Received By |
cpuell |
Date |
2022-10-26 |
Time |
11:05 |
Sent To |
|
|
Notes |
2022-10-26 11:10:03 | PROJECT HAS BEEN ASSIGNED THE ADDRESS OF 510 DATURA ST, | | SINCE NO DEMO PERMIT WAS APPLIED FOR 506 DATURA ST AND | | 514 DATURA ST WILL BE RETIRED ONCE THE BUILDING PERMIT | | IS APPLIED FOR. ADDITIONAL ADDRESSES OF 520 DATURS ST | | (MANAGEMENT AND LEASING OFFICE) 229 QUADRILLE PLAZA DR | | (HOTEL) AND 249 QUADRILLE PLAZA DR HAVE BEEN EARMARKED | | FOR THE FROUND FLOOR BUT WILL NOT BE ACTIVATED UNTIL | | THE BUILDING PERMIT IS APPLIED FOR. REPLAT IS TO BE | | DONE FOR THE THREE PARCELS, PLEASE EMAIL PRELIMINARY | | LETTER FOR PCN FROM THE COUNTY TO [email protected] | | ONCE IT HAS BEEN RECIEVED. |
|
|
Review Stop |
AD |
ADDRESSING |
Rev No |
1 |
Status |
F |
Date |
2022-10-06 |
|
|
Cont ID |
|
Sent By |
cpuell |
Date |
2022-10-06 |
Time |
11:54 |
Rev Time |
0.00 |
Received By |
cpuell |
Date |
2022-10-06 |
Time |
11:54 |
Sent To |
|
|
Notes |
2022-10-06 11:57:53 | PER THE PPRC COMMENTS DEVELOPMENT SERVICES DEPARTMENT, | | BUILDING DIVISION, COMMENTS: | | 11. BUILDING ADDRESS. EACH SEPARATE BUILDING, AND UNIT | | WITH AN INDEPENDENT ENTRANCE FROM THE STREET, SHALL | | HAVE A SEPARATE ADDRESS ASSIGNED BASED ON THE LOCATION | | OF THE BUILDING ENTRANCE. FOR STREET ADDRESSING, | | CONTACT CAROLINE PUELL, ADDRESSING COORDINATOR, AT | | (561) 805 6659, OR BY EMAIL: [email protected] | | | | PLEASE CONTACT [email protected] OR CALL 561-805-6659 SO | | THAT ADDRESS CAN BE ASSIGNED FOR THIS PROJECT. PLEASE | | EMAIL A SITE PLAN AND A GROUND FLOOR PLAN TO SEE WHAT | | ADDRESS WILL BE APPROPRIATE FOR THE PROJECT. | | | | | | |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
4 |
Status |
P |
Date |
2023-02-06 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2023-02-06 |
Time |
09:11 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2023-02-06 |
Time |
09:11 |
Sent To |
|
|
Notes |
2023-02-06 09:13:12 | FYI - FBC WPB 105.13 PHASED PERMIT APPROVAL. AFTER | | SUBMITTAL OF THE APPROPRIATE CONSTRUCTION DOCUMENTS, | | THE BUILDING OFFICIAL IS AUTHORIZED TO ISSUE A PERMIT | | FOR THE CONSTRUCT ION OF FOUNDATIONS OR ANY OTHER | | PART OF A BUILDING OR STRUCTURE BEFORE THE CONSTRUCTION | | DOCUMENTS FOR THE WHOLE BUILDING OR STRUCTURE | | HAVE BEEN SUBMITTED. THE HOLDER OF SUCH PERMIT FOR THE | | FOUNDATION OR OTHER PARTS OF A | | BUILDING OR STRUCTURE SHALL PROCEED AT THE HOLDER'S OWN | | RISK WITH THE BUILDING OPERATION AND | | WITHOUT ASSURANCE THAT A PERMIT FOR THE ENTIRE | | STRUCTURE WILL BE GRANTED |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
F |
Date |
2023-01-19 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2023-01-19 |
Time |
12:35 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2023-01-19 |
Time |
12:32 |
Sent To |
|
|
Notes |
2023-01-19 12:35:37 | FOUNDATION FOR A NEW HOTEL/APARTMENT BUILDING | | REVIEWED BY ROGER MCPHERSON | | 561-805-6716 | | [email protected] | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | AMENDMENT | | | | 2ND REVIEW NO CHANGES | | | | CORRECTIONS NEEDED - | | REVIEWED FOR FOUNDATION PERMIT ONLY | | | | 1) GEOTECHNICAL REPORT NEEDS TO SHOW AS DIGITALLY | | SIGNED IN ADOBE READER - SIGNED AND SEALED DRAWINGS IN | | PROJECTDOX NEED TO BE DIGITALLY/ELECTRONICALLY SIGNED | | TO BE USED IN ELECTRONIC PLAN REVIEW. (A | | CERTIFICATE-BASED DIGITAL SIGNATURE (OFTEN JUST CALLED | | A DIGITAL SIGNATURE) IS A SPECIFIC TYPE OF | | E-SIGNATURE). | | | | | | | | FYI - FBC WPB 105.13 PHASED PERMIT APPROVAL. AFTER | | SUBMITTAL OF THE APPROPRIATE CONSTRUCTION DOCUMENTS, | | THE BUILDING OFFICIAL IS AUTHORIZED TO ISSUE A PERMIT | | FOR THE CONSTRUCT ION OF FOUNDATIONS OR ANY OTHER | | PART OF A BUILDING OR STRUCTURE BEFORE THE CONSTRUCTION | | DOCUMENTS FOR THE WHOLE BUILDING OR STRUCTURE | | HAVE BEEN SUBMITTED. THE HOLDER OF SUCH PERMIT FOR THE | | FOUNDATION OR OTHER PARTS OF A | | BUILDING OR STRUCTURE SHALL PROCEED AT THE HOLDER'S OWN | | RISK WITH THE BUILDING OPERATION AND | | WITHOUT ASSURANCE THAT A PERMIT FOR THE ENTIRE | | STRUCTURE WILL BE GRANTED |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
F |
Date |
2022-12-21 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-12-21 |
Time |
12:42 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-12-21 |
Time |
12:42 |
Sent To |
|
|
Notes |
2022-12-21 12:43:25 | FOUNDATION FOR A NEW HOTEL/APARTMENT BUILDING | | REVIEWED BY ROGER MCPHERSON | | 561-805-6716 | | [email protected] | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | AMENDMENT | | | | 2ND REVIEW NO CHANGES | | | | CORRECTIONS NEEDED - | | REVIEWED FOR FOUNDATION PERMIT ONLY | | | | 1) PLEASE READ AND FILL OUT THE REQUIRED DOCUMENTS AND | | PROVIDE THE REQUIRED COPIES OF LICENSES PER THE | | "GUIDELINES AND POLICIES FOR PROJECTS CONCERNING | | THRESHOLD/SPECIAL INSPECTORS AND RESIDENT INSPECTORS". | | YOU CAN E MAIL ME AND ASK FOR A COPY. | | | | 2) PLEASE PROVIDE A SOILS REPORT. | | | | 3) A SEPARATE PERMIT IS REQUIRED FOR THE DEMO OF | | EXISTING BUILDINGS. | | | | FYI - FBC WPB 105.13 PHASED PERMIT APPROVAL. AFTER | | SUBMITTAL OF THE APPROPRIATE CONSTRUCTION DOCUMENTS, | | THE BUILDING OFFICIAL IS AUTHORIZED TO ISSUE A PERMIT | | FOR THE CONSTRUCT ION OF FOUNDATIONS OR ANY OTHER | | PART OF A BUILDING OR STRUCTURE BEFORE THE CONSTRUCTION | | DOCUMENTS FOR THE WHOLE BUILDING OR STRUCTURE | | HAVE BEEN SUBMITTED. THE HOLDER OF SUCH PERMIT FOR THE | | FOUNDATION OR OTHER PARTS OF A | | BUILDING OR STRUCTURE SHALL PROCEED AT THE HOLDER'S OWN | | RISK WITH THE BUILDING OPERATION AND | | WITHOUT ASSURANCE THAT A PERMIT FOR THE ENTIRE | | STRUCTURE WILL BE GRANTED |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2022-11-03 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-11-03 |
Time |
09:43 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-11-02 |
Time |
08:52 |
Sent To |
|
|
Notes |
2022-11-03 09:43:30 | FOUNDATION FOR A NEW HOTEL/APARTMENT BUILDING | | REVIEWED BY ROGER MCPHERSON | | 561-805-6716 | | [email protected] | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | AMENDMENT | | | | CORRECTIONS NEEDED - | | REVIEWED FOR FOUNDATION PERMIT ONLY | | | | 1) PLEASE READ AND FILL OUT THE REQUIRED DOCUMENTS AND | | PROVIDE THE REQUIRED COPIES OF LICENSES PER THE | | "GUIDELINES AND POLICIES FOR PROJECTS CONCERNING | | THRESHOLD/SPECIAL INSPECTORS AND RESIDENT INSPECTORS". | | YOU CAN E MAIL ME AND ASK FOR A COPY. | | | | 2) PLEASE PROVIDE A SOILS REPORT. | | | | 3) A SEPARATE PERMIT IS REQUIRED FOR THE DEMO OF | | EXISTING BUILDINGS. | | | | FYI - FBC WPB 105.13 PHASED PERMIT APPROVAL. AFTER | | SUBMITTAL OF THE APPROPRIATE CONSTRUCTION DOCUMENTS, | | THE BUILDING OFFICIAL IS AUTHORIZED TO ISSUE A PERMIT | | FOR THE CONSTRUCT ION OF FOUNDATIONS OR ANY OTHER | | PART OF A BUILDING OR STRUCTURE BEFORE THE CONSTRUCTION | | DOCUMENTS FOR THE WHOLE BUILDING OR STRUCTURE | | HAVE BEEN SUBMITTED. THE HOLDER OF SUCH PERMIT FOR THE | | FOUNDATION OR OTHER PARTS OF A | | BUILDING OR STRUCTURE SHALL PROCEED AT THE HOLDER'S OWN | | RISK WITH THE BUILDING OPERATION AND | | WITHOUT ASSURANCE THAT A PERMIT FOR THE ENTIRE | | STRUCTURE WILL BE GRANTED |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
3 |
Status |
P |
Date |
2023-01-25 |
|
|
Cont ID |
|
Sent By |
mpeterso |
Date |
2023-01-25 |
Time |
13:38 |
Rev Time |
0.00 |
Received By |
mpeterso |
Date |
2023-01-25 |
Time |
13:33 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
F |
Date |
2023-01-05 |
|
|
Cont ID |
|
Sent By |
mpeterso |
Date |
2023-01-05 |
Time |
12:45 |
Rev Time |
0.00 |
Received By |
mpeterso |
Date |
2023-01-05 |
Time |
12:45 |
Sent To |
|
|
Notes |
2023-01-05 12:46:47 | ELECTRIC REVIEW FAILED | | 1) PREVIOUS COMMENTS NOT ADDRESSED, SEE PREVIOUS | | COMMENTS | | | | PLEASE DETAIL SIZING CALCULATIONS FOR HANDHOLE. | | | | PLEASE INDICATE HOW THE EMERGENCY SYSTEM WILL BE KEPT | | COMPLETELY INDEPENDENT OF ALL OTHER WIRING AS PER NEC | | 700.10 (B) | | | | PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RESUBMITTAL FORM. | | | | CODES IN EFFECT: | | FBC = FLORIDA BUILDING CODE 2020 7TH EDITION | | WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FLORIDA | | BUILDING CODE 2020 7TH ED. | | FBC EB = FLORIDA BUILDING CODE EXISTING BUILDING 2020 | | 7TH EDITION | | FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2020 | | 7TH EDITION | | FBC RE = FLORIDA RESIDENTIAL CODE 2020 7TH EDITION | | NEC = NFPA 70 2017 EDITION, NATIONAL ELECTRICAL CODE | | FS = FLORIDA STATUTES | | | | V/R, | | | | MICHAEL PETERSON | | ELECTRICAL PLANS EXAMINER | | [email protected] | | 561-805-6746 | | |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
F |
Date |
2022-10-24 |
|
|
Cont ID |
|
Sent By |
mpeterso |
Date |
2022-10-24 |
Time |
09:30 |
Rev Time |
0.00 |
Received By |
mpeterso |
Date |
2022-10-24 |
Time |
09:14 |
Sent To |
|
|
Notes |
2022-10-24 10:33:01 | ELECTRIC REVIEW FAILED | | 1) PLEASE PROVIDE DETAILS AS TO THE MANHOLE IS SIZED IN | | COMPLIANCE WITH NEC 110.74 (A) NEC 314.28 | | 2) PLEASE PROVIDE DETAILS ON HOW MANHOLE IS IN | | COMPLIANCE WITH NEC 700.10(B) | | | | | | PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RESUBMITTAL FORM. | | | | CODES IN EFFECT: | | FBC = FLORIDA BUILDING CODE 2020 7TH EDITION | | WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FLORIDA | | BUILDING CODE 2020 7TH ED. | | FBC EB = FLORIDA BUILDING CODE EXISTING BUILDING 2020 | | 7TH EDITION | | FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2020 | | 7TH EDITION | | FBC RE = FLORIDA RESIDENTIAL CODE 2020 7TH EDITION | | NEC = NFPA 70 2017 EDITION, NATIONAL ELECTRICAL CODE | | FS = FLORIDA STATUTES | | | | V/R, | | | | MICHAEL PETERSON | | ELECTRICAL PLANS EXAMINER | | [email protected] | | 561-805-6746 | | |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
4 |
Status |
F |
Date |
2023-02-06 |
|
|
Cont ID |
|
Sent By |
rrossano |
Date |
2023-02-06 |
Time |
|
Rev Time |
0.00 |
Received By |
rrossano |
Date |
2023-02-06 |
Time |
|
Sent To |
|
|
Notes |
2023-02-06 12:12:58 | UNDER FORMAL ENGINEERING SUBMITTAL REVIEW. |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
3 |
Status |
F |
Date |
2023-01-23 |
|
|
Cont ID |
|
Sent By |
rrossano |
Date |
2023-01-23 |
Time |
|
Rev Time |
0.00 |
Received By |
rrossano |
Date |
2023-01-23 |
Time |
|
Sent To |
|
|
Notes |
2023-01-23 18:08:43 | UNDER FORMAL ENGINEERING SUBMITTAL. |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
2 |
Status |
F |
Date |
2022-12-27 |
|
|
Cont ID |
|
Sent By |
rrossano |
Date |
2022-12-27 |
Time |
|
Rev Time |
0.00 |
Received By |
rrossano |
Date |
2022-12-27 |
Time |
|
Sent To |
|
|
Notes |
2022-12-27 08:20:26 | UNDER FORMAL ENGINEERING SUBMITTAL REVIEW. |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
1 |
Status |
F |
Date |
2022-10-13 |
|
|
Cont ID |
|
Sent By |
rrossano |
Date |
2022-10-13 |
Time |
|
Rev Time |
|
Received By |
rrossano |
Date |
2022-10-13 |
Time |
|
Sent To |
|
|
Notes |
2022-10-13 12:13:08 | UNDER FORMAL ENGINEERING SUBMITTAL REVIEW. |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
1 |
Status |
P |
Date |
2022-10-07 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2022-10-07 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2022-10-05 |
Time |
14:13 |
Sent To |
|
|
Notes |
2022-10-07 16:28:59 | FOUNDATION ONLY AS PER THE APPLICATION | | | | | | PETER LEDUC | | FIRE MARSHAL | | 561-804-4709 | | [email protected] | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2023-02-07 |
|
|
Cont ID |
|
Sent By |
aoliver |
Date |
2023-02-07 |
Time |
08:59 |
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2023-02-03 |
Time |
12:02 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2023-01-25 |
|
|
Cont ID |
|
Sent By |
mpeterso |
Date |
2023-01-25 |
Time |
13:38 |
Rev Time |
0.00 |
Received By |
mpeterso |
Date |
2023-01-18 |
Time |
11:09 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2023-01-05 |
|
|
Cont ID |
|
Sent By |
mpeterso |
Date |
2023-01-05 |
Time |
13:06 |
Rev Time |
0.00 |
Received By |
mpeterso |
Date |
2022-12-20 |
Time |
09:29 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2022-12-08 |
|
|
Cont ID |
|
Sent By |
aoliver |
Date |
2022-12-08 |
Time |
08:04 |
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2022-10-04 |
Time |
09:51 |
Sent To |
|
|
Notes |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
1 |
Status |
F |
Date |
2022-11-03 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-11-03 |
Time |
09:44 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-11-03 |
Time |
09:43 |
Sent To |
|
|
Notes |
2022-11-03 09:45:14 | PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE | | DIGITALLY VIA PROJECTDOX UPON NOTIFICATION BY THIS | | OFFICE. NOTIFICATION MAY OCCUR WHEN PLANS ARE NEAREST | | FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE | | OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL | | IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME | | THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM | | CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS | | TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF | | | | UPON APPROVAL AND FEE PAYMENT, PLEASE UPLOAD THE | | RECEIPT TO YOUR PROJECT OR EMAIL IT TO | | [email protected] . | | |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
P |
Date |
2022-12-22 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2022-12-22 |
Time |
14:28 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2022-12-22 |
Time |
13:44 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2022-10-17 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2022-10-17 |
Time |
12:01 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2022-10-17 |
Time |
10:56 |
Sent To |
|
|
Notes |
2022-10-17 12:01:35 | 1ST REVIEW FBC-2020 PLUMBING | | PERMIT- 22090680 | | 10/17/22 | | | | CODES IN EFFECT: | | FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020 | | FBC ACC- FLORIDA ACCESSIBILITY CODE 7TH EDITION 2020 | | FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020 | | FS- FLORIDA STATUTES | | FAC- FLORIDA ADMINISTRATIVE CODE | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC | | | | PLAN REVIEW RESULTS: DENIED. | | | | 1) SHEET PF1.00: THE PLAN SHOWS A GREASE INTERCEPTOR | | WHICH WILL REQUIRE A SEPARATE PERMIT AND PLAN | | SUBMITTAL- SEC. 107.2.1 WPB. THE SUBMITTED PLUMBING | | PLANS FOR THE BUILDING WILL NOT BE APPROVED UNTIL A | | PERMIT APPLICATION FOR THE INTERCEPTOR HAS BEEN | | SUBMITTED.. YOU CAN SUBMIT AN APPLICATION TBD (TO BE | | DETERMINED) IF YOU DO NOT HAVE A CONTRACTOR SELECTED BY | | EMAILING A COMPLETED PERMIT APPLICATION TO | | [email protected]. YOU WILL RECEIVE INSTRUCTIONS | | TO PAY FEES AND UPLOAD PLANS. YOU MAY UPLOAD PLANS AND | | PAY FEES AT A FUTURE DATE, BUT THE APPLICATION IS | | REQUIRED AT THIS TIME. WE RECOMMEND THAT YOU PAY FEES | | AND UPLOAD PLANS AT THE SAME TIME. AFTER YOU HAVE THE | | PERMIT GENERATED, NOTIFY ME VIA EMAIL AND I WILL CHANGE | | THE REVIEW STATUS TO PASS. | | | | 2) PF1.00- AS NOTED ABOVE THE INTERECEPTOR SHALL BE | | INSTALLED UNDER A SEPARATE PERMT. A COMPLETE PLAN | | SUBMITTAL WILL BE REQUIRED AT THAT TIME WHICH SHALL | | INCLUDE THE FOLLOWING ITEMS: | | A) MANUFACTURER'S SPECIFICATIONS AND INSTALLATION | | GUIDELINES WITH APPROVAL STAMP BY THE ENGINEER OF | | RECORD- SECS.1003.3.5 OR 1003.3.7 FBC P. | | B) EQUIPMENT SCHEDULE INDICATING THE MAKE AND MODEL AND | | CAPACITY OF THE UNIT. | | C) SIZING CALCULATIONS IN ACCORDANCE WITH ASME | | A112.14.3, ASME A112.14.4, ASME A112.14.6, CSA B481.3, | | OR PDI G101 FOR HYDROMECHANICAL TYPES; OR SEC. 1003.3.7 | | FOR GRAVITY TYPES. | | D) DIMENSIONED TANK BURIAL, ANCHORING, AND BACKFILLING | | DETAILS | | E) ENLARGED PIPING DIAGRAM INCLUDING LOCATIONS AND | | SIZES OF INLETS, OUTLETS, CLEANOUTS, FLOW CONTROL | | VENTS, AND SAMPLING PORTS | | F) ACCESS LID DETAILS INDICATING THE LIDS WILL BE HEAVY | | DUTY TRAFFIC RATED AND WILL BE EQUIPPED WITH ACCESS | | RESTRICTORS. HEAVY DUTY LIDS ARE ALSO REQUIRED FOR | | CLEANOUTS, AND SAMPLING PORTS (IF INSTALLED). | | | | 3) PF1.00: PROVIDE EQUIPMENT SCHEDULES FOR THE SUMP | | PUMPS AND ENLARGED, TYPICAL PIT AND PLUMBING PIPING | | DETAILS- SEC. 712 FBC P. PLEASE NOTE THE DRAINAGE FROM | | THE PITS SHALL BE DISCHARGED INTO AN OIL INTERCEPTOR | | UNLESS THE PUMPS ARE EQUIPPED WITH AN APPROVED ALARM | | SYSTEM. THE CURRENT PLAN SHALL BE REVISED TO SHOW THE | | LOCATIONS OF THE REQUIRED INDIRECT WASTE RECEPTORS THAT | | WILL RECEIVE THE DRAINAGE FROM THE SUMP PUIMPS. | | | | 4) PF100: SUBMIT COMPLETE SANITARY DRAINAGE AND VENT | | RISER DRAWINGS THAT SHOW THE MAIN SOIL, WASTE, AND VENT | | STACKS- SEC. 107.3.5.1.3 WPB. PLEASE INCLUDE DFU | | CALCULATIONS WITH THE DRAWINGS- SEC.710.1 FBC P. PLEASE | | REVISE PF100 TO SHOW LOCATIONS OF VENT STACK | | CONNECTIONS WHERE REQUIRED- SEE SEC. 904.4 FBC P. | | | | 5) PF100: SUBMIT STORM DRAINAGE AND CONDENSATE DRAINAGE | | RISER DRAWINGS- SEC. 107.3.5.1.3 WPB. PLEASE INCLUDE | | THE GPM FLOW RATES AT AT THE ROOF DRAIN LOCATIONS, AND | | THE ACCUMULATIVE FLOW THROUGH THE BUILDING TO THE | | GROUND LEVEL MAIN HORIZONTAL STORM DRAIN PIPES- SEC. | | 1106.1, TABLES 1106.2 & 1106.3 FBC P. | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RE-SUBMITTAL FORM. | | | | CHRISTOPHER L. COLE | | MECHANICAL/PLUMBING PLANS EXAMINER | | 401 CLEMATIS STREET | | WEST PALM BEACH FL 33401 | | 561-805-6719 | | [email protected] | | |
|
|
Review Stop |
P-GREASE |
GREASE INTERCEPTOR/TRAP REVIEW |
Rev No |
1 |
Status |
N |
Date |
2022-12-22 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2022-12-22 |
Time |
14:29 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2022-12-22 |
Time |
14:29 |
Sent To |
|
|
Notes |
2022-12-22 14:30:08 | A SEPARATE PERMIT AND PLANS ARE REQUIRED FOR THE | | INTERCEPTOR. NO REVIEW UNDER THIS PERMIT. |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
4 |
Status |
P |
Date |
2023-02-06 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2023-02-06 |
Time |
09:13 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2023-02-06 |
Time |
09:13 |
Sent To |
|
|
Notes |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
3 |
Status |
F |
Date |
2023-01-19 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2023-01-19 |
Time |
12:36 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2023-01-19 |
Time |
12:36 |
Sent To |
|
|
Notes |
2023-01-19 12:36:56 | SIGNATURE REVIEW | | | | 1) GEOTECHNICAL REPORT NEEDS TO SHOW AS DIGITALLY | | SIGNED IN ADOBE READER - SIGNED AND SEALED DRAWINGS IN | | PROJECTDOX NEED TO BE DIGITALLY/ELECTRONICALLY SIGNED | | TO BE USED IN ELECTRONIC PLAN REVIEW. (A | | CERTIFICATE-BASED DIGITAL SIGNATURE (OFTEN JUST CALLED | | A DIGITAL SIGNATURE) IS A SPECIFIC TYPE OF | | E-SIGNATURE). | | | | | | | | |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
2 |
Status |
P |
Date |
2022-12-21 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-12-21 |
Time |
12:43 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-12-21 |
Time |
12:43 |
Sent To |
|
|
Notes |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
1 |
Status |
P |
Date |
2022-11-03 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-11-03 |
Time |
09:59 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-11-03 |
Time |
09:59 |
Sent To |
|
|
Notes |
|
|
Review Stop |
THRESHOLD |
THRESHOLD INSPECTOR DOCUMENTS |
Rev No |
1 |
Status |
P |
Date |
2023-01-19 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2023-01-19 |
Time |
12:37 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2023-01-19 |
Time |
12:37 |
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2022-12-06 |
|
|
Cont ID |
|
Sent By |
ckimmerl |
Date |
2022-12-06 |
Time |
12:22 |
Rev Time |
0.00 |
Received By |
ckimmerl |
Date |
2022-12-06 |
Time |
12:16 |
Sent To |
|
|
Notes |
2022-11-16 14:06:26 | SETBACKS AND FOUNDATION OKAY. | | | | | | STAFF HAS NOTED CHANGES TO ARCHITECTURAL AND SITE | | SPECIFIC DRAWINGS, WHEN PROJECT COMES IN FOR VERTICAL | | OR STRUCTURAL PERMITS, WILL HAVE TO ADDRESS CHANGES | | WITHIN AS-BUILTS OR SUBMIT FOR MINOR SITE PLAN | | AMENDMENT. |
|
|