Plan Review Details - Permit 22090503
Plan Review Stops For Permit 22090503
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2022-09-30 Cont ID  
Sent By rmcphers Date 2022-09-30 Time 13:15 Rev Time 0.00
Received By rmcphers Date 2022-09-30 Time 13:15 Sent To  
Notes
2022-11-14 11:42:30CHRIS TROOP HAS COMPLETED THE PEER REVIEW
 E MAIL COMMENTS
  
 ROGER, I HAVE COMPLETED MY REVIEW OF THE FINISHED
 CONSTRUCTION EC FOR THE SUBJECT SUBMITTAL. I HAVE TWO
 COMMENTS.
 1. THE ICC-ES REPORT FOR THE SMART VENTS SHOULD NOT BE
 ATTACHED TO THE EC. IT SHOULD BE UPLOADED AS A SEPARATE
 FILE. I RECOMMEND HAVING THEM RE-SUBMIT THE EC AND
 ICC-ES REPORT SEPARATELY.
 2. SAMANTHA HAS TOLD ME NOT TO PLACE MY BLDG. REVIEW
 STAMP ON THE EC. FEMA WANTS A CLEAN EC. (THIS WOULD BE
 AN EASY FIX IF YOU CONCUR, BUT YOU ARE THE ONLY ONE WHO
 CAN REMOVE YOUR STAMP). IF YOU REQUIRE #1 ABOVE, #2
 WOULD NOT BE APPLICABLE.
  
 REGARDS,
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2022-09-19 Cont ID  
Sent By rmcphers Date 2022-09-19 Time 14:24 Rev Time 0.00
Received By rmcphers Date 2022-09-19 Time 14:16 Sent To  
Notes
2022-09-19 14:24:28ELEVATION CERTIFICATE
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENT
  
 CORRECTIONS NEEDED -
  
 1) C2(A) = SHOULD SHOW THE STORAGE ROOM FLOOR
 ELEVATION.
  
 2) C2(B) = SHOULD SHOW THE LIVING SPACE FINISHED FLOOR
 ELEVATION.
  
 3) SECTION "D" = THE "CHECK HERE IF ATTACHMENTS" SHOULD
 BE CHECKED - FOR THE FLOOD VENT ENGINEERING APPROVAL
 DOCUMENTS.
  
 4) PLEASE PROVIDE THE FLOOD VENT PRODUCT APPROVALS OR
 ICC EVALUATION DOCUMENTS.
  
 5) PLEASE PROVIDE A FINAL SURVEY.
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-09-30 Cont ID  
Sent By rmcphers Date 2022-09-30 Time 13:15 Rev Time 0.00
Received By rmcphers Date 2022-09-29 Time 10:46 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status F Date 2022-09-19 Cont ID  
Sent By rmcphers Date 2022-09-19 Time 14:26 Rev Time 0.00
Received By rmcphers Date 2022-09-19 Time 05:39 Sent To  
Notes
***NONE***

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 1 Status P Date 2022-09-30 Cont ID  
Sent By rmcphers Date 2022-09-30 Time 13:15 Rev Time 0.00
Received By rmcphers Date 2022-09-30 Time 13:15 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-09-30 Cont ID  
Sent By rmcphers Date 2022-09-30 Time 13:15 Rev Time 0.00
Received By rmcphers Date 2022-09-30 Time 13:15 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-09-19 Cont ID  
Sent By rmcphers Date 2022-09-19 Time 14:26 Rev Time 0.00
Received By rmcphers Date 2022-09-19 Time 14:26 Sent To  
Notes
***NONE***