Plan Review Details - Permit 22061553
Plan Review Stops For Permit 22061553
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2022-09-22 Cont ID  
Sent By rmcdouga Date 2022-09-22 Time 13:33 Rev Time 0.00
Received By rmcdouga Date 2022-09-22 Time 13:23 Sent To  
Notes
2022-09-22 13:35:44PLAN
 REVIEW COMMENTS
  
 2ND REVIEW: FBC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 THE PREVIOUS COMMENTS BELOW WERE NOT ADDRESSED.
  
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
 1) FBC 107.3.5.3 - PROVIDE WIND DESIGN DATA ON THE
 PLANS PURSUANT TO FBC-R301.2.
  
 2) THE NARRATIVE LETTER SPECIFIES THE WIND SPEED AS 160
 MPH. THE VULT WIND SPEED FOR THE CITY OF WEST PALM
 BEACH IS 170 MPH. THE EXPOSURE CATEGORY FOR THIS
 PROJECT IS C WHICH IS CORRECT IN THE LETTER. PLEASE
 REVISE THE WIND SPEED TO 170 MPH. CITY OF WPB
 AMENDMENTS FBC 120.1
  
 3) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH
 OF THE REVIEW COMMENTS HAS BEEN ADDRESSED.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2022-08-17 Cont ID  
Sent By rmcdouga Date 2022-08-17 Time 15:03 Rev Time 0.00
Received By rmcdouga Date 2022-08-17 Time 14:16 Sent To  
Notes
2022-08-17 15:03:20PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) FBC 107.3.5.3 - PROVIDE WIND DESIGN DATA ON THE
 PLANS PURSUANT TO FBC-R301.2.
  
 2) THE NARRATIVE LETTER SPECIFIES THE WIND SPEED AS 160
 MPH. THE VULT WIND SPEED FOR THE CITY OF WEST PALM
 BEACH IS 170 MPH. THE EXPOSURE CATEGORY FOR THIS
 PROJECT IS C WHICH IS CORRECT IN THE LETTER. PLEASE
 REVISE THE WIND SPEED TO 170 MPH. CITY OF WPB
 AMENDMENTS FBC 120.1
  
 3) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH
 OF THE REVIEW COMMENTS HAS BEEN ADDRESSED.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2022-08-01 Cont ID  
Sent By jleahy Date 2022-08-01 Time 15:25 Rev Time 0.00
Received By jleahy Date 2022-08-01 Time 15:21 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-09-22 Cont ID  
Sent By rmcdouga Date 2022-09-22 Time 13:33 Rev Time 0.00
Received By rmcdouga Date 2022-08-21 Time 08:26 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-08-17 Cont ID  
Sent By rmcdouga Date 2022-08-17 Time 15:03 Rev Time 0.00
Received By rmcdouga Date 2022-07-15 Time 05:38 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-08-01 Cont ID  
Sent By jleahy Date 2022-08-01 Time 15:25 Rev Time 0.00
Received By jleahy Date 2022-08-01 Time 15:25 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2022-07-27 Cont ID  
Sent By vbroglia Date 2022-07-27 Time 11:16 Rev Time 0.00
Received By vbroglia Date 2022-07-27 Time 11:16 Sent To  
Notes
***NONE***