Plan Review Details - Permit 22060269
Plan Review Stops For Permit 22060269
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2023-06-02 Cont ID  
Sent By rbrown Date 2023-06-02 Time 11:12 Rev Time 0.00
Received By rbrown Date 2023-06-02 Time 11:12 Sent To  
Notes
2023-06-02 11:13:38NOTE ADDED TO FINAL INSPECTION STATING:
 BEFORE THIS ELECTRICAL PERMIT PASSES FINAL
 INSPECTION, RESTRIPE PERMIT 23050482
 MUST PASS FINAL INSPECTION TO SHOW THAT
 AN ADA SPACE HAS A CHARGING STATION. RB

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2023-04-11 Cont ID  
Sent By rbrown Date 2023-04-11 Time 19:09 Rev Time 0.00
Received By rbrown Date 2023-04-11 Time 19:09 Sent To  
Notes
2023-04-11 19:15:47ACCESSIBLE PARKING.
 PER THE COMMENT ALREADY PROVIDED UNDER THE ZONING
 REVIEW, AT LEAST ONE OF THE PROPOSED EV CHARGING POINTS
 MUST BE IN AN ACCESSIBLE PARKING SPACE. EV PARKING IS
 AN ADDITIONAL PARKING FACILITY JUST LIKE PARKING UNDER
 COVER IS AN ADDITIONAL PARKING FACILITY, AND EACH
 PARKING FACILITY SHALL OFFER ACCESSIBLE PARKING PER
 SECTION 208 OF FLORIDA ACCESSIBILITY CODE WHICH STATES
 THE FOLLOWING:
 208 PARKING SPACES
 208.2 MINIMUM NUMBER.
 PARKING SPACES COMPLYING WITH 502 SHALL BE PROVIDED IN
 ACCORDANCE WITH TABLE 208.2 EXCEPT AS REQUIRED BY
 208.2.1, 208.2.2, AND 208.2.3. WHERE MORE THAN ONE
 PARKING FACILITY IS PROVIDED ON A SITE, THE NUMBER OF
 ACCESSIBLE SPACES PROVIDED ON THE SITE SHALL BE
 CALCULATED ACCORDING TO THE NUMBER OF SPACES REQUIRED
 FOR EACH PARKING FACILITY.
  
 **QUOTE PERMIT# ON ALL CORRESPONDENCE**
  
 END OF REVIEW COMMENTS
 THE CODE REFERENCES GIVE ADDITIONAL INFO
 ROBERT BROWN
 E-MAIL: [email protected]

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2022-06-27 Cont ID  
Sent By mpeterso Date 2022-06-27 Time 12:39 Rev Time 0.00
Received By mpeterso Date 2022-06-27 Time 12:39 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2023-06-02 Cont ID  
Sent By aoliver Date 2023-06-02 Time 14:22 Rev Time 0.00
Received By aoliver Date 2023-05-15 Time 15:03 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2023-01-31 Cont ID  
Sent By lmarchan Date 2023-01-31 Time 16:47 Rev Time 0.00
Received By lmarchan Date 2022-12-17 Time 18:51 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-10-27 Cont ID  
Sent By rmcphers Date 2022-10-27 Time 11:06 Rev Time 0.00
Received By rmcphers Date 2022-09-23 Time 08:15 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-07-18 Cont ID  
Sent By lmarchan Date 2022-07-18 Time 16:30 Rev Time 0.00
Received By lmarchan Date 2022-06-07 Time 06:27 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-10-27 Cont ID  
Sent By rmcphers Date 2022-10-27 Time 11:06 Rev Time 0.00
Received By rmcphers Date 2022-10-27 Time 11:06 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-06-27 Cont ID  
Sent By mpeterso Date 2022-06-27 Time 12:40 Rev Time 0.00
Received By mpeterso Date 2022-06-27 Time 12:40 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 4 Status P Date 2023-05-15 Cont ID  
Sent By eschneid Date 2023-05-15 Time 15:02 Rev Time 0.25
Received By eschneid Date 2023-05-15 Time 15:02 Sent To  
Notes
2023-05-15 15:03:20PROVISO
  
 PRIOR TO THE FINAL ELECTRICAL (203) INSPECTION:
 A. STRIPING PERMIT 23050482 SHALL HAVE PASSED ITS FINAL
 (104) INSPECTION.
 B. LANDSCAPE PERMIT 23040273 SHALL HAVE PASSED ITS
 FINAL LANDSCAPE (502) INSPECTION FOR THE SCREENING AND
 TREE RELOCATION.
  

Review Stop Z ZONING
Rev No 3 Status F Date 2023-01-31 Cont ID  
Sent By eschneid Date 2023-01-31 Time 16:40 Rev Time 0.75
Received By eschneid Date 2023-01-31 Time 14:04 Sent To  
Notes
2023-01-31 16:41:20FAILED
  
 1) UPDATED COMMENT: THE DC CHARGEBOX IS MECHANICAL
 EQUIPMENT THAT IS REQUIRED TO BE SCREENED WITH A HEDGE
 GROWN TO THE FULL HEIGHT OF THE DC CHARGEBOX. ****
 SHEET E-3 CALLS OUT THAT THE CHARGEBOX WILL BE
 SCREENED. THE MINOR AMENDMENT LISTS THE SCREEN MATERIAL
 AS A COCOPLUM HEDGE. PRIOR TO ZONING APPROVAL OF THIS
 PERMIT, A LANDSCAPE PERMIT, SHOWING THE HEDGE
 SPECIFICATIONS MUST BE SUBMITTED. PRIOR TO THE FINAL
 INSPECTION FOR THE CHARGEBOX, THE LANDSCAPE PERMIT
 SHALL HAVE PASSED ITS FINAL INSPECTION (502).
  
 2) UPDATED COMMENT: THE GOOGLE STREET VIEW SHOWS A TREE
 IN THE LOCATION OF THE PROPOSED DC CHARGEBOX. ****
 NEITHER THIS PERMIT NOR THE LANDSCAPE PLAN INCLUDED
 WITH THE MINOR AMENDMENT PROVIDE FOR THE DISPOSITION OF
 THIS TREE.
 A. IF THE TREE IS TO REMAIN IN PLACE, IT MUST BE
 CLEARLY SHOWN ON THIS PERMIT PLAN AS WELL AS THE MINOR
 AMENDMENT LANDSCAPE PLAN.
 B. IF THE TREE IS TO BE RELOCATED, THEN THIS SHALL BE
 CLEARLY SHOWN ON THE MINOR AMENDMENT LANDSCAPE PLAN AND
 PRIOR TO ZONING APPROVAL OF THIS PERMIT, A LANDSCAPE
 PERMIT, SHOWING THE NEW TREE LOCATION MUST BE
 SUBMITTED. PRIOR TO THE FINAL INSPECTION FOR THE
 CHARGEBOX, THE LANDSCAPE PERMIT SHALL HAVE PASSED ITS
 FINAL INSPECTION (502).
  
 3) UPDATED COMMENT: THE PROPOSED EV PARKING SPACES ARE
 CUSTOMER PARKING SPACES, SO YOU ARE REQUIRED TO PROVIDE
 EV TO AT LEAST ONE ADA PARKING SPACE. **** THE
 SUBMITTED MINOR AMENDMENT SHOWS A PARKING ROW BEING
 RESTRIPED SO THAT ONE ADA PARKING SPACE HAS EV ACCESS.
 STAFF IS UNABLE TO LOCATE A PERMIT FOR THE PROPOSED
 RESTRIPING. PRIOR TO STAFF APPROVAL OF THIS PERMIT, A
 PERMIT TO RESTRIPE THE ADA PARKING SPACE LOCATION MUST
 BE SUBMITTED TO AND APPROVED BY THE CITY. PRIOR TO THE
 FINAL INSPECTION FOR THE EV CHARGERS, THE STRIPING
 PERMIT SHALL HAVE PASSED ITS FINAL INSPECTION.
  
 CONTACT ERIC SCHNEIDER @ 561-822-1446
 [email protected]
  

Review Stop Z ZONING
Rev No 2 Status F Date 2022-10-26 Cont ID  
Sent By eschneid Date 2022-10-26 Time 16:41 Rev Time 0.25
Received By eschneid Date 2022-10-26 Time 14:39 Sent To  
Notes
2022-10-26 16:43:06FAILED
  
 1) PROVIDE A SITE PLAN THAT SHOWS THE LIMITS OF WORK
 FOR THE EV CHARGERS AND DC CHARGEBOX AT A LARGER SCALE.
 THE EV CHARGERS, DC CHARGEBOX, TO INCLUDE THE PAD,
 PARKING SPACES, SIDEWALKS AND LANDSCAPE AREAS SHALL BE
 CLEARLY IDENTIFIED, INCLUDING ACCURATE DIMENSIONS.
  
 2) THE DC CHARGEBOX IS MECHANICAL EQUIPMENT IS REQUIRED
 TO BE SCREENED WITH A HEDGE GROWN TO THE FULL HEIGHT OF
 THE DC CHARGEBOX.
  
 3) THE GOOGLE STREET VIEW SHOWS A TREE IN THE LOCATION
 OF THE PROPOSED DC CHARGEBOX. YOU HAVE TWO OPTIONS:
 A. LEAVE THE TREE IN PLACE AND INSTALL THE DC CHARGEBOX
 FURTHER EAST OUTSIDE OF THE TREE'S ROOT ZONE. THIS WILL
 REQUIRE THAT A HEDGE OF SUFFICIENT MATERIAL TO SCREEN
 THE DC CHARGEBOX BE SHOWN ON THE SITE PLAN. THE HEDGE
 MATERIAL MUST BE CALLED OUT ON THE SITE PLAN.
 B. INSTALL THE DC CHARGEBOX AS SHOWN AND RELOCATE THE
 TREE TO A LOCATION NEARBY. THIS REQUIRES THE SUBMITTAL
 OF A LANDSCAPE PLAN, CREATED BY A LANDSCAPE ARCHITECT,
 SHOWING THE NEW LOCATION OR THE TREE AND THE REQUIRED
 HEDGE, AS PART OF THIS PERMIT RESUBMITTAL.
  
 4) THE PROPOSED EV PARKING SPACES ARE CUSTOMER PARKING
 SPACES, SO YOU ARE REQUIRED TO PROVIDE EV TO AT LEAST
 ONE ADA PARKING SPACE. THIS NEEDS TOO BE CLEARLY
 DESIGNATED ON THE PLANS.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446
 [email protected]
  

Review Stop Z ZONING
Rev No 1 Status F Date 2022-07-18 Cont ID  
Sent By eschneid Date 2022-07-18 Time 15:42 Rev Time 0.50
Received By eschneid Date 2022-07-18 Time 15:21 Sent To  
Notes
2022-07-18 16:15:20FAILED
  
 1) THE INSTALLATION OF THE ABOVE GROUND EV
 INFRASTRUCTURE REQUIRES CHANGES TO THE SITE AND
 LANDSCAPE PLANS. THESE CHANGES REQUIRE THE APPROVAL OF
 A MINOR PLANNED DEVELOPMENT AMENDMENT TO THE CURRENTLY
 APPROVED PLANS. PLEASE CONTACT ME FOR INFORMATION ON
 THE APPLICATION. THE MINOR PLANNED DEVELOPMENT
 AMENDMENT MUST BE APPROVED PRIOR TO THE ZONING APPROVAL
 OF THIS PERMIT.
  
 2) THE PROPOSED LOCATION OF THE EV CHARGERS, THE DC
 CHARGEBOX, THE UNDERGROUND ELECTRIC CONNECTIONS, ETC.
 DIRECTLY CONFLICT WITH EXISTING LANDSCAPE. THE PROPOSED
 INSTALLATION MUST BE OVERLAID ON THE APPROVED LANDSCAPE
 PLAN TO VERIFY THAT THERE ARE NO CONFLICTS. PLEASE NOTE
 THAT STAFF WILL NOT SUPPORT THE REMOVAL OF TREES FOR
 THE INSTALLATION OF THE EV INFRASTRUCTURE.
  
 3) THE DC CHARGEBOX IS MECHANICAL EQUIPMENT IS REQUIRED
 TO BE SCREENED.
  
 4) THE SPACES THAT ARE ADJACENT TO THE EV SPACES ARE
 CUSTOMER PARKING SPACES, TO YOU ARE REQUIRED TO PROVIDE
 EV TO AT LEAST ONE ADA PARKING SPACE.
  
 5) ADDITIONAL COMMENTS MAY BE ISSUED UPON REVIEW OF THE
 MINOR PLANNED DEVELOPMENT AMENDMENT APPLICATION.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446
 [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved