Plan Review Details - Permit 22041035
Plan Review Stops For Permit 22041035 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
F |
Date |
2022-05-26 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-05-26 |
Time |
15:20 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-05-26 |
Time |
15:20 |
Sent To |
|
|
Notes |
2022-05-26 15:23:02 | SPECIAL EVENT | | REVIEWED BY ROGER MCPHERSON | | 561-805-6716 | | [email protected] | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | AMENDMENT | | | | CORRECTIONS NEEDED - | | | | 1) PLEASE SHOW THE ACCESSIBLE ROUTE FOR THE | | RISER/PLATFORM PER FBC A 402.2 - PLEASE SHOW ANY RAMPS | | TO COMPLY WITH FBC A 405 - - FBC A 206.2.4 ADVISORY | | 206.2.4 SPACES AND ELEMENTS. ACCESSIBLE ROUTES MUST | | CONNECT ALL SPACES AND ELEMENTS REQUIRED TO BE | | ACCESSIBLE INCLUDING, BUT NOT LIMITED TO, RAISED AREAS | | AND SPEAKER PLATFORMS. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2022-05-16 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-05-16 |
Time |
13:13 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-05-16 |
Time |
13:13 |
Sent To |
|
|
Notes |
2022-05-16 13:21:35 | SPECIAL EVENT | | REVIEWED BY ROGER MCPHERSON | | 561-805-6716 | | [email protected] | | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 | | AMENDMENT | | | | CORRECTIONS NEEDED - | | | | 1) DRAWING SAYS "RISER" WHAT IS A RISER? STAGE? | | PLATFORM? PLEASE SHOW THE STAIR TO THE RISER/PLATFORM | | TO COMPLY WITH FBC 1011 - PLEASE SHOW THE ACCESSIBLE | | ROUTE FOR THE RISER/PLATFORM PER FBC A 402.2 - PLEASE | | SHOW ANY RAMPS TO COMPLY WITH FBC A 405 |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
2 |
Status |
P |
Date |
2022-05-27 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2022-05-27 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2022-05-27 |
Time |
11:33 |
Sent To |
|
|
Notes |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
1 |
Status |
F |
Date |
2022-04-20 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2022-04-20 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2022-04-20 |
Time |
14:29 |
Sent To |
|
|
Notes |
2022-04-20 14:37:15 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE | | MARSHAL, WITH THE FOLLOWING COMMENTS: | | | | | | 1) THERE IS AN INDICATION OF A RISER/PLATFORM. | | | | FOR THE OFFICIAL RECORD, PLEASE PROVIDE THE PLATFORM | | TYPE, HEIGHT, WIDTH, STAIRS, HANDRAILS, ETC. | | | | PLEASE PROVIDE DETAILS | | | | 1A) IS THERE ANY PROPOSED LIGHTING AND/OR GENERATOR | | USE? | | | | PLEASE PROVIDE DETAILS, IF ANY, AND LOCATION OF | | GENERATOR AND EXTENSION CORDS. | | | | | | | | 2) IS THERE ANY PROPOSED USE OF ANY OPEN | | FLAMES/CANDLES? | | | | PLEASE PROVIDE DETAILS. OPEN FLAMES/CANDLES NEED TO BE | | PREAPPROVED. | | | | | | 3) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET | | REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE | | ABOVE. | | | | | | 4) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE | | RE-SUBMITTAL OF THE ABOVE. | | | | | | PETER LEDUC | | FIRE MARSHAL | | 561-804-4709 | | [email protected] | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2022-05-31 |
|
|
Cont ID |
|
Sent By |
aoliver |
Date |
2022-05-31 |
Time |
08:10 |
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2022-05-26 |
Time |
08:49 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2022-05-18 |
|
|
Cont ID |
|
Sent By |
amcgrego |
Date |
2022-05-18 |
Time |
09:34 |
Rev Time |
0.00 |
Received By |
amcgrego |
Date |
2022-04-20 |
Time |
13:26 |
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2022-05-16 |
|
|
Cont ID |
|
Sent By |
ajones |
Date |
2022-05-16 |
Time |
14:27 |
Rev Time |
0.00 |
Received By |
ajones |
Date |
2022-05-16 |
Time |
14:27 |
Sent To |
|
|
Notes |
|
|
|
Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved |
 |
 |