Plan Review Details - Permit 22040039
Plan Review Stops For Permit 22040039
Review Stop ENG ENGINEERING CSD
Rev No 3 Status P Date 2022-05-09 Cont ID  
Sent By rrossano Date 2022-05-09 Time   Rev Time 0.00
Received By rrossano Date 2022-05-09 Time   Sent To I
Notes
2022-05-09 08:29:54PASSED WITH PROVISOS:
  
 AVAILABLE CITY RECORDS SHOW WATER METER IN CLOSER
 PROXIMITY TO PROPOSED DRIVEWAY THAN SHOWN ON SUBMITTED
 PLANS. DRIVEWAY SHALL NOT BE CONSTRUCTED ON TOP OF
 WATER METER. THERE ARE WATER AND SEWER LINES IN THE
 VICINITY OF THIS PROJECT. PER CHAPTER 556 OF THE
 FLORIDA STATE STATUTES, YOU MUST CALL 811 FOR UTILITY
 LOCATES AT LEAST TWO FULL BUSINESS DAYS IN ADVANCE OF
 ANY CONSTRUCTION OR DEMOLITION WORK AND CONFIRM
 LOCATION OF WATER METER.
  
  
 THANKS,
 RICK ROSSANO, SENIOR PROJECT COORDINATOR, CITY OF WPB
 ENGINEERING SERVICES DEPARTMENT
 DIRECT: (561) 494-1098, FAX: (561) 494-1116, MOBILE:
 (561) 246-9525
 EMAIL: [email protected] HTTPS://WWW.WPB.ORG/GOVERNMENT/
 ENGINEERING/ENGINEERING-STANDARDS-DETAILS
  
  

Review Stop ENG ENGINEERING CSD
Rev No 2 Status F Date 2022-04-25 Cont ID  
Sent By rrossano Date 2022-04-25 Time   Rev Time 0.00
Received By rrossano Date 2022-04-25 Time   Sent To  
Notes
2022-04-25 09:16:36PREVIOUS COMMENT:
  
 THE PAVER DRIVEWAY AGREEMENT IS A REQUIREMENT IF PAVERS
 ARE USED IN THE RIGHT OF WAY PORTION OF THE DRIVEWAY.
 THE AGREEMENT MUST BE RECORDED AT PALM BEACH COUNTY
 COURTHOUSE - RECORDING DEPT. 4.25. A RECORDED COPY OF
 THIS DOCUMENT SHOULD BE FAXED TO (561) 494-1116.
 ATTENTION: DRIVEWAY REVIEWER, AND ALSO UPLOADED WITH
 RESUBMITTAL OF DEVELOPMENT SERVICES APPLICATION FOR
 DRIVEWAY. DOCUMENT NEEDS TO BE RECORDED PRIOR TO FINAL
 SIGN OFF.
  
 FOR A PDF COPY OF THE PAVER DRIVEWAY AGREEMENT GO TO:
 HTTPS://WWW.WPB.ORG/HOME/SHOWPUBLISHEDDOCUMENT/3298/637
 523652570000000
  
  
 THANKS,
 RICK ROSSANO, SENIOR PROJECT COORDINATOR,
 CITY OF WPB ENGINEERING SERVICES DEPARTMENT
 DIRECT: (561) 494-1098, FAX: (561) 494-1116, MOBILE:
 (561) 246-9525
 EMAIL: [email protected]
 HTTPS://WWW.WPB.ORG/GOVERNMENT/ENGINEERING/ENGINEERING-
 STANDARDS-DETAILS
 CENTRAL OPERATIONS CENTER (DISPATCH):
 24-HOUR EMERGENCY RESPONSE SERVICES TO PUBLIC
 UTILITIES, PUBLIC WORKS, PARKS, ETC. 561-822-2210

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2022-04-13 Cont ID  
Sent By rrossano Date 2022-04-13 Time   Rev Time  
Received By rrossano Date 2022-04-13 Time   Sent To  
Notes
2022-04-13 11:56:39PLEASE CLEARLY SHOW RIGHT OF WAY AND DIMENSIONS OF
 PROPOSED DRIVEWAY APRON. MAXIMUM DRIVEWAY WIDTHS AT
 RIGHT OF WAY SHALL NOT EXCEED 20 FT.PLUS TWO 3 FT.
 FLARES.
  
 SHOW ANY CITY INFRASTRUCTURE ALONG PROPERTY FRONTAGE -
 WATER METER, STORM DRAIN INLETS, SANITARY CLEANOUTS.
  
 THE PAVER DRIVEWAY AGREEMENT IS A REQUIREMENT IF PAVERS
 ARE USED IN THE RIGHT OF WAY PORTION OF THE DRIVEWAY.
 THE AGREEMENT MUST BE RECORDED AT PALM BEACH COUNTY
 COURTHOUSE - RECORDING DEPT. 4.25. A RECORDED COPY OF
 THIS DOCUMENT SHOULD BE FAXED TO (561) 494-1116.
 ATTENTION: DRIVEWAY REVIEWER, AND ALSO UPLOADED WITH
 RESUBMITTAL OF DEVELOPMENT SERVICES APPLICATION FOR
 DRIVEWAY. DOCUMENT NEEDS TO BE RECORDED PRIOR TO FINAL
 SIGN OFF.
  
 FOR A PDF COPY OF THE PAVER DRIVEWAY AGREEMENT GO TO:
 HTTPS://WWW.WPB.ORG/HOME/SHOWPUBLISHEDDOCUMENT/3298/637
 523652570000000
  
  
 THANKS,
 RICK ROSSANO, SENIOR PROJECT COORDINATOR,
 CITY OF WPB ENGINEERING SERVICES DEPARTMENT
 DIRECT: (561) 494-1098, FAX: (561) 494-1116, MOBILE:
 (561) 246-9525
 EMAIL: [email protected]
 HTTPS://WWW.WPB.ORG/GOVERNMENT/ENGINEERING/ENGINEERING-
 STANDARDS-DETAILS
 CENTRAL OPERATIONS CENTER (DISPATCH):
 24-HOUR EMERGENCY RESPONSE SERVICES TO PUBLIC
 UTILITIES, PUBLIC WORKS, PARKS, ETC. 561-822-2210

Review Stop HIST HISTORICAL
Rev No 2 Status P Date 2022-04-28 Cont ID  
Sent By amhamilt Date 2022-04-28 Time 11:50 Rev Time 0.00
Received By amhamilt Date 2022-04-28 Time 11:50 Sent To  
Notes
***NONE***

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2022-04-19 Cont ID  
Sent By amhamilt Date 2022-04-19 Time 10:43 Rev Time 0.00
Received By amhamilt Date 2022-04-19 Time 10:43 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2022-05-10 Cont ID  
Sent By aoliver Date 2022-05-10 Time 07:47 Rev Time 0.00
Received By aoliver Date 2022-05-01 Time 08:07 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-04-29 Cont ID  
Sent By aoliver Date 2022-04-29 Time 09:20 Rev Time 0.00
Received By aoliver Date 2022-04-22 Time 12:30 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-04-20 Cont ID  
Sent By aoliver Date 2022-04-20 Time 08:06 Rev Time 0.00
Received By aoliver Date 2022-04-05 Time 06:36 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2022-04-27 Cont ID  
Sent By vbroglia Date 2022-04-27 Time 16:33 Rev Time 0.00
Received By vbroglia Date 2022-04-27 Time 16:33 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2022-04-07 Cont ID  
Sent By vbroglia Date 2022-04-07 Time 16:37 Rev Time 0.00
Received By vbroglia Date 2022-04-07 Time 16:37 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved