Rev No 3 Status F Date 2022-11-15 Cont ID  
Sent By sberglun Date 2022-11-15 Time 12:56 Rev Time 0.00
Received By sberglun Date 2022-11-15 Time 12:53 Sent To  
Notes
2022-11-15 12:56:171) THE PLAN VIEW OVER THE AERIAL SHOWS THE POLE TO BE
 LOCATED WITHIN THE PAVEMENT (IN THE CHEVRON SECTION).
 THE POLE NEEDS TO BE LOCATED AT A MINIMUM OF 2' FROM
 THE EDGE OF THE PAVEMENT.
 2) PLANS WILL BE RE-REVIEWED AFTER ZONING APPROVAL.
 SUZANNE BERGLUND
 [email protected]

Review Stop ENG ENGINEERING CSD
Rev No 2 Status F Date 2022-08-08 Cont ID  
Sent By sberglun Date 2022-08-08 Time 15:35 Rev Time 0.00
Received By sberglun Date 2022-08-08 Time 15:33 Sent To  
Notes
2022-08-08 15:35:071) THE CITY WILL NOT APPROVE OF A DIRECTIONAL BORE THAT
 LINES UP DIRECTLY ON TOP OF CITY INFRASTRUCTURE
 INCLUDING A STORM SEWER AND A SANITARY SEWER MANHOLE.
 PLEASE REVISE THE LOCATION OF YOUR PROPOSED ELECTRIC
 ROUTE.
 SUZANNE BERGLUND
 [email protected]

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2022-05-26 Cont ID  
Sent By   Date 2022-05-26 Time   Rev Time  
Received By   Date 2022-05-26 Time   Sent To  
Notes
2022-05-26 14:56:011) NO PATCH REPAIRS ALLOWED ON SIDEWALKS. FULL FLAG OF
 SIDEWALK MUST BE REMOVED AND REPLACED.
 2) RELOCATE HANDHOLES OUTSIDE OF SIDEWALK RAMPS.
 3) PLEASE SUBMIT COPIES OF THE CITY AS-BUILT
 INFORMATION USED TO PREPARE THESE DRAWINGS.
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2022-11-30 Cont ID  
Sent By lmarchan Date 2022-11-30 Time 08:41 Rev Time 0.00
Received By lmarchan Date 2022-09-01 Time 08:38 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-08-24 Cont ID  
Sent By aoliver Date 2022-08-24 Time 07:32 Rev Time 0.00
Received By aoliver Date 2022-06-27 Time 13:47 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-05-26 Cont ID  
Sent By aoliver Date 2022-05-26 Time 15:07 Rev Time 0.00
Received By aoliver Date 2022-01-25 Time 14:23 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 3 Status F Date 2022-11-29 Cont ID  
Sent By ckimmerl Date 2022-11-03 Time 10:41 Rev Time 0.00
Received By ckimmerl Date 2022-11-29 Time 16:06 Sent To  
Notes
2022-11-29 16:14:461. REPEAT COMMENT: POWER PULLED FROM LOCATION ALONG
 ALLEY FRONTAGE, THE BULB-OUT IS NOT PART OF THE ALLEY
 OR STREET ROW AND POWER SOURCE IS LOCATED ON PRIVATE
 PROPERTY. PLAN SHEETS AND SURVEY ALSO SUGGEST PRIVATE
 PROPERTY, PLEASE PROVIDE PROOF OF WORK BEING DONE
 WITHIN GENERAL UTILITY EASEMENT, IN ORDER TO PULL POWER
 FROM THIS LOCATION. OTHERWISE POWER MUST BE OBTAINED
 FROM ANOTHER SOURCE.
  
 CHRIS KIMMERLY, AICP
 URBAN DESIGN PLANNER
 [email protected] 822-1426
  

Review Stop Z ZONING
Rev No 2 Status F Date 2022-08-23 Cont ID  
Sent By ckimmerl Date 2022-08-23 Time 13:46 Rev Time 0.00
Received By ckimmerl Date 2022-08-23 Time 13:45 Sent To  
Notes
2022-08-23 13:46:178.23.22 REVIEW
  
 1. SATISFIED - SURVEY PROVIDED.
  
 2. POWER PULLED FROM LOCATION ALONG ALLEY FRONTAGE, THE
 BULB-OUT IS NOT PART OF THE ALLEY ROW AND POWER SOURCE
 IS LOCATED ON PRIVATE PROPERTY. PLAN SHEETS AND SURVEY
 ALSO SUGGEST PRIVATE PROPERTY, PLEASE PROVIDE OWNERS
 CONSENT OR PROVIDE PROOF OF NECESSARY EASEMENTS TO PULL
 POWER FROM THIS LOCATION. OTHERWISE POWER MUST BE
 OBTAINED FROM ANOTHER SOURCE.
  
 3. PARTIALLY SATISFIED - POLE ELEVATION SHEET INCLUDED.
 PLEASE PROVIDE PLAN SHEETS OF THE WCF POLE AS WELL AS
 ELECTRIC ROUTE.
  
 4. PLEASE PROVIDE AN 8FT. BUFFER BETWEEN THE TRUNK OF
 ANY TREES AND PALMS FROM ANY HANDHOLES, BOREPITS, AND
 EXCAVATION WORK.
  
 5. PLEASE PROVIDE LETTER OF NO RESPONSE FROM UTILITY
 PROVIDERS, SHOULD THERE BE NO RESPONSE TO PREVIOUS
 COMMUNICATIONS.
  
 CHRIS KIMMERLY, AICP
 URBAN DESIGN PLANNER
 822.1426 [email protected]

Review Stop Z ZONING
Rev No 1 Status F Date 2022-03-02 Cont ID  
Sent By ckimmerl Date 2022-03-02 Time 14:25 Rev Time 0.00
Received By ckimmerl Date 2022-03-02 Time 14:24 Sent To  
Notes
2022-03-02 14:25:251. PROVIDE A SURVEY, PREPARED BY A FLORIDA LICENSED
 SURVEYOR, WHICH SHOWS THE POLE LOCATION, UNDERGROUND
 ELECTRIC COMPONENTS (BOREPITS, HANDHOLES, & CONDUIT
 ROUTE) AND THE RIGHT-OF-WAY LINE SO THAT STAFF CAN
 VERIFY THAT THE WIRELESS COMMUNICATION FACILITY AND
 COMPONENTS ARE WITHIN THE RIGHT-OF-WAY AND NOT ON
 PRIVATE PROPERTY.
 2. PLEASE INCLUDE WIRELESS COMMUNICATION FACILITY
 (POLE) ELEVATION AND DETAILS, TO PROVIDE A REFERENCE TO
 THE PROPOSED POLE AND MAINTAIN CONSISTENCY BETWEEN PLAN
 SETS.
 3. CONDUIT DEPTH AND PATH APPEARS TO AVOID CONFLICTS
 WITH LANDSCAPING/STREET TREES AND EXISTING UTILITIES.
  
  
 CHRIS KIMMERLY @ (561)822-1426
 [email protected]
  