Plan Review Details - Permit 22010543
Plan Review Stops For Permit 22010543
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2022-05-02 Cont ID  
Sent By rmcphers Date 2022-05-02 Time 15:01 Rev Time 0.00
Received By rmcphers Date 2022-05-02 Time 15:01 Sent To  
Notes
2022-05-02 15:01:34AUDIT ONLY

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2022-05-02 Cont ID  
Sent By mpeterso Date 2022-05-02 Time 14:00 Rev Time 0.00
Received By mpeterso Date 2022-05-02 Time 14:00 Sent To  
Notes
***NONE***

Review Stop HIST HISTORICAL
Rev No 3 Status P Date 2022-04-22 Cont ID  
Sent By amhamilt Date 2022-04-22 Time 15:41 Rev Time 0.00
Received By amhamilt Date 2022-04-22 Time 15:41 Sent To  
Notes
***NONE***

Review Stop HIST HISTORICAL
Rev No 2 Status P Date 2022-03-24 Cont ID  
Sent By amhamilt Date 2022-03-24 Time 13:09 Rev Time 0.00
Received By amhamilt Date 2022-03-24 Time 13:09 Sent To  
Notes
***NONE***

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2022-02-11 Cont ID  
Sent By amhamilt Date 2022-02-11 Time 16:13 Rev Time 0.00
Received By amhamilt Date 2022-02-11 Time 16:13 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 7 Status N Date   Cont ID  
Sent By   Date 2022-05-03 Time   Rev Time 0.00
Received By lmarchan Date 2022-05-02 Time 12:04 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2022-05-02 Cont ID  
Sent By aoliver Date 2022-05-02 Time 10:56 Rev Time 0.00
Received By aoliver Date 2022-04-25 Time 15:41 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 5 Status F Date 2022-04-22 Cont ID  
Sent By shill Date 2022-04-22 Time 15:28 Rev Time 0.00
Received By shill Date 2022-03-28 Time 11:09 Sent To  
Notes
2022-04-22 15:51:57MECHANICAL PLANS, ENERGY CALCS, ETC. WERE NOT
 SUBMITTED. THIS DOES NOT MEET MINIMUM PLAN REVIEW
 CRITERIA, FBC 107.3.5.3(11) AND (14).
 MECHANICAL PLANS AND ASSOCIATED CALCULATIONS, ENERGY
 CALCS, CANNOT BE DEFERRED PER BUILDING OFFICIAL. SEE
 FBC 107.3.4.1.
  
  

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2022-04-21 Cont ID  
Sent By aoliver Date 2022-04-21 Time 11:08 Rev Time 0.00
Received By aoliver Date 2022-03-28 Time 07:18 Sent To  
Notes
2022-03-29 06:52:51NEW PRODUCT APPROVALS UPLOADED, NEEDS HISTORIC
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date   Cont ID  
Sent By   Date 2022-03-24 Time   Rev Time 0.00
Received By aoliver Date 2022-03-02 Time 07:27 Sent To  
Notes
2022-03-18 07:41:231ST ZONING REVIEW - ONLY 4 ARCH SHEETS WERE SUBMITTED,
 NO PRODUCT APPROVALS.
 THIS RESUMITTAL INCLUDES ADDITIONAL ARCH SHEETS AND
 PRODUCT APPROVALS.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-02-14 Cont ID  
Sent By jgomez Date 2022-02-14 Time 11:27 Rev Time 0.00
Received By jgomez Date 2022-01-31 Time 07:57 Sent To  
Notes
***NONE***

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 2 Status P Date 2022-05-04 Cont ID  
Sent By aoliver Date 2022-05-04 Time 11:34 Rev Time 0.00
Received By aoliver Date 2022-05-03 Time 08:19 Sent To  
Notes
2022-05-04 11:34:2205/04/22 NO IMPACT FEES DUE, SEE EMAIL UPLOADED AO
2022-05-03 08:20:065/3/22 EMAILED IMPACT FOR REVIEW AS PER SH -AO

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 1 Status F Date   Cont ID  
Sent By   Date 2022-02-15 Time   Rev Time 0.00
Received By   Date 2022-02-15 Time   Sent To  
Notes
2022-02-15 08:07:02PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE
 DIGITALLY VIA PROJECTDOX UPON NOTIFICATION BY THIS
 OFFICE. NOTIFICATION WILL OCCUR WHEN PLANS ARE NEAREST
 FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE
 OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL
 IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME
 THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM
 CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS
 TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF
  
 UPON APPROVAL AND FEE PAYMENT, PLEASE EMAIL THE RECEIPT
 TO [email protected].
  

Review Stop P PLUMBING
Rev No 1 Status P Date 2022-05-03 Cont ID  
Sent By ccole Date 2022-05-03 Time 16:32 Rev Time 0.00
Received By ccole Date 2022-05-03 Time 16:02 Sent To  
Notes
***NONE***

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 6 Status P Date   Cont ID  
Sent By   Date 2022-05-02 Time   Rev Time 0.00
Received By   Date 2022-05-02 Time   Sent To  
Notes
***NONE***

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 5 Status F Date   Cont ID  
Sent By   Date 2022-05-02 Time   Rev Time 0.00
Received By   Date 2022-05-02 Time   Sent To  
Notes
2022-05-02 10:44:29FS553.791, AN ACCURATE AFFIDAVIT IS REQUIRED PRIOR TO
 BUILDING DIVISION AUDIT.
  
 1. S.01 DATE ON AFFIDAVIT DOES NOT MATCH THE REVISION
 DATE ON PAGE UPLOADED TO PROJECTDOX.
 2. THERE ARE THREE DIFFERENT SURVEY FILES IN
 PROJECTDOX, ONE APPEARS TO BE AN OLD PAGE (SUPERSEDED
 BY A NEW DOCUMENT) AND ANOTHER APPEARS TO BE A
 DUPLICATE. THE ORIGINAL SUBMITTAL HAD THE TWO PAGE
 SURVEY UPLOADED AS TWO SEPARATE PAGES IN DRAWINGS. A
 SURVEY SENT VIA EMAIL WAS UPLOADED AND SUPERSEDED PAGE
 2 OF THE ORIGINAL SUBMITTAL. A THIRD SURVEY DOCUMENT
 WAS UPLOADED TO SUPPORTING DOCS FOLDER BY THE
 APPLICANT. PLEASE EMAIL [email protected] AND
 REQUEST THAT THE SURVEY DRAWINGS IN THE DRAWINGS FOLDER
 BE LOCKED.
 3. THE MOST RECENT SURVEY UPLOADED BY APPLICANT HAS A
 REVISION DATE OF 4/27/22, AFFIDAVIT DOES NOT INCLUDE
 REVISION 3.
  

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 4 Status P Date 2022-04-28 Cont ID  
Sent By rmcphers Date 2022-04-28 Time 13:23 Rev Time 0.00
Received By rmcphers Date 2022-04-28 Time 13:23 Sent To  
Notes
***NONE***

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 3 Status F Date   Cont ID  
Sent By   Date 2022-03-25 Time   Rev Time 0.00
Received By   Date 2022-03-25 Time   Sent To  
Notes
2022-03-25 16:20:37 
 STRUCTURAL SHEET S.01 IS DATED 2/10/22- THE AFFIDAVIT
 SHOWS DATE 2/11/2022 (APPEARS TO BE A TYPO).
 STRUCTURAL SHEETS S.02, S.03, S.04, S.O5 DATED
 11/30/2021- THE AFFIDAVIT SH0WS DATE 11/3/2021 (APPEARS
 TO BE A TYPO).
 ELECTRICAL SHEET E.01 IS DATED 2/22/22- AFFIDAVIT SHOWS
 DATE 2/11/22 (APPEARS TO BE A TYPO).
 FL17154-R4- CERTIFICATION AGENCY DOCUMENT AND
 INSTALLATION INSTRUCTIONS NOT UPLOADED.
 FL15180.1 & 15180.5 COVER SHEET NOT UPLOADED.
 NOA #20-0429.09 NOT UPLOADED.
 PLEASE NOTE THERE WERE NO MECHANICAL PLANS UPLOADED.
  
2022-03-25 09:48:04 
  
  
  

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 2 Status F Date 2022-02-14 Cont ID  
Sent By jgomez Date 2022-02-14 Time 11:21 Rev Time 0.00
Received By jgomez Date 2022-02-14 Time 11:12 Sent To  
Notes
2022-02-14 11:23:25PRIVATE PROVIDER
 SEC. 553.791 F.S.
  
 1- THERE IS NOT PRIVATE PROVIDER PLAN REVIEW COMPLIANCE
 AFFIDAVIT SUBMITTED.
  
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]
  
  

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 1 Status F Date 2022-01-28 Cont ID  
Sent By dbattles Date 2022-01-28 Time 13:36 Rev Time 0.00
Received By dbattles Date 2022-01-28 Time 13:36 Sent To  
Notes
2022-01-28 13:40:03CREDENTIALS - OK
 PRIVATE PROVIDER PLAN REVIEW AFFIDAVIT REVIEW TO BE
 DONE UPON OTHER AGENCY APPROVALS (ZONING)
  
 DYLAN BATTLES
 561-805-6718
 [email protected]
  

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status P Date 2022-05-02 Cont ID  
Sent By rmcphers Date 2022-05-02 Time 15:03 Rev Time 0.00
Received By rmcphers Date 2022-05-02 Time 15:03 Sent To  
Notes
2022-05-02 15:03:41AUDIT ONLY

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2022-05-02 Cont ID  
Sent By rmcphers Date 2022-05-02 Time 15:03 Rev Time 0.00
Received By rmcphers Date 2022-05-02 Time 15:03 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 3 Status P Date 2022-04-22 Cont ID  
Sent By fmittner Date 2022-04-22 Time 13:22 Rev Time 0.00
Received By fmittner Date 2022-04-22 Time 13:22 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 2 Status P Date 2022-03-24 Cont ID  
Sent By amhamilt Date 2022-03-24 Time 13:09 Rev Time 0.00
Received By amhamilt Date 2022-03-24 Time 13:09 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2022-02-11 Cont ID  
Sent By vbroglia Date 2022-02-11 Time 16:13 Rev Time 0.00
Received By amhamilt Date 2022-02-11 Time 16:13 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy