Plan Review Stops For Permit 21120947 |
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
3 |
Status |
F |
Date |
2022-11-15 |
|
|
Cont ID |
|
Sent By |
sberglun |
Date |
2022-11-15 |
Time |
12:44 |
Rev Time |
0.00 |
Received By |
sberglun |
Date |
2022-11-15 |
Time |
12:43 |
Sent To |
|
|
Notes |
2022-11-15 12:44:35 | 1) PLEASE ADDRESS ZONING COMMENTS. ENGINEERING WILL | | RE-REVIEW UPON RESUBMITTAL. | | SUZANNE BERGLUND | | [email protected] |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
2 |
Status |
F |
Date |
2022-06-27 |
|
|
Cont ID |
|
Sent By |
sberglun |
Date |
2022-06-27 |
Time |
14:38 |
Rev Time |
0.00 |
Received By |
sberglun |
Date |
2022-06-27 |
Time |
14:38 |
Sent To |
|
|
Notes |
2022-06-27 14:40:56 | 1) CITY UTILITIES ARE SHOWN INCORRECTLY ON PLANS. | | INCLUDE CITY UNDERGROUND UTILITIY PIPE SIZE, PIPE | | MATERIAL, AND DESCRIPTION ON THE SITE PLAN. CONTACT | | JANICE TARBILL, [email protected] FOR AS-BUILT | | INFORMATION. INCLUDE AS-BUILT INFORMATION IN YOUR | | RESUBMITTAL. | | 2) PROFILE VIEW DOES NOT ACCURATELY REFLECT CITY | | UTILITIES. | | 3) ALL ROADWAY, SIDEWALK, AND SWALE RESTORATIONS ARE | | REQUIRED PER CITY STANDARD. | | | | SUZANNE BERGLUND | | [email protected] | | 561-494-1075 | | |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
1 |
Status |
F |
Date |
2022-05-26 |
|
|
Cont ID |
|
Sent By |
sberglun |
Date |
2022-05-26 |
Time |
|
Rev Time |
0.00 |
Received By |
sberglun |
Date |
2022-05-26 |
Time |
14:28 |
Sent To |
I |
|
Notes |
2022-05-26 14:42:21 | 1) NO PATCH REPAIRS ALLOWED ON SIDEWALKS. FULL FLAG OF | | SIDEWALK MUST BE REMOVED AND REPLACED. | | 2) RELOCATE HANDHOLES OUTSIDE OF SIDEWALK RAMPS. | | 3) PLEASE SUBMIT COPIES OF THE CITY AS-BUILT | | INFORMATION USED TO PREPARE THESE DRAWINGS. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2022-11-16 |
|
|
Cont ID |
|
Sent By |
aoliver |
Date |
2022-11-16 |
Time |
10:25 |
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2022-09-15 |
Time |
06:52 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2022-08-24 |
|
|
Cont ID |
|
Sent By |
aoliver |
Date |
2022-08-24 |
Time |
07:30 |
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2022-06-14 |
Time |
15:52 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2022-05-26 |
|
|
Cont ID |
|
Sent By |
aoliver |
Date |
2022-05-26 |
Time |
15:05 |
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2021-12-20 |
Time |
12:23 |
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
3 |
Status |
F |
Date |
2022-11-03 |
|
|
Cont ID |
|
Sent By |
ckimmerl |
Date |
2022-11-03 |
Time |
10:49 |
Rev Time |
0.00 |
Received By |
ckimmerl |
Date |
2022-11-03 |
Time |
10:49 |
Sent To |
|
|
Notes |
2022-11-03 10:49:43 | 1. POWER PULLED FROM LOCATION ALONG ALLEY FRONTAGE, THE | | BULB-OUT IS NOT PART OF THE ALLEY OR STREET ROW AND | | POWER SOURCE IS LOCATED ON PRIVATE PROPERTY. PLAN | | SHEETS AND SURVEY ALSO SUGGEST PRIVATE PROPERTY, PLEASE | | PROVIDE PROOF OF WORK BEING DONE WITHIN GENERAL UTILITY | | EASEMENT, IN ORDER TO PULL POWER FROM THIS LOCATION. | | OTHERWISE POWER MUST BE OBTAINED FROM ANOTHER SOURCE. | | | | CHRIS KIMMERLY, AICP | | URBAN DESIGN PLANNER | | [email protected] 822-1426 | | |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
F |
Date |
2022-08-23 |
|
|
Cont ID |
|
Sent By |
ckimmerl |
Date |
2022-08-23 |
Time |
13:24 |
Rev Time |
0.00 |
Received By |
ckimmerl |
Date |
2022-08-23 |
Time |
13:21 |
Sent To |
|
|
Notes |
2022-08-23 13:22:43 | 8.23.22 REVIEW | | | | 1. SATISFIED - SURVEY HAS BEEN PROVIDED. | | | | 2. PARTIALLY SATISFIED - POLE ELEVATION SHEET INCLUDED. | | PLEASE PROVIDE PLAN SHEETS OF THE WCF POLE AS WELL AS | | ELECTRIC ROUTE. | | | | 3. NOT SATISFIED - PLEASE PROVIDE AN 8FT. BUFFER | | BETWEEN THE TRUNK OF ANY TREES AND PALMS FROM ANY | | HANDHOLES, BOREPITS, AND EXCAVATION WORK. PLANS SHOW AS | | LITTLE AS 5FT, RISKS IMPACT TO ROOT SYSTEM OF TREES. | | | | 4. PLEASE PROVIDE LETTER OF NO RESPONSE FROM UTILITY | | PROVIDERS, SHOULD THERE BE NO RESPONSE TO PREVIOUS | | COMMUNICATIONS. | | | | CHRIS KIMMERLY, AICP | | URBAN DESIGN PLANNER | | 822.1426 [email protected] |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
F |
Date |
2022-01-19 |
|
|
Cont ID |
|
Sent By |
ckimmerl |
Date |
2022-01-19 |
Time |
14:47 |
Rev Time |
0.00 |
Received By |
ckimmerl |
Date |
2022-01-19 |
Time |
14:43 |
Sent To |
|
|
Notes |
2022-01-19 14:43:17 | 1. PROVIDE A SURVEY, PREPARED BY A FLORIDA LICENSED | | SURVEYOR, WHICH SHOWS THE POLE LOCATION, UNDERGROUND | | CONDUIT PATH, AND THE RIGHT-OF-WAY LINE SO THAT STAFF | | CAN VERIFY THAT THE WIRELESS COMMUNICATION FACILITY AND | | UNDERGROUND ELECTRIC CONNECTIONS ARE WITHIN THE | | RIGHT-OF-WAY AND NOT ON PRIVATE PROPERTY. | | - PLEASE PROVIDE A COMPLETE SURVEY SHOWING THE FULL | | SCOPE OF WORK. | | | | 2. PROVIDE VERIFICATION THAT THE PROPOSED WIRELESS | | FACILITY (POLE) THAT THE PROPOSED POWER CONDUIT | | CONNECTS TO MEETS THE CITY OF WEST PALM BEACH | | CONCEALMENT (STEALTH), STYLE AND HEIGHT REQUIREMENTS | | LISTED IN SECTIONS 78-411(E), 78-411(F) AND 78-411(G) | | OF THE CITY CODE. PROVIDE DETAILS OF THE POLE THAT IT | | MEETS THE CITY CODE REQUIREMENTS. | | | | 3. PROVIDE VERIFICATION THAT THE PROPOSED HANDHOLE | | (PCA1173026T-9003) WILL NOT DAMAGE THE ROOT ZONE OF THE | | ADJACENT PALM TREE, WILL NOT DAMAGE THE ADJACENT FIRE | | HYDRANT, OR DECORATIVE CITY STREET LAMP. | | | | CHRIS KIMMERLY @ (561)822-1426 | | [email protected] | | |
|
|