Review Stop AD ADDRESSING
Rev No 1 Status P Date 2021-12-07 Cont ID  
Sent By cpuell Date 2021-12-07 Time 16:35 Rev Time 0.00
Received By cpuell Date 2021-12-07 Time 16:35 Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 3 Status P Date 2023-04-18 Cont ID  
Sent By sberglun Date 2023-04-18 Time 11:02 Rev Time 0.00
Received By sberglun Date 2023-04-18 Time 11:02 Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 2 Status F Date 2023-01-24 Cont ID  
Sent By sberglun Date 2023-01-24 Time 13:19 Rev Time 0.00
Received By sberglun Date 2023-01-24 Time 13:17 Sent To  
Notes
2023-01-24 13:19:351) REPEAT COMMENT FROM ZONING: POLE APPEARS TO BE
 LOCATED ON TOP OF AN EXISTING GAS MAIN. PLEASE PROVIDE
 A LETTER GRANTING APPROVAL FROM THE GAS MAIN OWNER OR
 COORDINATE THE RELOCATION OF THE GAS MAIN WITH THEM.
 2) OTHER COMMENTS REGARDING CITY UTILITES HAVE BEEN
 ADDRESSED.
 SUZANNE BERGLUND
 [email protected]
  

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2022-06-23 Cont ID  
Sent By sberglun Date 2022-06-23 Time 17:00 Rev Time 0.00
Received By sberglun Date 2022-06-23 Time 16:58 Sent To  
Notes
2022-06-23 16:59:571) CITY UTILITIES ARE SHOWN INCORRECTLY ON PLANS.
 INCLUDE CITY UNDERGROUND UTILITIY PIPE SIZE, PIPE
 MATERIAL, AND DESCRIPTION ON THE SITE PLAN. CONTACT
 JANICE TARBILL, [email protected] FOR AS-BUILT
 INFORMATION. INCLUDE AS-BUILT INFORMATION IN YOUR
 RESUBMITTAL.
 2) BORE PIT LOCATION IS ON TOP OF A CITY STORM SEWER
 PIPE BASED ON CITY UTILITY GIS INFORMATION.
 2) PROVIDE PROFILE FOR PROPOSED UNDERGROUND ELECTRIC
 SHOWING ALL CROSSING DATA FOR OTHER UTILITIES.
 3) ALL ROADWAY, SIDEWALK, AND SWALE RESTORATIONS ARE
 REQUIRED PER CITY STANDARD.
  
 SUZANNE BERGLUND
 [email protected]
 561-494-1075
  

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2023-06-02 Cont ID  
Sent By aoliver Date 2023-06-02 Time 08:17 Rev Time 0.00
Received By aoliver Date 2023-04-21 Time 09:11 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2023-04-19 Cont ID  
Sent By aoliver Date 2023-04-19 Time 07:11 Rev Time 0.00
Received By aoliver Date 2023-02-17 Time 15:27 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2023-02-03 Cont ID  
Sent By aoliver Date 2023-02-03 Time 08:52 Rev Time 0.00
Received By aoliver Date 2022-12-27 Time 09:12 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-06-24 Cont ID  
Sent By aoliver Date 2022-06-24 Time 07:40 Rev Time 0.00
Received By aoliver Date 2021-12-07 Time 13:38 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status N Date 2023-02-03 Cont ID  
Sent By aoliver Date 2023-02-03 Time 08:52 Rev Time 0.00
Received By aoliver Date   Time   Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-12-17 Cont ID  
Sent By shill Date 2021-12-17 Time 15:45 Rev Time 0.00
Received By shill Date 2021-12-17 Time 15:45 Sent To  
Notes
2021-12-17 15:45:57SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 COMMUNICATIONS APPLICATIONS - NEW PROCESS EFFECTIVE
 12/6/2021
  
 1. FOR ALL FUTURE SUBMITTALS, PRIOR TO SUBMISSION,
 CONTACT [email protected] TO OBTAIN THE CORRECT ADDRESS
 FOR YOUR APPLICATION. SHE WILL ASSIGN AN ADDRESS VIA
 EMAIL. WHEN YOU SUBMIT THE APPLICATION, INCLUDE THE
 EMAIL AS AN ATTACHMENT.
  
 2. FOR ALL FUTURE SUBMITTALS, TO SUBMIT THE
 COMMUNICATIONS APPLICATION, EMAIL THE COMPLETED
 APPLICATION TO [email protected]. THEY WILL
 GENERATE YOUR APPLICATION AND SEND YOU INSTRUCTIONS TO
 UPLOAD YOUR PLANS.
  
 3. FS471/FS481 DOCUMENTS PREPARED BY AN ARCHITECT OR
 ENGINEER AND SUBMITTED FOR PUBLIC RECORD ARE TO BE
 SIGNED, SEALED, DATED ORIGINALS. IT APPEARS THAT THE
 DOCUMENTS SUBMITTED PAPER TO THE BUILDING DIVISION WERE
 DIGITALLY SIGNED PLANS THAT WERE PRINTED.
  
 IF THIS APPLICATION FAILS REVIEW - WHEN RESUBMITTING,
 UPLOAD INDIVIDUALLY SIGNED AND SEALED DRAWINGS IF
 POSSIBLE. IF YOU CANNOT OBTAIN PLANS IN THAT FORMAT,
 UPLOAD THE SINGLE MULTIPAGE DIGITALY SIGNED PDF TO THE
 SIGNATURE FOLDER.
  
 IF THIS APPLICATION PASSES REVIEW - UPLOAD THE
 DIGITALLY SIGNED DOCUMENTS (SHOULD BE IDENTICAL TO THE
 DOCUMENTS REVIEWED) TO THE SIGNATURE FOLDER.
  
 IF THE ENGINEER DOES NOT HAVE A DIGITAL SIGNATURE,
 PLEASE CONTACT ME DIRECTLY TO DISCUSS OPTIONS.
  
  
  

Review Stop Z ZONING
Rev No 4 Status P Date 2023-06-01 Cont ID  
Sent By ckimmerl Date 2023-06-01 Time 11:48 Rev Time 0.00
Received By ckimmerl Date 2023-06-01 Time 11:48 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 3 Status F Date 2023-04-18 Cont ID  
Sent By sberglun Date 2023-04-18 Time 11:04 Rev Time 0.00
Received By sberglun Date 2023-04-18 Time 11:02 Sent To  
Notes
2023-04-18 11:03:531. REPEAT COMMENT: THIS LOCATION IS WITHIN A HISTORIC
 DISTRICT. PLEASE PROVIDE A COPY OF THE STATE HISTORIC
 PRESERVATION OFFICE APPROVAL OF THIS LOCATION.
  
 2. POLE SIZE, COLOR, AND DESIGN MEETS CITY ZONING
 STANDARDS.
  
 CHRIS KIMMERLY, AICP
 URBAN DESIGN PLANNER
 822-1426 [email protected]

Review Stop Z ZONING
Rev No 2 Status F Date 2023-02-02 Cont ID  
Sent By ckimmerl Date 2023-02-02 Time 11:03 Rev Time 0.00
Received By ckimmerl Date 2023-02-02 Time 10:48 Sent To  
Notes
2023-02-02 10:58:581. THIS LOCATION IS WITHIN A HISTORIC DISTRICT. PLEASE
 PROVIDE A COPY OF THE STATE HISTORIC PRESERVATION
 OFFICE APPROVAL OF THIS LOCATION.
  
 2. [REPEAT COMMENT] CONCRETE CAISSON, POLE, &
 UNDERGROUND ELECTRIC SHOWN ON DRAWINGS TO CONFLICT WITH
 EXISTING GAS LINES, PLEASE PROVIDE A LETTER FROM THE
 GAS MAIN OWNER GRANTING APPROVAL OF THE PROPOSED BORE
 PITS, UNDERGROUND ELECTRIC, AND POLE LOCATIONS.
  
 3. POLE SIZE, COLOR, AND DESIGN MEETS CITY ZONING
 STANDARDS.
  
 CHRIS KIMMERLY, AICP
 URBAN DESIGN PLANNER
 822-1426 [email protected]

Review Stop Z ZONING
Rev No 1 Status F Date 2022-01-04 Cont ID  
Sent By ckimmerl Date 2022-01-04 Time 09:59 Rev Time 0.00
Received By ckimmerl Date 2022-01-04 Time 09:58 Sent To  
Notes
2022-01-04 09:59:141. SITE SURVEY (B-1) IS MISSING AN ADDITIONAL OVERHEAD
 WOODEN DISTRIBUTION POLE, DIRECTLY ADJACENT TO THE POLE
 WHERE THE PROPOSED ELECTRICAL HOOKUP TAKES PLACE.
 PLEASE ADJUST SITE SURVEY AND DRAWINGS TO ACCURATELY
 REFLECT CURRENT SITE CONDITIONS.
  
 2. CONCRETE CAISSON IS SHOWN ON SURVEY TO CONFLICT WITH
 EXISTING GAS LINE, PLEASE PROVIDE THE NECESSARY PUBLIC
 UTILITY LETTER GRANTING APPROVAL OF THIS PROPOSED POLE
 LOCATION AND DEPTH.
  
 3. POLE & UNDERGROUND ELECTRIC SHOWN ON DRAWINGS TO
 CONFLICT WITH EXISTING GAS LINES, PLEASE PROVIDE THE
 NECESSARY PUBLIC UTILITY LETTERS GRANTING APPROVAL OF
 THIS PROPOSED BORE PITS, UNDERGROUND ELECTRIC, AND POLE
 LOCATIONS.
  
 4. PLEASE PROVIDE A TYPICAL CROSS-SECTION SHOWING THE
 DEPTH OF THE UNDERGROUND ELECTRICAL COMPONENTS.
  
 5. THE POLE STEALTH DESIGN MEETS CITY STANDARDS.
  