Plan Review Details - Permit 21120280
Plan Review Stops For Permit 21120280
Review Stop AD ADDRESSING
Rev No 1 Status P Date 2021-12-07 Cont ID  
Sent By cpuell Date 2021-12-07 Time 16:43 Rev Time 0.00
Received By cpuell Date 2021-12-07 Time 16:43 Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 5 Status P Date 2023-06-06 Cont ID  
Sent By sberglun Date 2023-06-06 Time 13:49 Rev Time 0.00
Received By sberglun Date 2023-06-06 Time 13:49 Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 4 Status F Date 2023-03-27 Cont ID  
Sent By sberglun Date 2023-03-27 Time 12:48 Rev Time 0.00
Received By sberglun Date 2023-03-27 Time 12:48 Sent To  
Notes
***NONE***

Review Stop ENG ENGINEERING CSD
Rev No 3 Status F Date 2022-12-30 Cont ID  
Sent By sberglun Date 2022-12-30 Time 10:45 Rev Time 0.00
Received By sberglun Date 2022-12-30 Time 10:42 Sent To  
Notes
2022-12-30 10:45:211) MILL AND RESURFACE ON 50' EACH SIDE OF TRENCH
 REQUIRED INCLUDING RESTRIPING CITY DETAIL GC-9,
 INCLUDING ALLEYWAYS.
 2) GENERAL COMMENT, SIDEWALK RESTORATION REQUIRED PER
 CITY STANDARD GC-1. ENTIRE FLAG OF SIDEWALK MUST BE
 REPLACED.
 3) HANDHOLE CAN NOT BE PLACED ON TOP OF CITY'S EXISTING
 4" WATERMAIN. THIS BORE AND UTILITY MUST BE 5' MIN
 DISTANCE FROM THE CITY WATER MAIN.
 4) POLE LOCATION APPEARS TO BE ON TOP OF AN EXISTING
 GAS MAIN. LETTER FROM FPU REQUIRED OR THE POLE MUST BE
 RELOCATED.
 SUZANNE BERGLUND
 [email protected]
  

Review Stop ENG ENGINEERING CSD
Rev No 2 Status F Date 2022-10-25 Cont ID  
Sent By sberglun Date 2022-10-25 Time 08:08 Rev Time 0.00
Received By sberglun Date 2022-10-25 Time 08:06 Sent To  
Notes
2022-10-25 08:08:011) 2' MINIMUM DISTANCE FROM FACE OF CURB TO FACE OF
 POLE.
 2) PLEASE ADDRESS ALL ZONING COMMENTS.WILL RE-REVIEW
 AFTER RESUBMITTAL.
  
 SUZANNE BERGLUND
 [email protected]
  

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2022-06-24 Cont ID  
Sent By sberglun Date 2022-06-24 Time 08:55 Rev Time 0.00
Received By sberglun Date 2022-06-24 Time 08:54 Sent To  
Notes
2022-06-24 08:55:121) CITY UTILITIES ARE SHOWN INCORRECTLY ON PLANS.
 INCLUDE CITY UNDERGROUND UTILITIY PIPE SIZE, PIPE
 MATERIAL, AND DESCRIPTION ON THE SITE PLAN. CONTACT
 JANICE TARBILL, [email protected] FOR AS-BUILT
 INFORMATION. INCLUDE AS-BUILT INFORMATION IN YOUR
 RESUBMITTAL.
 2) PROFILE PROVIDED DOES NOT ACCURATELY SHOW CITY
 UTILITIES. INCLUDE UTILITY TYPE, PIPE SIZE, PIPE
 MATERIAL AND CROSSIND DATA FOR ALL UTILITIES.
 3) ALL ROADWAY, SIDEWALK, AND SWALE RESTORATIONS ARE
 REQUIRED PER CITY STANDARD.
  
 SUZANNE BERGLUND
 [email protected]
 561-494-1075
  

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2023-06-07 Cont ID  
Sent By lmarchan Date 2023-06-07 Time 10:38 Rev Time 0.00
Received By lmarchan Date 2023-04-21 Time 09:10 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2023-04-19 Cont ID  
Sent By aoliver Date 2023-04-19 Time 07:12 Rev Time 0.00
Received By aoliver Date 2023-02-27 Time 08:59 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2023-01-27 Cont ID  
Sent By aoliver Date 2023-01-27 Time 09:14 Rev Time 0.00
Received By aoliver Date 2022-12-09 Time 08:40 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-10-26 Cont ID  
Sent By rmcphers Date 2022-10-26 Time 09:04 Rev Time 0.00
Received By rmcphers Date 2022-09-08 Time 08:08 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-06-27 Cont ID  
Sent By lmarchan Date 2022-06-27 Time 08:47 Rev Time 0.00
Received By lmarchan Date 2021-12-07 Time 11:20 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status N Date 2023-04-19 Cont ID  
Sent By aoliver Date 2023-04-19 Time 07:12 Rev Time 0.00
Received By aoliver Date 2023-04-19 Time 07:12 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status F Date 2022-10-26 Cont ID  
Sent By rmcphers Date 2022-10-26 Time 09:03 Rev Time 0.00
Received By rmcphers Date 2022-10-26 Time 09:03 Sent To  
Notes
2022-10-26 09:04:42SIGNATURE REVIEW
  
 CORRECTIONS NEEDED -
  
 1) DRAWING B-1 DOES NOT SHOW AS DIGITALLY SIGNED IN
 ADOBE READER -
  
 SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED TO BE USED IN
 ELECTRONIC PLAN REVIEW. (A CERTIFICATE-BASED DIGITAL
 SIGNATURE (OFTEN JUST CALLED A DIGITAL SIGNATURE) IS A
 SPECIFIC TYPE OF E-SIGNATURE).
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-12-17 Cont ID  
Sent By shill Date 2021-12-17 Time 17:30 Rev Time 0.00
Received By shill Date 2021-12-17 Time 17:30 Sent To  
Notes
2021-12-17 17:30:23SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 COMMUNICATIONS APPLICATIONS - NEW PROCESS EFFECTIVE
 12/6/2021
  
 1. FOR ALL FUTURE SUBMITTALS, PRIOR TO SUBMISSION,
 CONTACT [email protected] TO OBTAIN THE CORRECT ADDRESS
 FOR YOUR APPLICATION. SHE WILL ASSIGN AN ADDRESS VIA
 EMAIL. WHEN YOU SUBMIT THE APPLICATION, INCLUDE THE
 EMAIL AS AN ATTACHMENT.
  
 2. FOR ALL FUTURE SUBMITTALS, TO SUBMIT THE
 COMMUNICATIONS APPLICATION, EMAIL THE COMPLETED
 APPLICATION TO [email protected]. THEY WILL
 GENERATE YOUR APPLICATION AND SEND YOU INSTRUCTIONS TO
 UPLOAD YOUR PLANS.
  
 3. FS471/FS481 DOCUMENTS PREPARED BY AN ARCHITECT OR
 ENGINEER AND SUBMITTED FOR PUBLIC RECORD ARE TO BE
 SIGNED, SEALED, DATED ORIGINALS. IT APPEARS THAT THE
 DOCUMENTS SUBMITTED PAPER TO THE BUILDING DIVISION WERE
 DIGITALLY SIGNED PLANS THAT WERE PRINTED.
  
 IF THIS APPLICATION FAILS REVIEW - WHEN RESUBMITTING,
 UPLOAD INDIVIDUALLY SIGNED AND SEALED DRAWINGS IF
 POSSIBLE. IF YOU CANNOT OBTAIN PLANS IN THAT FORMAT,
 UPLOAD THE SINGLE MULTIPAGE DIGITALY SIGNED PDF TO THE
 SIGNATURE FOLDER.
  
 IF THIS APPLICATION PASSES REVIEW - UPLOAD THE
 DIGITALLY SIGNED DOCUMENTS (SHOULD BE IDENTICAL TO THE
 DOCUMENTS REVIEWED) TO THE SIGNATURE FOLDER.
  
 IF THE ENGINEER DOES NOT HAVE A DIGITAL SIGNATURE,
 PLEASE CONTACT ME DIRECTLY TO DISCUSS OPTIONS.
  
  
  

Review Stop Z ZONING
Rev No 5 Status P Date 2023-06-06 Cont ID  
Sent By ckimmerl Date 2023-06-06 Time 15:07 Rev Time 0.00
Received By ckimmerl Date 2023-06-06 Time 12:41 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 4 Status F Date 2023-04-18 Cont ID  
Sent By sberglun Date 2023-04-18 Time 10:39 Rev Time 0.00
Received By sberglun Date 2023-04-18 Time 10:39 Sent To  
Notes
2023-04-18 10:40:16PENDING LETTER FROM FPU.

Review Stop Z ZONING
Rev No 3 Status F Date 2023-01-26 Cont ID  
Sent By ckimmerl Date 2023-01-26 Time 10:26 Rev Time 0.00
Received By ckimmerl Date 2023-01-26 Time 10:23 Sent To  
Notes
2023-01-26 10:26:401. PROPOSED WCF POLE LOCATION, STEALTH DESIGN, COLOR,
 AND DETAILS MEET CITY ZONING STANDARDS.
  
 2. PLEASE ADDRESS ENGINEERING CONCERNS WITH LOCATION OF
 PROPOSED POLE/HANDHOLES AND UNDERGROUND ELECTRIC IN
 RELATION TO GASLINE AND WATERMAIN.
  
  
 ***FAIL IS DUE TO PENDING ENGINEERING REVIEW &
 APPROVAL. UPON ENGINEERING REVIEW & APPROVAL, ZONING
 STAFF MAY APPROVE AND ISSUE LETTER.***
  
 CHRIS KIMMERLY, AICP
 URBAN DESIGN PLANNER
 (561)822-1426 [email protected]
  

Review Stop Z ZONING
Rev No 2 Status F Date 2022-09-26 Cont ID  
Sent By ckimmerl Date 2022-09-26 Time 14:03 Rev Time 0.00
Received By ckimmerl Date 2022-09-26 Time 14:02 Sent To  
Notes
2022-09-26 14:03:271. PROPOSED POLE LOCATION SHOWN TO POTENTIALLY CONFLICT
 WITH EXISTING PRIVATE UTILITY GAS LINE, PLEASE PROVIDE
 THE NECESSARY UTILITY LETTERS GRANTING APPROVAL/NO
 OBJECTION OF THIS POLE LOCATION AND BORE DEPTH, IF NO
 RESPONSE CAN BE OBTAINED FROM UTILITY PROVIDER, PLEASE
 PROVIDE PROOF OF COMMUNICATION AND A LETTER OF NO
 RESPONSE.
  
 2. PLEASE PROVIDE SURVEY FOR ENTIRE SCOPE OF PROJECT,
 INCLUDING THE POWER ROUTE. APPEARS POWER IS BEING
 PULLED FROM A POLE WITHIN ALLEY RIGHT-OF-WAY, STAFF
 WOULD LIKE TO VERIFY THIS VIA SURVEY. IF THE POLE THAT
 THE POWER IS BEING DRAWN FROM IS WITHIN PRIVATE
 PROPERTY, PLEASE PROVIDE PROOF OF UTILITY/ACCESS
 EASEMENT ON THE SURVEY OR PROVIDE OWNER???S CONSENT.
  
 3. THE POLE STEALTH DESIGN AND COLOR MEETS CITY
 STANDARDS, PROPOSED RELOCATION GENERALLY SATISFIES
 STAFF???S PREVIOUS CONCERNS WITH CLEMATIS ST. AND
 SPECIAL EVENTS APPROVAL.
  
 CHRIS KIMMERLY, AICP
 URBAN DESIGN PLANNER
 (561)822-1426 [email protected]
  

Review Stop Z ZONING
Rev No 1 Status F Date 2022-01-13 Cont ID  
Sent By ckimmerl Date 2022-01-05 Time 14:25 Rev Time 0.00
Received By ckimmerl Date 2022-01-05 Time 14:24 Sent To  
Notes
2022-01-05 14:24:56PROPOSED POLE LOCATION IS SUBJECT TO SPECIAL EVENTS
 REVIEW. ALL COMMENTS BELOW ARE PENDING THE LOCATION
 APPROVAL FROM SPECIAL EVENTS.
  
 1. PROPOSED POWER ROUTE, BORE PIT, AND UNDERGROUND
 ELECTRICAL CONNECTION IS SHOWN TO POTENTIALLY CONFLICT
 WITH EXISTING GAS LINE, SEWER, AND WATER, PLEASE
 PROVIDE THE NECESSARY UTILITY LETTERS GRANTING APPROVAL
 OF THIS ELECTRICAL CONNECTION LOCATION AND DEPTH.
  
 2. PROPOSED BORE PITS AND HANDHOLE ARE TOO CLOSE TO
 EXISTING PALM TREES, PLEASE ADJUST TO PROVIDE THE
 NECESSARY SPACING TO PROTECT ROOT/TREE VIABILITY.
 RECOMMENDED AT LEAST 8 FT. CLEARANCE FROM PALMS TO
 SAFELY PROVIDE A BUFFER TO THE ROOT SYSTEM.
  
 3. PLEASE PROVIDE A TYPICAL CROSS-SECTION SHOWING THE
 DEPTH OF THE UNDERGROUND ELECTRICAL COMPONENTS.
  
 4. PROPOSED LOCATION IS SUBJECT TO SPECIAL EVENTS
 APPROVAL.
  
 5. THE POLE STEALTH DESIGN MEETS CITY STANDARDS.
  
 CHRIS KIMMERLY @ (561)822-1426
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved