Plan Review Details - Permit 21101362
Plan Review Stops For Permit 21101362
Review Stop AD ADDRESSING
Rev No 2 Status P Date 2021-12-20 Cont ID  
Sent By cpuell Date 2021-12-20 Time 15:26 Rev Time 0.00
Received By cpuell Date 2021-12-20 Time 15:26 Sent To  
Notes
2021-12-20 15:26:33ADDRESSES HAVE BEEN ASSIGNED FOR UNITS, WORK IS TO
 REMODEL THE WHOLE BUILDING.

Review Stop AD ADDRESSING
Rev No 1 Status F Date 2021-11-09 Cont ID  
Sent By cpuell Date 2021-11-09 Time 15:50 Rev Time 0.00
Received By cpuell Date 2021-11-09 Time 15:50 Sent To  
Notes
2021-11-09 15:52:45WORKING WITH CRAIG MONZIO ON THE READRESSING, WAITING
 TO HEAR BACK ON SUGGESTIONS.

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 2 Status P Date 2022-02-02 Cont ID  
Sent By rmcphers Date 2022-02-02 Time 11:24 Rev Time 0.00
Received By rmcphers Date 2022-02-02 Time 11:24 Sent To  
Notes
***NONE***

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status F Date 2021-12-22 Cont ID  
Sent By rmcphers Date 2021-12-22 Time 14:56 Rev Time 0.00
Received By rmcphers Date 2021-12-22 Time 14:56 Sent To  
Notes
2021-12-22 14:57:16PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED, AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY.
  
 ADDITIONAL INFORMATION REGARDING ASBESTOS REQUIREMENTS
 CAN BE FOUND ON THEIR WEBSITE:
  
 HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE
 S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2022-03-02 Cont ID  
Sent By rmcphers Date 2022-03-02 Time 13:31 Rev Time 0.00
Received By rmcphers Date 2022-03-02 Time 13:31 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2022-02-02 Cont ID  
Sent By rmcphers Date 2022-02-02 Time 11:25 Rev Time 0.00
Received By rmcphers Date 2022-02-02 Time 11:05 Sent To  
Notes
2022-02-02 11:14:28ALTERATION
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENT
  
 CORRECTIONS NEEDED -
  
 1) DRAWING A9.0.1 - PLEASE SHOW THE DOOR MANEUVERING
 SPACE NEEDED TO EXIT THE RESTROOM (ROOM 210) (18"
 BESIDE THE DOOR) FBC A 404.2.4
  
 2) PLEASE SHOW THE HOURLY FIRE RATING FOR THE PROPOSED
 SHAFT ENCLOSURES FBC 713.4
  
  
  
  
  
  
  
  
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2021-12-22 Cont ID  
Sent By rmcphers Date 2021-12-22 Time 15:46 Rev Time 0.00
Received By rmcphers Date 2021-12-22 Time 10:35 Sent To  
Notes
2021-12-22 15:46:14ALTERATION
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENT
  
 CORRECTIONS NEEDED -
  
 1) PLEASE SHOW THE OCCUPANCY LOAD FOR ALL UNITS/AREAS
 (SOME ARE THERE SOME ARE MISSING) - FBC 1004.1
  
 2) DRAWING LS.3.1 SHOWS EGRESS PATH THROUGH THE WALLS -
 PLEASE CLARIFY - FBC 1006.2
  
 3) DRAWING A1.2.2 - PLEASE SHOW THE DOOR MANEUVERING
 SPACE NEEDED TO EXIT THE RESTROOM (18" BESIDE THE DOOR)
 FBC A 404.2.4
  
 4) ACCESSIBLE RESTROOM - PLEASE SHOW THE TOILET GRAB
 BAR LOCATION DIMENSIONS FROM THE CENTER OF THE TOILET
 PER FBC A 604.5.2
  
 5) ACCESSIBLE RESTROOM - PLEASE SHOW THE MIRROR
 LOCATION DIMENSIONS FROM THE FINISHED FLOOR TO THE
 BOTTOM OF THE "REFLECTIVE SURFACE" PER FBC A 603.3
  
 6) ACCESSIBLE RESTROOMS - PLEASE SHOW THE SHOWER GRAB
 BAR SIZES AND LOCATION DIMENSIONS PER FBC 608.3
  
 7) PLEASE SHOW THAT THE DOORS THAT OPEN INTO THE
 CORRIDOR COMPLY WITH FBC 1005.7.1 DOORS.
 DOORS, WHEN FULLY OPENED, SHALL NOT REDUCE THE REQUIRED
 WIDTH BY MORE THAN 7 INCHES (178 MM). DOORS IN ANY
 POSITION SHALL NOT REDUCE THE REQUIRED WIDTH BY MORE
 THAN ONE-HALF.
  
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2022-02-08 Cont ID  
Sent By jleahy Date 2022-02-08 Time 07:50 Rev Time 0.00
Received By jleahy Date 2022-02-04 Time 16:01 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2021-12-27 Cont ID  
Sent By jleahy Date 2021-12-27 Time 11:19 Rev Time 0.00
Received By jleahy Date 2021-12-27 Time 08:40 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 3 Status P Date 2022-02-25 Cont ID  
Sent By pleduc Date 2022-02-25 Time   Rev Time 0.00
Received By pleduc Date 2022-02-25 Time 13:46 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2022-01-25 Cont ID  
Sent By pleduc Date 2022-01-25 Time   Rev Time 0.00
Received By pleduc Date 2022-01-25 Time 13:26 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2021-11-17 Cont ID  
Sent By pleduc Date 2021-11-17 Time   Rev Time 0.00
Received By pleduc Date 2021-11-12 Time 10:15 Sent To  
Notes
***NONE***

Review Stop HIST HISTORICAL
Rev No 2 Status P Date 2022-02-03 Cont ID  
Sent By fmittner Date 2022-02-03 Time 16:26 Rev Time 0.00
Received By fmittner Date 2022-02-03 Time 16:26 Sent To  
Notes
***NONE***

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2021-12-29 Cont ID  
Sent By fmittner Date 2021-12-29 Time 14:28 Rev Time 0.00
Received By fmittner Date 2021-12-29 Time 14:28 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2022-03-14 Cont ID  
Sent By mpeterso Date 2022-03-14 Time 12:54 Rev Time 0.00
Received By mpeterso Date 2022-03-11 Time 06:53 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2022-03-09 Cont ID  
Sent By lmarchan Date 2022-03-09 Time 16:22 Rev Time 0.00
Received By lmarchan Date 2022-02-24 Time 08:56 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2022-02-08 Cont ID  
Sent By jleahy Date 2022-02-08 Time 07:50 Rev Time 0.00
Received By jleahy Date 2022-01-24 Time 16:17 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2022-01-03 Cont ID  
Sent By cpuell Date 2022-01-03 Time 08:50 Rev Time 0.00
Received By cpuell Date 2021-11-01 Time 08:41 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2022-01-27 Cont ID  
Sent By medwards Date 2022-01-27 Time 16:56 Rev Time 0.00
Received By medwards Date 2022-01-27 Time 16:56 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2021-11-23 Cont ID  
Sent By medwards Date 2021-11-23 Time 15:29 Rev Time 0.00
Received By medwards Date 2021-11-23 Time 15:29 Sent To  
Notes
2021-11-23 15:30:121ST REVIEW FBC-2020 MECHANICAL
 PERMIT-21101362
  
 CODES IN EFFECT:
  
 FBC B- FLORIDA BUILDING CODE
 FBC M- FLORIDA MECHANICAL CODE
 FBC EC- FLORIDA ENERGY CONSERVATION
 FBC FG- FLORIDA FUEL GAS
 FBC EX- FLORIDA EXISTING BUILDING CODE
 FBC RES- FLORIDA RESIDENTIAL BUILDING CODE
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC
  
 PLAN REVIEW RESULTS: DENIED.
  
  
 1) PLEASE PROVIDE THE OUTDOOR AIR CALCULATIONS FOR EACH
 USE OF SPACE SERVED BY THE MECHANICAL SYSTEMS INSTALLED
 UNDER THIS PROJECT. FBC M 403.3.1.1 AND TABLE 403.3.1.1
  
 2) PLEASE SHOW THE CONDENSATE PIPING, MATERIAL AND
 TERMINATION LOCATION. FBC M 307
  
 3) PLEASE EXPLAIN THE NEED FOR THE GV-1?S FBC 107.2.1
  
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM.
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop P PLUMBING
Rev No 3 Status P Date 2022-02-28 Cont ID  
Sent By ccole Date 2022-02-28 Time 08:55 Rev Time 0.00
Received By ccole Date 2022-02-28 Time 07:49 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status F Date 2022-02-01 Cont ID  
Sent By ccole Date 2022-02-01 Time 10:36 Rev Time 0.00
Received By ccole Date 2022-01-31 Time 09:28 Sent To  
Notes
2022-02-01 10:37:022ND REVIEW FBC-2020 PLUMBING
 PERMIT- 21101362
 2/1/2022
  
 CODES IN EFFECT:
 FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020
 FBC ACC- FLORIDA ACCESSIBILITY CODE 7TH EDITION 2020
 FBC EC- FLORIDA ENERGY CONSERVATION CODE 7TH EDITION
 2020
 FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) SHEET LS.1.1, ARCH. & PLUMB. SHEETS: THE PLANS DO
 NOT SHOW THE LOCATIONS OF THE REQUIRED DRINKING
 FOUNTAINS FOR THE MERCANTILE AND ASSEMBLY OCCUPANCIES
 ON THE 1ST FLOOR. IF CLAIMING THE EXCEPTION FOR
 SUBSTITUTION UNDER SEC. 410.4 FOR THE A-2 FUTURE
 RESTAURANT, PLEASE PLACE A NOTE ON THE PLANS. THERE IS
 NO EXCEPTION FOR THE MERCANTILE OCCUPANCIES.
  
 2) A9.0.1 DETAIL B: PLEASE SHOW THE REQUIRED 36-INCH
 SHOWER OPENING MEASUREMENTS- SEC. 608.2.3 FBC ACC.
  
 3) A9.02 DETAILS 1, 8, 13, 16: SHOW THE MINIMUM 9-INCH
 HIGH TOE CLEARANCE AT THE LAV SINKS- SEC. 306.2 FBC
 ACC.
  
 4) A9.0.3 DETAIL 14: SHOW THE DRINKING FOUNTAIN SPOUT
 HEIGHTS- SECS 602.4 & 602.7 FBC ACC.
  
 5) P1.0, P5.3, & P5.4: GREASE INTERCEPTOR CALCULATIONS
 FOR HYDROSTATIC-TYPE INTERCEPTORS SHALL NOT USE THE
 NUMBER OF SEATS AS THE BASIS FOR SIZING. SIZING BY
 SEATS IS AN OUTDATED FORMULA THAT WAS PREVIOUSLY USED
 FOR GRAVITY TYPE INTERCEPTORS. SIZING FOR THE SCHIER
 INTERCEPTORS SHALL BE DETERMINED BY THE EXPECTED
 MAXIMUM FLOW IN GALLONS PER MINUTE THAT THE INTERCEPTOR
 WILL RECEIVE- SEC. 1003.3.5 FBC P. PLEASE REVISE THE
 CALCULATIONS.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2021-12-06 Cont ID  
Sent By ccole Date 2021-12-06 Time 18:08 Rev Time 0.00
Received By ccole Date 2021-12-06 Time 10:31 Sent To  
Notes
2021-12-06 18:10:091ST REVIEW FBC-2020 PLUMBING
 PERMIT- 21101362
 12/6/2021
  
 CODES IN EFFECT:
 FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020
 FBC ACC- FLORIDA ACCESSIBILITY CODE 7TH EDITION 2020
 FBC EC- FLORIDA ENERGY CONSERVATION CODE 7TH EDITION
 2020
 FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) SHEET AD2.1.1: PLEASE SUBMIT THE INTERIOR PLUMBING
 DEMOLITION PLANS FOR THE PROJECT- SECTION 107.2.1 WPB.
 THE NOTE ON THE PLAN INDICATES UNDER SEPARATE PERMIT
 HOWEVER A PLUMBING REVIEW WAS NOT PERFORMED UNDER
 PERMIT- 21080441.
  
 2) AD2.1.1- PLUMBING DEMO NOTE 1:
 A) UTILITY RELEASE - CITY OF WEST PALM BEACH WATER
 DEPARTMENT, REQUEST FOR METER PULL, ON THEIR FORM
 "DEMOLITION APPLICATION" PLEASE *FAX THE COMPLETED
 "DEMOLITION APPLICATION" FORM TO 561-822-2183.
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
 B) IF A WATER TRUCK IS DESIRED FOR WATERING DOWN SITE,
 DETAILS WILL BE REQUIRED.
 IF A HYDRANT METER OR BACKFLOW PREVENTER IS DESIRED,
 THEN A PARTIAL RELEASE WILL BE NOTED ON THEIR FORM.
 C) KEY NOTE DE27: PLEASE NOTE THAT A SEPARATE PERMIT IS
 REQUIRED FOR REMOVAL OF THE BACKFLOW PREVENTER DEVICE
 AT THE PROPERTY. REPLACEMENT OF THE BACKFLOW WILL ALSO
 REQUIRE A SEPARATE PERMIT. PLEASE PLACE NOTES ON THE
 PLAN FOR CLARIFICATION. FOR FURTHER INFORMATION ABOUT
 THE BACKFLOW PREVENTER PLEASE CONTACT THE UTILITIES
 DEPT. AT 561-822-2244.
  
 3) LS.1.1: PROVIDE PLUMBING FIXTURE CALCULATIONS FOR
 RETAIL SPACES 112 & 113 (M), AND THE FUTURE KITCHEN AND
 RESTAURANT (A2)- SEE TABLE 403.1 FBC P. PLEASE OUTLINE
 THE RESTAURANT AREA AND PROVIDE THE OCCUPANCY
 CLASSIFICATION AND OCCUPANT LOAD. PLEASE SHOW THE
 FIXTURE LOCATIONS ON THE PLANS FOR THESE TENANT SPACES.
  
 4) LS.3.1: PLEASE LABEL THE FIXTURE REQUIREMENTS AS
 THIRD FLOOR INSTEAD OF SECOND FLOOR- SECTION 107.2.1
 WPB.
  
 5) A9.0.1: DETAIL A- FBC ACC MISSING DETAILS AND
 CORRECTIONS.
 A) CLEAR FLOOR SPACE DIAGRAMS AND DIMENSIONS FOR THE
 WATER CLOSETS- SECTION 604.3.
 B) CLEAR FLOOR SPACE DIAGRAMS AND DIMENSIONS FOR THE
 LAVATORIES- 606.2.
 C) TURNING SPACE DIAMETERS- SECTION 304.3.
 D) THE DOORS SHALL NOT SWING INTO THE CLEAR FLOOR
 SPACES FOR THE LAVATORIES- 603.2.3.
  
 6) A9.0.1 DETAILS 2 & 8: PLEASE SHOW THE LENGTHS OF THE
 SIDE GRAB BARS AS DEPICTED IN FIGURE 604.5.1.
  
 7) A9.0.1 DETAILS 1 & 5: PLEASE SHOW THE LENGTHS OF THE
 REAR GRAB BARS AS DEPICTED IN FIGURE 604.5.2.
  
 8) A9.0.1 DETAILS 1 & 5: PLEASE SHOW THE HEIGHTS OF THE
 MIRRORS FROM THE FINISHED FLOORS TO THE REFLECTIVE
 SURFACES- 603.3.
  
 9) A9.0.1 DETAILS 1 & 5: PLEASE RELOCATE THE WATER
 CLOSET FLUSH CONTROLS TO THE OPEN SIDES OF THE
 FIXTURES- 604.6.
  
 10) A9.0.1: SHOW THE KNEE AND TOE CLEARANCES FOR THE
 LAVATORIES IN RR 116 & RR 117- 606.2.
  
 11) A9.0.1 DETAIL B- FBC ACC MISSING DETAILS AND
 CORRECTIONS.
 A) CLEAR FLOOR SPACE DIAGRAMS AND DIMENSIONS FOR THE
 WATER CLOSETS- SECTION 604.3.
 B) CLEAR FLOOR SPACE DIAGRAMS AND DIMENSIONS FOR THE
 LAVATORIES- 606.2.
 C) TURNING SPACE DIAMETERS- SECTION 304.3.
  
 12) A9.0.2 DETAIL A- FBC ACC MISSING DETAILS AND
 CORRECTIONS.
 A) CLEAR FLOOR SPACE DIAGRAMS AND DIMENSIONS FOR THE
 WATER CLOSETS- SECTION 604.3.
 B) CLEAR FLOOR SPACE DIAGRAMS AND DIMENSIONS FOR THE
 LAVATORIES- 606.2.
 C) TURNING SPACE DIAMETERS- SECTION 304.3.
 D) THE DOORS SHALL NOT SWING INTO THE CLEAR FLOOR
 SPACES FOR THE LAVATORIES- 603.2.3.
  
 12) A9.0.2- DETAILS 4 & 6: PLEASE SHOW THE LENGTHS OF
 THE SIDE GRAB BARS AS SPECIFIED IN FIGURE 604.5.1- FBC
 ACC.
  
 13) A9.0.2- DETAILS 3 & 5: PLEASE SHOW THE LENGTHS OF
 THE REAR GRAB BARS AS SPECIFIED IN FIGURE 604.5 FBC
 ACC.
  
 14) A9.0.2- DETAILS 1 & 5: PLEASE SHOW THE HEIGHTS OF
 THE MIRRORS FROM THE FINISHED FLOORS TO THE REFLECTIVE
 SURFACES- 603.3 FBC ACC.
  
 15) A9.02- DETAILS 6, 10, 12: SHOW THE CENTERLINES OF
 THE TOILET PAPER DISPENSERS MEASURED FROM THE FRONTS OF
 THE WATER CLOSETS- SECTION AND FIGURE 604.7 FBC ACC.
  
 16) A9.0.2- DETAILS 8, 13, & 16: SHOW THE KNEE AND TOE
 CLEARANCES FOR THE LAVATORIES- 606.2 FBC ACC.
  
 17) A9.02: PLEASE CLARIFY IF THE URINAL IS INTENDED TO
 BE ACCESSIBLE AND PROVIDE COMPLIANCE DETAILS- CLEAR
 FLOOR SPACE DIAGRAM AND DIMENSIONS, RIM HEIGHT- 605.2 &
 605.3 FBC ACC.
  
 18) A9.02 DETAIL A: THE 4'-1" LENGTH OF THE WOMEN'S
 STANDARD TOILET STALL IS NOT IN COMPLIANCE. MINIMUM 56"
 LENGTH REQUIRED FOR WALL HUNG WATER CLOSET STALLS-
 SECTION 405.3.1 FBC P.
  
 19) A9.03 DETAIL 6- PLEASE SHOW THE LENGTHS OF THE SIDE
 GRAB BARS A DEPICTED IN FIGURE 604.5.1- FBC ACC.
  
 20) A9.03 DETAIL 6: SHOW THE CENTERLINE OF THE TOILET
 PAPER DISPENSER MEASURED FROM THE FRONTS OF THE WATER
 CLOSETS- SECTION AND FIGURE 604.7 FBC ACC.
  
 21) A9.0.3- DETAILS 8, 9, & 11: SHOW THE KNEE AND TOE
 CLEARANCES FOR THE LAVATORIES- 606.2 FBC ACC.
  
 22) A10.2.1- DETAIL 1: SHOW THE DEPTH OF THE SINK
 COUNTER- 308.1 FBC ACC.
  
 23) A10.2.1- DETAIL 1: SHOW THE MAXIMUM 25 INCHES
 MAXIMUM KNEE CLEARANCE- 306.3 FBC ACC.
  
 24) A10.2.1 DETAIL 1: SHOW THE MINIMUM 11-INCH KNEE
 CLEARANCE AT 9 INCHES ABOVE THE FINISHED FLOOR, AND 8
 INCHES DEEP MINIMUM AT 27 INCHES ABOVE THE FLOOR- 306.3
 FBC ACC.
  
 25) P1.0: CIVIL DRAWINGS ARE REFERENCED IN THE KEY
 NOTES HOWEVER THE DRAWINGS WERE NOT PROVIDED- SECTION
 107.2.1 WPB.
  
 26) P1.0, P5.2, & P5.3: PLEASE IDENTIFY OR LABEL THE
 GREASE INTERCEPTORS AND SOLIDS INTERCEPTORS ON P5.2 &
 P5.3 TO CORRELATE WITH THE PLUMBING PLAN LABELS WHICH
 ARE GL-1, GL-2, SL-1, SL-2- SECTION 107.2.1 WPB.
  
 26) P1.0, P5.2 & P5.3: PLEASE PLACE A NOTE ON THE PLAN
 TO INDICATE SEPARATE PERMITS ARE REQUIRED FOR THE
 INTERCEPTORS- SECTIONS 105.1 & 107.2.1 WPB.
  
 27) P1.0 & P.5.3: THE GREASE INTERCEPTOR CALCULATIONS
 INDICATE EXISTING TENANT, HOWEVER THE PLAN SHOWS TWO
 NEW TENANT SPACES. PLEASE PROVIDE CALCULATIONS FOR EACH
 NEW TENANT SPACE. PLEASE NOTE THE SPACES ARE IDENTIFIED
 AS RETAIL 112 & 113.
  
 28) P1.0 & P.5.3: SHOW THE LOCATION OF THE SAMPLING
 PORT FOR GL-2- SECTION 1003.3.5 FBC P.
  
 29) P1.0 KEYNOTE 2: INDICATE THE MAXIMUM DEVELOPED
 LENGTH IN FEET OF THE SYSTEM- TABLE E201.1 FBC P.
  
 30) P1.0 KEYNOTE 19: PLEASE INDICATE THE DISCHARGE
 LOCATION OF THE SUMP LINE- 712.3.5 FBC P.
  
 31) P1.0 KEYNOTES 20, 21, & 22: PLEASE REFER TO COMMENT
 #1.
  
 32) P1.0: SHOW THE LOCATION OF KEYNOTE 38 ON THE PLAN-
 SECTION 107.2.1 WPB.
  
 33) P1.0 KEYNOTE 44: PLEASE PROVIDE SUPPORT AND HANGING
 DETAILS FOR INSTALLATION OF THE DRAIN PANS- SECTION
 107.2.1 WPB.
  
 34) P1.0 KEYNOTE 55: INDICATE HOW ACCESS WILL BE
 PROVIDED FOR THE BACKWATER VALVE- SECTION 714.3 FBC P.
  
 35) P1.0: PLEASE PROVIDE ENLARGED PIPING DRAWINGS FOR
 THE NEW ACCESSIBLE RESTROOMS 116 & 117- SECTION 107.2.1
 WPB.
  
 36) P2.0 KEYNOTE 22: PLEASE PROVIDE ADDITIONAL
 INFORMATION FOR THE SUMP LINE IN THE MECH CHASE. IS THE
 CHASE A FIRE-RATED SHAFT OR PLENUM ENCLOSURE? PLEASE
 NOTE THAT PVC PIPE IS COMBUSTIBLE MATERIAL AND MAY BE
 RESTRICTED FROM INSTALLATION IN THE CHASE- SECTION
 602.2.1 FBC M.
  
 37) P4.1: ROOF DRAINAGE:
 A) PLEASE PROVIDE KEYNOTES FOR THE NEW ROOF DRAINS
 (RD-1)- SECTION 107.2.1 WPB.
 B) SHOW THE GPM DRAINAGE FLOW AT EACH NEW AND EXISTING
 DRAIN LOCATION. PLEASE INCLUDE THE EXISTING VERTICAL
 LEADER PIPE SIZES- 1106.1 FBC P.
 C) SHOW THE DRAINAGE SLOPES OF THE ROOF TO THE DRAIN
 LOCATIONS- 1101.7, 1105.1 FBC P.
  
 38) P7.1: INDICATE HOW TEMPERED WATER WILL BE DELIVERED
 FROM THE LAVATORIES- SECTION 419.5 FBC P.
  
 39) P7.2 PLEASE INDICATE THE SIZE AND SLOPE OF THE
 EXISTING SANITARY WASTE PIPE AND THE TOTAL DFU?S OF THE
 SYSTEM- TABLE 710.1(1) FBC P.
  
 40) P7.2: PLEASE PROVIDE A TOTAL DFU CALCULATION THAT
 INCLUDES THE FUTURE FIXTURES ON THE 3RD FLOOR- TABLE
 710.1(1) FBC P.
  
 41) P5.2: PLEASE NOTE THAT THE WPB BUILDING DEPT. DOES
 NOT ALLOW ALL THE USE OF BARRIER-TYPE TRAP SEALS IN
 KITCHEN AREAS OR OTHER AREAS WHERE GREASE, OIL, DEBRIS
 OR OTHER SUBSTANCES ARE COLLECTED AND WHICH MAY CAUSE
 FAILURE OF THE DEVICE- SECTION 1002.4.1.3 FBC P.
  
 42) P5.1: PROVIDE EQUIPMENT SCHEDULES FOR THE NEW WATER
 HEATERS AND THERMAL EXPANSION TANKS AND SUBMIT
 MANUFACTURER'S SPECIFICATIONS AND INSTALLATION MANUALS-
 SECTION 502.1 FBC P.
  
 43) P6.1 & P6.2: PLEASE NOTE THAT MANUFACTURER'S
 SPECIFICATIONS AND INSTALLATION MANUALS FOR ALL
 PLUMBING FIXTURES, APPLIANCES, AND DEVICES SHALL BE
 ONSITE AT TIME OF INSPECTION- SECTION 107.2.1 WPB. IF
 SUBMITTALS ARE TO BE DEFERRED PLEASE PROVIDE A LIST OF
 PRODUCTS ON THE PLAN- SECTION 107.3.4.1 WPB.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  
  
  
  
  
  

Review Stop P-GREASE GREASE INTERCEPTOR/TRAP REVIEW
Rev No 2 Status N Date 2022-02-28 Cont ID  
Sent By ccole Date 2022-02-28 Time 08:55 Rev Time 0.00
Received By ccole Date 2022-02-28 Time 07:49 Sent To  
Notes
2022-02-28 08:56:18SEPARATE PERMIT REQUIRED FOR GREASE INTERCEPTOR
 INSTALLATIONS.

Review Stop P-GREASE GREASE INTERCEPTOR/TRAP REVIEW
Rev No 1 Status F Date 2022-02-01 Cont ID  
Sent By ccole Date 2022-02-01 Time 10:38 Rev Time 0.00
Received By ccole Date 2022-02-01 Time 10:37 Sent To  
Notes
2022-02-01 10:38:502ND REVIEW FBC-2020 PLUMBING
 PERMIT- 21101362
 2/1/2022
  
 CODES IN EFFECT:
 FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020
 FBC ACC- FLORIDA ACCESSIBILITY CODE 7TH EDITION 2020
 FBC EC- FLORIDA ENERGY CONSERVATION CODE 7TH EDITION
 2020
 FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC
  
 PLAN REVIEW RESULTS: DENIED.
  
 5) P1.0, P5.3, & P5.4: GREASE INTERCEPTOR CALCULATIONS
 FOR HYDROSTATIC-TYPE INTERCEPTORS SHALL NOT USE THE
 NUMBER OF SEATS AS THE BASIS FOR SIZING. SIZING BY
 SEATS IS AN OUTDATED FORMULA THAT WAS PREVIOUSLY USED
 FOR GRAVITY TYPE INTERCEPTORS. SIZING FOR THE SCHIER
 INTERCEPTORS SHALL BE DETERMINED BY THE EXPECTED
 MAXIMUM FLOW IN GALLONS PER MINUTE THAT THE INTERCEPTOR
 WILL RECEIVE- SEC. 1003.3.5 FBC P. PLEASE REVISE THE
 CALCULATIONS.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 4 Status P Date 2022-03-14 Cont ID  
Sent By mpeterso Date 2022-03-14 Time 12:54 Rev Time 0.00
Received By mpeterso Date 2022-03-14 Time 12:10 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status F Date 2022-03-02 Cont ID  
Sent By rmcphers Date 2022-03-02 Time 13:34 Rev Time 0.00
Received By rmcphers Date 2022-03-02 Time 13:34 Sent To  
Notes
2022-03-02 13:36:31SIGNATURE REVIEW
  
 CORRECTIONS NEEDED -
  
 1) DRAWINGS A9.0.3, A9.0.2, A9.0.1, A2.0.2, LS.1.1 DO
 NOT SHOW AS DIGITALLY SIGNED IN ADOBE READER -
  
 SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW. (A
 CERTIFICATE-BASED DIGITAL SIGNATURE (OFTEN JUST CALLED
 A DIGITAL SIGNATURE) IS A SPECIFIC TYPE OF
 E-SIGNATURE).- OR - IF YOUR ARCHITECT OR ENGINEER DOES
 NOT HAVE AN ELECTRONIC OR DIGITAL SIGNATURE - YOU CAN
 DROP OFF THE ORIGINAL SIGNED AND SEALED
 DRAWINGS/DOCUMENTS TO THE FRONT DESK IN THE BUILDING
 DIVISION AT THE CITY HALL.
  
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2022-02-02 Cont ID  
Sent By rmcphers Date 2022-02-02 Time 11:42 Rev Time 0.00
Received By rmcphers Date 2022-02-02 Time 11:42 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2021-12-22 Cont ID  
Sent By rmcphers Date 2021-12-22 Time 16:15 Rev Time 0.00
Received By rmcphers Date 2021-12-22 Time 16:14 Sent To  
Notes
***NONE***

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 2 Status N Date 2022-02-02 Cont ID  
Sent By rmcphers Date 2022-02-02 Time 11:24 Rev Time 0.00
Received By rmcphers Date 2022-02-02 Time 11:24 Sent To  
Notes
***NONE***

Review Stop THRESHOLD THRESHOLD INSPECTOR DOCUMENTS
Rev No 1 Status F Date 2021-12-22 Cont ID  
Sent By rmcphers Date 2021-12-22 Time 14:59 Rev Time 0.00
Received By rmcphers Date 2021-12-22 Time 14:59 Sent To  
Notes
2021-12-22 15:01:47THRESHOLD BUILDING
  
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 NOTE: THIS STRUCTURE IS CONSIDERED A THRESHOLD BUILDING
 PER FS 553.71 12) "THRESHOLD BUILDING" MEANS ANY
 BUILDING WHICH IS GREATER THAN THREE STORIES OR 50 FEET
 IN HEIGHT, OR WHICH HAS AN ASSEMBLY OCCUPANCY
 CLASSIFICATION AS DEFINED IN THE FLORIDA BUILDING CODE
 WHICH EXCEEDS 5,000 SQUARE FEET IN AREA AND AN OCCUPANT
 CONTENT OF GREATER THAN 500 PERSONS.
  
 PLEASE READ AND FILL OUT THE REQUIRED DOCUMENTS PER THE
 "GUIDELINES AND POLICIES FOR PROJECTS CONCERNING
 THRESHOLD/SPECIAL INSPECTORS AND RESIDENT INSPECTORS".
 YOU CAN E MAIL ME AND ASK FOR A COPY.
  
 1) ANY REPAIRS TO THRESHOLD BUILDINGS ARE REQUIRED TO
 COMPLY WITH FS 553.79. THRESHOLD BLDG. REQUIRED
 STATEMENT: W.P.B. AMENDMENT 110.8.4.4 ALL PLANS FOR THE
 BUILDING WHICH ARE REQUIRED TO BE SIGNED AND SEALED BY
 THE ARCHITECT OR ENGINEER OF RECORD CONTAIN A STATEMENT
 THAT, TO THE BEST OF THE ARCHITECT'S OR ENGINEER'S
 KNOWLEDGE, THE PLANS AND SPECIFICATIONS COMPLY WITH THE
 APPLICABLE MINIMUM BUILDING CODES AND THE APPLICABLE
 FIRE-SAFETY STANDARDS AS DETERMINED BY THE LOCAL
 AUTHORITY IN ACCORDANCE WITH THIS SECTION AND CHAPTER
 633 FLORIDA STATUTES.
  
 A) FBC (CITY AMENDMENTS)110.8.1 THRESHOLD INSPECTION
 PLAN. THE ENFORCING AGENCY SHALL REQUIRE A SPECIAL
 INSPECTOR TO PERFORM STRUCTURAL INSPECTIONS ON A
 THRESHOLD BUILDING PURSUANT TO A STRUCTURAL INSPECTION
 PLAN PREPARED BY THE ENGINEER OF RECORD. THE STRUCTURAL
 INSPECTION PLAN MUST BE SUBMITTED TO THE ENFORCING
 AGENCY PRIOR TO THE ISSUANCE OF A BUILDING PERMIT FOR
 THE CONSTRUCTION OF A THRESHOLD BUILDING. THE PURPOSE
 OF THE STRUCTURAL INSPECTION PLAN IS TO PROVIDE
 SPECIFIC INSPECTION PROCEDURES AND SCHEDULES SO THAT
 THE BUILDING CAN BE ADEQUATELY INSPECTED FOR COMPLIANCE
 WITH THE PERMITTED DOCUMENTS.
  
 B) THRESHOLD INSPECTOR: WPB AMENDMENT 110.8.1 W.P.B.
 CONSTRUCTION SERVICES DEPARTMENT REQUEST FOR THRESHOLD
 BUILDINGS A SPECIAL INSPECTOR AS REQUIRED BY 553.79(5)
 FLORIDA STATUTES TO THE MINIMUM INSPECTIONS REQUIRED BY
 THIS CODE. THE THRESHOLD INSPECTION FORMS ARE REQUIRED
 TO BE FILED OUT BY ALL PARTIES WITH INTEREST, NOTARIZED
 AND RETURNED TO THIS OFFICE, AND REVIEWED AND APPROVED
 BEFORE PERMIT ISSUANCE WILL TAKE PLACE.
  
 C) THRESHOLD BLDG. REQUIRED STATEMENT: W.P.B. AMENDMENT
 110.8.4.4 ALL PLANS FOR THE BUILDING WHICH ARE REQUIRED
 TO BE SIGNED AND SEALED BY THE ARCHITECT OR ENGINEER OF
 RECORD SHALL CONTAIN A STATEMENT THAT, TO THE BEST OF
 THE ARCHITECT'S OR ENGINEER'S KNOWLEDGE, THE PLANS AND
 SPECIFICATIONS COMPLY WITH THE APPLICABLE MINIMUM
 BUILDING CODES AND THE APPLICABLE FIRE-SAFETY STANDARDS
 AS DETERMINED BY THE LOCAL AUTHORITY IN ACCORDANCE WITH
 THIS SECTION AND CHAPTER 633 FLORIDA STATUTES.
  
 D) FOR THE SPECIAL INSPECTOR PLEASE PROVIDE A RESUME OF
 INSPECTION EXPERIENCE ON PREVIOUS PROJECT. THE RESUME
 MUST BE ACCOMPANIED BY ALL CERTIFICATES AS SPECIFIED
 HEREIN. THE BUILDING OFFICIAL OR HIS DESIGNEE WILL
 REVIEW THE RESUME. AFTER THE RESUME IS REVIEWED, AN
 INTERVIEW WILL BE SCHEDULED. UNDER NO CIRCUMSTANCES
 WILL AN INSPECTOR BE INTERVIEWED FOR WORK WITHOUT FIRST
 MEETING THE ABOVE CRITERIA.
  
 E) THE CONTRACTOR WILL PRODUCE A JOB SUMMARY OR HISTORY
 FOR THIS TYPE OF CONSTRUCTION.
  
 F) 110.8.4.3 ALL SHORING AND RESHORING PROCEDURES,
 PLANS AND DETAILS SHALL BE SUBMITTED TO THE ENFORCEMENT
 AGENCY FOR RECORDKEEPING. EACH SHORING AND RESHORING
 INSTALLATION SHALL BE SUPERVISED, INSPECTED AND
 CERTIFIED TO BE IN COMPLIANCE WITH THE SHORING
 DOCUMENTS BY THE CONTRACTOR.
  

Review Stop Z ZONING
Rev No 3 Status P Date 2022-03-09 Cont ID  
Sent By ckimmerl Date 2022-03-09 Time 09:23 Rev Time 0.00
Received By ckimmerl Date 2022-03-09 Time 09:23 Sent To  
Notes
2022-03-09 09:23:24PROVISO: APPROPRIATE ROOFTOP MECHANICAL EQUIPMENT
 SCREENING SHALL BE COORDINATED WITH PLANNING
 DEPARTMENT.

Review Stop Z ZONING
Rev No 2 Status F Date 2022-02-02 Cont ID  
Sent By ckimmerl Date 2022-02-02 Time 15:53 Rev Time 0.00
Received By ckimmerl Date 2022-02-02 Time 15:50 Sent To  
Notes
2022-02-02 15:52:501. PLEASE PROVIDE ADDITIONAL INFORMATION AND DETAILS
 SHOWING THE HEIGHT OF THE PROPOSED NEW ROOFTOP
 MECHANICAL EQUIPMENT. FURTHER DISCUSSION IS NEEDED ON
 POSSIBLE SCREENING OPTIONS.

Review Stop Z ZONING
Rev No 1 Status F Date 2021-12-21 Cont ID  
Sent By llouie Date 2021-12-21 Time 09:10 Rev Time 0.00
Received By ckimmerl Date 2021-12-21 Time 09:10 Sent To  
Notes
2021-12-21 09:10:15SEC.94-109 - PROJECTION VERTICAL:
 MECHANICAL EQUIPMENT AND APPURTENANCES NECESSARY TO THE
 OPERATION OR MAINTENANCE OF THE BUILDING OR STRUCTURE
 ITSELF SUCH AS, BUT NOT LIMITED TO, COOLING TOWERS,
 ELEVATORS, STAIRS AND MECHANICAL PENTHOUSES, VENT
 STACKS AND ANTENNAS SHALL BE ENCLOSED AND SCREENED IN
 SUCH A MANNER THAT THE ENCLOSURE IS DESIGNED AS AN
 INTEGRAL PART OF THE OVERALL BUILDING DESIGN.
  
 - ALL ROOFTOP MOUNTED EQUIPMENT SHALL BE SCREENED FROM
 VIEW WITH A SCREEN EQUAL TO THE HEIGHT OF THE
 EQUIPMENT.